Hanover Insurance v. Atlantis Drywall & Framing LLC

611 F. App'x 585
CourtCourt of Appeals for the Eleventh Circuit
DecidedMay 26, 2015
Docket13-14482
StatusUnpublished
Cited by7 cases

This text of 611 F. App'x 585 (Hanover Insurance v. Atlantis Drywall & Framing LLC) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hanover Insurance v. Atlantis Drywall & Framing LLC, 611 F. App'x 585 (11th Cir. 2015).

Opinion

PER CURIAM:

This is an interlocutory appeal from an order denying a motion to compel arbitration. For the following reasons, we affirm the district court’s order.

I.

In the summer of 2010, the University of Alabama approved a project to construct a new student-housing complex on the' University’s main campus in Tuscaloosa, Alabama. The University retained Brice Building Company, LLC (“Brice”), as the general contractor. On March 8, 2011, Brice retained Atlantis Drywall and Framing, LLC (“Atlantis”), through a subcontract agreement (“Subcontract”) to install drywall. The Subcontract contained the following arbitration provision:

Paragraph CC. The parties acknowledge and agree that this Subcontract and the subject matter hereof is substantially connected with and involved with interstate commerce. In the event of a dis-putéis), claim(s) or other matter(s) in question of any kind whatsoever between the parties (i) arising out of or related or collateral to the provisions and/or subject matter of this Subcontract or the breach thereof, or independent from the Subcontract or (ii) relating to any transaction or occurrence of any kind between the parties to this Subcontract or their officers, directors, agents and/or employees, it is agreed that the parties to this Subcontract will attempt to resolve such dispute(s), claim(s), or other matter(s) in. question amicably by informal discussions and negotiations within a seven (7)-day period. Notwithstanding any conflicting or contrary provisions contained within the General Contract nor any provisions in this Subcontract that incorporates herein the terms and conditions of the General Contract by reference, all dispute^), claim(s) and other matter(s) in question which cannot be settled by negotiation among the parties within such time shall at the election of, the Contractor (but not otherwise), be submitted by the parties to arbitration under the Construction Industry Arbitration Rules of the American Arbitration Association except as such rules may be modified or restricted by any provision of this Subcontract. The parties intend that the scope of this arbitration clause shall be construed as broadly as possible so as to include, but not be limited to, the enforceability of this arbitration provision, the arbitrability of a particular claim or dispute, as well as any claims of misrepresentation, concealment of material facts, or fraud among the parties whether occurring before or after the execution of this agreement.
Notice of demand by Contractor for arbitration shall be filed in writing with the other party or parties to this Subcontract and with the American Arbitration Association and shall be made within a reasonable time after the dispute, *587 claim or other matter in question has arisen but in no event shall be made after the date when institution of legal or equitable proceedings based on such dispute, claim or other matter in question would be barred by the applicable statute of limitations.... The Subcontractor agrees that any arbitration instituted under this paragraph shall, at Contractor’s election, be consolidated with any other arbitration proceeding involving a common question of fact or law between the Contractor, the Owner, the Architect/Engineer or any of their agents, consultants or other representatives, and/or any other subcontractor(s) of 'any tier performing work in connection with the Project.

Because this was a' public-works project, both Brice and Atlantis were statutorily obligated to obtain performance and payment bonds. See Ala.Code § 39-1-1. Atlantis sought to obtain these bonds from The Hanover Insurance Company (“Hanover”). As Hanover was not willing to assume the sole risk that any failure or default by Atlantis might result in a loss to it, Hanover required indemnification by Atlantis and its principals: Bay Meadows Consulting, LLC, (“Bay Meadows”), Marilourdes Deyo (“Deyo”), Laurence Lamphere and Christin Lamphere (the “Lampheres”) (Atlantis’s principals are collectively referred to as “Indemni-tors”). On May 19, 2011, Hanover and the Indemnitors executed such an agreement (“Indemnity Agreement”). The Indemnity Agreement did not contain an arbitration provision. In relevant part, the Indemnity Agreement provided,

The Hanover Insurance Company ... has executed, or may in its discretion hereafter execute certain surety contracts, undertakings, and/or other instruments of guarantee of indemnity....

Pursuant to this provision, on June 30, 2011, Hanover executed the statutorily required performance and payment bonds (the “Bonds”), which provided that Hanover would perform Atlantis’s responsibilities under the Subcontract if Atlantis defaulted on its obligations. The Bonds specifically and expressly incorporated the Subcontract, stating in relevant part,

WHEREAS, Principal [Atlantis] has by written agreement dated 3/8/11 entered into a subcontract with Obligee [Brice] for UA North Bluff Residential Community (600-10-1090), Drywall, Metal, Framing, Acoustical Ceilings ... which subcontract is by reference made a part hereof, and is hereinafter referred to as the subcontract.

To summarize, Atlantis was a party to all three agreements (the Subcontract, the Indemnity Agreement, and the Bonds). Hanover was a party to the Indemnity Agreement and the Bonds, and Brice was a party to the Subcontract and the Bonds. But the Indemnitors were parties to the Indemnity Agreement only.

Atlantis later defaulted on the Subcontract. Accordingly, Hanover made payments under the Bonds and then sought indemnification pursuant to the Indemnity Agreement. Atlantis and the Indemnitors failed to comply with Hanover’s request, so Hanover filed a complaint against Atlantis and the Indemnitors 1 in the United States District Court of the Northern District of Alabama seeking indemnification, exoneration and quia timet, specific performance, and damages for breach of contract. Atlantis, the Lampheres, Bay Meadows, and *588 Deyo each moved to compel arbitration under the Federal Arbitration Act and to stay judicial proceedings, and in the alternative, to dismiss, principally arguing that the Indemnity Agreement incorporated the Subcontract, and therefore its arbitration clause.

The district court denied the Lam-pheres’ motion on September 4, 2018, and two weeks later, on September 18, 2018, denied both Bay Meadows’s and Deyo’s motions. On September 26, 2013, the In-demnitors timely filed a notice of interlocutory appeal pursuant to 9 U.S.C. § 16(a). 2

On August 29, 2014, a panel of this Court vacated the district court’s order and remanded the case with instructions to order arbitration. Hanover then petitioned for rehearing. With leave, the Surety & Fidelity Association of America filed an amicus curiae brief in support of Hanover’s petition. On October 29, 2014, the Court vacated its previous panel opinion and granted rehearing. Thereafter, Hanover settled with Bay Meadows and the Lampheres.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
611 F. App'x 585, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hanover-insurance-v-atlantis-drywall-framing-llc-ca11-2015.