Hannah v. Fife

27 Mich. 172, 1873 Mich. LEXIS 87
CourtMichigan Supreme Court
DecidedApril 29, 1873
StatusPublished
Cited by14 cases

This text of 27 Mich. 172 (Hannah v. Fife) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hannah v. Fife, 27 Mich. 172, 1873 Mich. LEXIS 87 (Mich. 1873).

Opinion

Christiancy, Ch. J.

This was an action of assumpsit brought by Fife and Haviland in the circuit court for the county of Grand ■ Traverse against the plaintiffs in error, as the sureties of one Oscar L. Noble, in a contract between said Noble and Fife and Haviland, by which Noble agreed to enter into and perform a contract with the state for the construction of a swamp-land state road, for the bnilding of which said Fife and Haviland had been the lowest bidders, and to give them as a bonus for being allowed to take their place in the contract, eight sections of the swamp lands to be received from the state for the performance of the work.

A copy of the contract is given below.

The evidence in the case tends to show the following state of facts:

JDewitt 0. Leach, in April, 1868, being the local commissioner of the road in question, whose business it was, on behalf of the state, to let the contract for the building of the road to the lowest responsible bidder, subject to the approval of the general swamp-land state road commissioners, and having given due notice of the time and place of letting the contract, proceeded, in accordance with said notice, on the 9th day of April, 1868, to open the bids, which had been received, two bids only having been put in for the whole work advertised to be let, one of which was by said Oscar L. Noble and the other by Fife and Haviland. And upon opening the bids in the presence of all these parties, it was found that Noble’s bid was for a road-bed to be graded only sixteen feet wide, which was not in accord[174]*174anee with the plan adopted by the state authorities or with the notice, which required such road-bed to be twenty feet wide; but he proposed to complete the work by the first day of December then next, while the bid of Fife and Haviland was for a road-bed twenty feet wide, according to the plan and notice, but proposed the completion of the work only by the 7th day of April, 1869. Each of the bids was for two sections of land to the mile, which was the maximum quantity allowed by law for the work. — Laws of 1863, pp. 322-323; Laws of 1867, Vol. 2, p. 854. The commissioner, therefore, on reading the bids aloud in the hearing of the parties, said to them that it was manifest from the reading of the bids, to whom the job must go, meaning to Fife and Haviland, and all the parties so understanding him. And the commissioner was about to award the contract to them, and would have done so at once; but Noble, in that stage of the transaction, requested the commissioner not to take any further steps in the matter until he and Fife and Haviland should have an opportunity to consult together; and thereupon Noble and Fife and Haviland left the room, and returning in a few minutes, all joined in a request that matters should remain as they were until they could have more time to consult. The matter then remained open until the 11th day of April; and during this time there was considerable consultation between the parties, and they separately conferred with the commissioner. The result was that Noble and Fife and Haviland, having entered into the agreement upon which this suit is brought,, on the 11th of April the contract with the state for building the road was, by the commissioner, with the assent and approval of Fife and Haviland, made directly with Noble, •instead of Fife and Haviland, to whom it would otherwise have been awarded. But the commissioner made this contract with Noble substantially upon the terms of the bid of Fife and Haviland, though upon somewhat more favorable terms to the state, as it provided for the completion of the work by December 1st, 1868, instead of April 7th,. 1869, [175]*175which that bid proposed. The contract with Noble being executed by the local commissioner was delivered to Noble with the bids, to be taken to Lansing, but the local commissioner made no report to the state commissioner, of the facts in the case or the substitution of Noble in place of Fife and Haviland, nor does it appear that he was ever notified of it. The contract of Noble was approved by the state commissioner; and the better to appreciate the nature of the contract of Noble with Fife and Haviland, upon which this suit is brought, it is proper to say that the substance of Noble’s contract with the state was for the building of this road (59 miles and 25 chains) in the particular manner therein specified, to be completed by the first day of December, 1868; upon the completion and acceptance of which, and a certificate by the proper authorities, Noble was to receive in full compensation for the work, a grant by patent from the state, of one thousand two hundred and eighty acres (two sections) of swamp lands per mile; one-half to be taken from the counties in which the road ran, in proportion to its length in each county, and the other half from any unsold state swamp lands in the lower peninsula applicable to the construction of this road at the time of selection. And this contract was expressly made subject to the approval of the swamp-land state road commissioner.

Such was the substance of Noble’s contract with the state, and such the circumstauces under which that contract was made, as well as the contract of Noble with the plaintiffs below, in which the defendants below were Noble’s sureties. This contract is in the following words: “An agreement made this 11th day of April, A. D. 1868, by and between W. H. Fife and Joseph B. Haviland, of Grand Traverse county, state of Michigan, parties of the first part, and Oscar L. Noble, of Antrim county, state aforesaid, of the second part, and Perry Hannah and Henry H. Noble as sureties for the performance of this contract on the part of Oscar L. Noble, party of the second part, to wit:

“W. H. Fife and Joseph B. Haviland this day agree to [176]*176allow D. 0. Leach, local commissioner on the north division of the Midland City and Traverse Bay state swamp-land road, to make out and execute a contract with Oscar L. Noble, for the building of the north division of the Midland City and Traverse Bay state road, which was awarded to said Fife and Haviland at the declaring of said bid by the said local commissioner, on the 9 th day of April, A. D. 1868. In consideration of the said Fife and Haviland agreeing to the above, the said Oscar L. Noble agrees on his part to execute a contract according to the printed forms of the state road commissioner, with the local commissioner, for the building of the north division of the Midland City and Grand Traverse Bay state swamp-land road, to be completed by the 1st day of December next, for the same pay in state swamp lands from the state of Michigan that is contained in the bid of Fife and Haviland.

“And the said Osear L.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J J Zayti Trucking, Inc. v. City of Detroit
359 N.W.2d 201 (Michigan Court of Appeals, 1984)
City of Roseville v. LOCAL 1614, INTERN. ASS'N OF FIREFIGHTERS, AFL-CIO
220 N.W.2d 147 (Michigan Court of Appeals, 1974)
Mahoney v. Lincoln Brick Co.
8 N.W.2d 883 (Michigan Supreme Court, 1943)
Hardison v. . Reel
70 S.E. 463 (Supreme Court of North Carolina, 1911)
Baars v. Township of Laketon
129 N.W. 7 (Michigan Supreme Court, 1910)
Conway v. Garden City Paving & Post Co.
60 N.E. 82 (Illinois Supreme Court, 1901)
United States v. Addyston Pipe & Steel Co.
85 F. 271 (Sixth Circuit, 1898)
Hoffman v. McMullen
83 F. 372 (Ninth Circuit, 1897)
McMullan v. Hoffman
69 F. 509 (U.S. Circuit Court for the District of Oregon, 1895)
Richardson v. Buhl
6 L.R.A. 457 (Michigan Supreme Court, 1889)
Hunter v. Pfeiffer
9 N.E. 124 (Indiana Supreme Court, 1886)
Beard v. DeGoit
58 Mich. 245 (Michigan Supreme Court, 1885)
Horn v. Star Foundry Co.
23 W. Va. 522 (West Virginia Supreme Court, 1884)

Cite This Page — Counsel Stack

Bluebook (online)
27 Mich. 172, 1873 Mich. LEXIS 87, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hannah-v-fife-mich-1873.