Hambly v. Delaware, M. & V. R.

21 F. 541, 1884 U.S. App. LEXIS 2414
CourtUnited States Circuit Court
DecidedJuly 21, 1884
StatusPublished
Cited by2 cases

This text of 21 F. 541 (Hambly v. Delaware, M. & V. R.) is published on Counsel Stack Legal Research, covering United States Circuit Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hambly v. Delaware, M. & V. R., 21 F. 541, 1884 U.S. App. LEXIS 2414 (uscirct 1884).

Opinions

Bradley, Justice.

This is an action of covenant, brought on an agreement under seal, made the eighth of May, 1869, between the plaintiff and the original defendant, whereby the plaintiff agreed to lay the superstructure of the defendant’s railroad from Georgetown to Delaware bay, near Lewes, about 17 miles, under the direetioh of the company’s engineer; and to.build a pier out into the bay, according. to certain specifications, and to furnish the cross-ties, iron rails, timber, and other materials therefor. The plaintiff further agreed to begin the work within 30 days from the execution of the agreement; to complete the road to the depot grounds at Lewes by the first day of August then next, if the rails and ties could be had by that time; to have the piles of the pier driven by the last day of July; and to complete the whole work by the thirty-first day of October. In compensation for the work thus contracted for, the defendant agreed to pay the plaintiff $176,000 in the internal improvement bonds of the state of Delaware, (to be furnished to the defendant as provided for by an act of the legislature passed in 1865, and the amendments thereof,) and $150,000 in certificates of full-paid stock of the company, for which the plaintiff was to subscribe on the execution of the contract. This consideration was to be paid as follows: Sixty thousand dollars as soon as that amount of materials should be furnished and labor performed, according to the estimate of the engineer, and monthly thereafter, upon like estimates, in amounts equal to the materials furnished and labor done during each month, respectively, with any balance before unsettled for; the part payments to be in bonds and stock, proportional to the respective amounts of bonds and stock to be paid for the whole work.

The declaration has seven counts, in each of which the agreement is set forth in full. The first and second counts rely upon the implied agreement of the defendant to permit the plaintiff to carry on the work to its completion, and allege, by way of breach, that the defendant prevented the plaintiff from doing so, and thereby deprived him of the profits of the undertaking. The statement of this implied covenant in the first count, as finally amended and settled by consent of the parties, is to the following effect, namely: That in [543]*543and by the said articles of agreement the defendant covenanted and agreed with the plaintiff to permit him to carry on, prosecute, and perform the work agreed to be done, until the same should be fully done and completed, in manner as provided in, and according to the provisions and requirements of, said articles of agreement, and the plan, design, and specifications therein referred to, or until the thirty-first day of October, 1869, whichever should first happen. In the second count it is slightly varied, stating the implied covenant to be to permit the plaintiff to perform and complete tho work by tho thirty-first day of October, 1869, in manner as provided in, and according to the provisions and requirements of, said articles of agreement, and the plan, design, and specifications therein referred to. The assignment oí a breach in each case, after categorically alleging, in the terms of the covenant, that the defendant did not permit the plaintiff to perform and complete the work, proceeded to aver that, on the contrary, the defendant, before the work was fully done, to-wit, on the twentieth of August, 1869, did wrongfully prevent the plaintiff from carrying on and performing the said work, and from subscribing for the $150,000 stock of the company, although tho plaintiff was in good faith engaged in carrying on and performing said work, and ready, willing, and able to carry it on to completion, as provided in the agreement, and to subscribe for said stock.

These counts wero demurred to, on the grounds—First, that the implied covenant to permit the plaintiff to do the work is not correctly set out; secondly, that the breaches, as get forth, do not correspond with the covenant; and, thirdly, that the counts are generally bad.

I do not think that either of these grounds is well taken. I do not well see how the implied covenant could have been better stated. The agreement on the part of the plaintiff to do the work, and on the part of the defendant to pay for it, certainly raised an implied covenant on tho part of the latter to pormit the plaintiff to do the work in the manner, and according to the provisions and requirements, of the agreement. This is exactly what the plaintiff, in the first and second counts, states tho implied covenant to have been. It was certainly not necessary to repeat all those terms and requirements ovor again. These stood as they were written, unaffected by the covenant as expressed or unexpressed, and qualifying its effect in either case alike. In the two counts the implied covenant is set forth in different terms, hut amounting to substantially the same thing. The agreement was that the work should be completed by the thirty-first day of October. This means that it should be completed on that day, or before. The first count expresses it in both ways; the second simply uses the terms of the agreement—by the thirty-first of October. Both are right.

It is objected that the implied covenant, as defined in the declaration, obliged the defendant to permit the plaintiff to go on with the [544]*544work without complying with certain conditions, such as subscribing for stock immediately upon the execution of the agreement, commencing within 30 days, etc. If these were conditions, either precedent or subsequent, they are fitly provided for in the - qualification annexed to the plaintiff’s definition of the covenant, namely, to permit the plaintiff to prosecute and perform the work until performed and finished in manner as provided in, and according to the provisions and requirements of, the articles of agreement, and the plan, design, and specifications therein referred to.

The counsel of the defendant, however, contend that several of the “provisions and requirements” of the agreement were conditions precedent, the performance of which was necessary to entitle the plaintiff to proceed further with the work, and to claim the compensation provided for; and that he ought to have alleged performance of these conditions, or that the company prevented.him from performing them; and they enumerate the following'as such conditions precedent: (1) Subscribing for $150,000 capital stock upon the execution of the agreement; (2) beginning the work within 30 days therefrom;. (3) having the piles of the pier driven by July 31st; (4) having the road ballasted and finished to the depot grounds at Lewes by the first, of August. But I do not regard these engagements as conditions precedent, if they are. conditions at all.. They are not, in terms, made so by the parties themselves, and I cannot perceive any implied intent that they should be so. They stand simply on the agreement of the plaintiff, for the breach of which he might be liable to damages if the defendant could show anj damages resulting therefrom. If the plaintiff’s delinquency in these particulars evinced an intention on his part to abandon the contract, and not perform it at all, it would be evidence on that issue, and such abandonment would have'authorized the defendant to consider the contract as at an end, and to stop the plaintiff from further intermeddling with the road and pier. This is the .result of the most recent authority. Mersey Steel & Iron Co. v. Naylor, 9 Q. B. Div. 648.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fairchild Stratos Corporation v. Lear Siegler, Inc.
337 F.2d 785 (Fourth Circuit, 1964)
The Mame
184 F. 968 (D. Connecticut, 1911)

Cite This Page — Counsel Stack

Bluebook (online)
21 F. 541, 1884 U.S. App. LEXIS 2414, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hambly-v-delaware-m-v-r-uscirct-1884.