Hall v. Villarreal Development Corporation

517 S.W.2d 326, 1974 Tex. App. LEXIS 2932
CourtCourt of Appeals of Texas
DecidedNovember 27, 1974
Docket910
StatusPublished
Cited by7 cases

This text of 517 S.W.2d 326 (Hall v. Villarreal Development Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hall v. Villarreal Development Corporation, 517 S.W.2d 326, 1974 Tex. App. LEXIS 2932 (Tex. Ct. App. 1974).

Opinion

OPINION

NYE, Chief Justice.

This is a suit by the contractor, Villarreal Development Corporation, to recover the balance due on a written contract for work done in connection with the construction of a washateria building in the City of McAllen. The owners, V. K. Hall and wife, Betty Barbe Hall, filed a cross action to recover damages for the delay on the part of the contractor in completing the *328 building. The case was tried to the court without intervention of a jury. Judgment was rendered for the contractor. All relief was denied to the owners on their cross action. The owners have perfected their appeal from the judgment of the trial court.

On June 21, 1973, the contractor entered into a written contract with the owners to construct a concrete block and brick wash-ateria building for the sum of $35,200.00. Contemporaneous with the written contract, the owners executed a promissory note in this amount. The note was payable in installments equal to 90% of all of the labor expended and material installed or delivered to the job site during that installment period. The remaining 10% of the total consideration was to be' paid within thirty (30) days after completion, inspection and satisfabtion. The building was to be built in accordance with the plans and specifications agreed upon between the parties. However, part of the work was performed pursuant to certain oral agreements entered into as changes in the work specified in the plans and specifications were necessary. The owners ultimately paid the contractor the sum of $31,786.61, leaving a little less than 10% of the contract unpaid.

Later, certain disputes arose between the contractor and owners. The first controversy arose over whether or not there should have been a recirculating pump at the hot water heater and three lines running to the bulkhead where the washing machines were located, or whether the hot water line would run to a recirculating pump on the bulkhead, as was done in this case. The second controversy arose over whether or not there was an agreed change in the original plans and specifications between the parties concerning an overhang thus making it unnecessary to put on certain types of brackets and braces which were originally agreed upon. After completion of the building, the owners took possession on January 5, 1974. Because of the above controversies, the owners withheld the balance due under the contract.

The contractor then brought suit to recover the balance withheld. The owners’ cross action against the contractor was predicated on the above controversies and the delay by the contractor in completion of the contract. The trial was before the court without a jury. The trial court entered judgment in favor of the contractor for $3,414.39, and denied any relief to the owners on their cross action. The pertinent findings of fact filed by the trial court were:

(2) I find as a fact that the contractor and PLAINTIFF, VILLARREAL DEVELOPMENT CORPORATION completed the building in accordance with the plans and specifications in a good workmanlike manner, with the exception of the following:
(a) By mutual agreement, the parties agreed to alter the plans with respect to the 10 feet overhang of the building and to substitute steel braces and beams in lieu of the wooden braces or brackets in order to construct a more substantial building. That there was a meeting of the minds on the change and that the alteration was for the benefit of the Defendant without additional cost to him.
(3) I find that there was no meeting of the minds with respect to the construction of the recirculating hot water unit to be placed on the slab under the building; that a recirculating unit was installed and that the only plans and specifications regarding the same, as set out in the contract, was that such plumbing comply with local and State ordinances and that the plumbing was done in accordance with State and local ordinances.”

Appellants’ first and second points of error are insufficient evidence points and are directed to the controversy concerning re *329 circulation of the hot water. The owners argue that the building is not functional as a laundromat without a recirculating hot water system that would provide for hot water instantly and at all times, and the trial court erred in so finding. They further argue in their points of error that the plumber and contractor could have plumbed in the water system so that it would circulate in a complete circle and the customers could get hot water immediately rather than having to wait for as long as one minute; that a failure to do so brought about a failure to produce the building intended by the parties. The ap-pellee contractor answers this contention saying that the plumbing was installed so that it would circulate and it does. The contractor says in effect that if the owners had wanted the specific system that they now argue for, they should have set it out specifically in the contract, plans and specifications. The plumbing was done in accordance with State and local ordinances.

Where a case is tried before the court without a jury, the trial court acts as a trier of facts and stands in the same position as a jury, being the judge of the credibility of witnesses and the weight to be given their testimony. His findings are entitled to the same weight and conclusiveness on appeal as is the verdict of a jury. Where such findings are supported by evidence of probative force, they are binding upon the appellate courts. Carriere v. Bodungen, 500 S.W.2d 692 (Tex.Civ.App.—Corpus Christi 1973, no writ) ; Lindley v. Lindley, 201 S.W.2d 108 (Tex.Civ.App.—Fort Worth 1947, writ ref’d n. r. e.). We are not authorized to disregard such findings unless we find, as a matter of law, that they are not supported by any evidence or that such findings are so against the great weight and degree of credible testimony as to be manifestly wrong and unjust. As in other cases, fact findings may embody inferences properly deducible from the evidence. We will not disturb the fact findings if there is some evidence of probative force to support them, view-ing the evidence in the light most favorable to the successful party and indulging every legitimate conclusion that is favorable to him. 4 McDonald, Texas Civil Practice § 16.10 (1971); Hidalgo County v. Pate, 443 S.W.2d 80 (Tex.Civ.App.—Corpus Christi 1969, writ ref’d n. r. e.) ; Red Arrow Freight Lines, Inc. v. Howe, 480 S.W.2d 281 (Tex.Civ.App.-Corpus Christi 1972, writ ref’d n. r. e.); Mitchell’s, Inc. v. Nelms, 454 S.W.2d 809 (Tex.Civ.App.—Dallas 1970, writ ref’d n. r. e.) ; Denton v. Bennett, 364 S.W.2d 857 (Tex.Civ.App.—Fort Worth 1963, writ ref’d n. r. e.) ; Bennett v. Belton, 436 S.W.2d 161 (Tex.Civ.App.—Fort Worth 1968, writ ref’d n. r. e., 442 S.W.2d 678).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Holsworth v. Czeschin
632 S.W.2d 643 (Court of Appeals of Texas, 1982)
Ryan v. Morgan Spear Associates, Inc.
546 S.W.2d 678 (Court of Appeals of Texas, 1977)
Hosack v. Cassidy
543 S.W.2d 202 (Court of Appeals of Texas, 1976)
Loeb, Rhoades & Co. v. Stanley
541 S.W.2d 869 (Court of Appeals of Texas, 1976)
In re E. F.
535 S.W.2d 213 (Court of Appeals of Texas, 1976)
Matter of EF
535 S.W.2d 213 (Court of Appeals of Texas, 1976)
Hall v. Villarreal Development Corporation
522 S.W.2d 195 (Texas Supreme Court, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
517 S.W.2d 326, 1974 Tex. App. LEXIS 2932, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hall-v-villarreal-development-corporation-texapp-1974.