Halff Associates, Inc. v. Jacob & Martin, LLC

Court of Appeals of Texas·Decided May 29, 2025·No. 02-24-00439-CV·Published

Opinion

In the

Court of Appeals Second Appellate District of Texas at Fort Worth

No. 02-24-00439-CV

HALFF ASSOCIATES, INC., Appellant V.

JACOB & MARTIN, LLC, Appellee

On Appeal from the 415th District Court Parker County, Texas

Trial Court No. CV23-2017

Before Kerr, Wallach, and Walker, JJ.

Memorandum Opinion by Justice Wallach

MEMORANDUM OPINION

This is an interlocutory appeal from the trial court’s dismissal of Halff Associates, Inc.’s (Halff) third-party action for contribution or indemnity against Jacob & Martin, LLC (JM) pursuant to Texas Civil Practice and Remedies Code Section 150.002 because of Halff’s failure to file a compliant certificate of merit. Because we hold that Halff complied, albeit marginally, with the requirements of Section 150.002(b), we reverse the trial court’s judgment and remand the case for further proceedings.

I. Background The City of Willow Park (City) sued Halff, a professional engineering firm, contending that Halff had prepared an opinion of construction costs (OPCC) to enable the City to secure funding from the Texas Water Development Board Revolving Fund in connection with the construction of a municipal water facility project, sometimes referred to as the Fort Worth Wholesale Water Project. The City alleged that Halff prepared a Project Budget based on its OPCC of $13,770,000 (Project Budget) and submitted it to the Texas Water Development Board (Board) with the City’s loan application. The Project Budget provided that the Project would cost $13,770,000, and the loan application that Halff prepared and submitted to the Board on the City’s behalf sought $13,770,000 to finance the Project. On or about August 13, 2019, the Board approved the application and loaned the City approximately $13,770,000 for the Project. Allegedly, the actual cost to complete the

Project exceeded $13,770,000 by millions of dollars. Because of the significant shortfall in funding obtained for the Project at a favorable interest rate, the City allegedly was required to secure additional funding at a higher interest rate to cover the shortfall. Additionally, other costs and expenses were allegedly incurred by the City that could have been avoided had the costs of the Project been properly estimated. The City alleged that Halff was negligent in its project cost estimation and budget submission resulting in the City’s incurring unnecessary costs to complete the Project. The City attached a certificate-of-merit affidavit from Vinio Floris, a licensed professional engineer, to its original petition.

Halff answered the City’s petition with a general denial and several affirmative defenses and a counterclaim against the City for breach of contract. Halff also filed a third-party petition against JM, a professional engineering firm, seeking statutory contribution under Chapter 33 of the Texas Civil Practice and Remedies Code or common law indemnity from JM in the event that Halff was found to be liable to the City. Halff attached the Floris certificate and also the affidavit-certificate of merit of its own engineer expert, Joseph W. Norris, P.E., to its third-party petition.

JM answered Halff’s third-party petition subject to filing a motion to dismiss Halff’s claims pursuant to Texas Civil Practice and Remedies Code Section 150.002. See Tex. Civ. Prac. & Rem. Code Ann. § 150.002. JM’s motion to dismiss sought to dismiss Halff’s third-party claim for failing to attach a “sufficient” certificate of merit. JM contended that Norris’s certificate did not set forth specifically JM’s “negligence, if

any, or other action, error[,] or omission” nor the “factual basis” for each of Halff’s claims. See id. § 150.002(b).

Halff responded to JM’s motion to dismiss. Halff noted that it had denied the City’s allegations of liability against it and that its claims for contribution or indemnity against JM were derivative in nature and contingent on the City’s prevailing against it. To establish the nature of the City’s claims against it, Halff attached Floris’s certificate of merit to its third-party petition. To support its third-party claim against JM, it attached Norris’s certificate of merit. Halff argued that Floris’s certificate was quite detailed in its description of the facts and alleged errors of Halff in the preparation of the cost estimations for the Project. Floris’s certificate thus served as a factual basis for the claims being made against Halff that Halff was seeking to attribute to JM, in whole or in part, by means of its claims for contribution or indemnity.

Because Floris’s certificate did not mention JM, Halff attached Norris’s certificate to support its claims against JM. Norris’s certificate described the numerous documents he had reviewed in preparing his certificate. He pointed out that JM was involved in the preparation of the estimated construction costs that were being critiqued by the City in its original petition. Norris also stated that JM was responsible for submitting the estimated construction costs to the Board to apply for the very project funding that the City is alleging to be insufficient in this case. Norris further stated that JM sealed the Engineering Feasibility Report, which included the criticized estimated construction costs, to seek and obtain funding from the Board for the

Project. Halff argued that this act alone (applying an engineer’s seal to a report containing the estimated construction costs) demonstrates JM’s responsibility for the estimated construction costs that are critiqued in the City’s claim against Halff in this lawsuit.1 Finally, Norris’s certificate also said:

The [City]’s criticisms in the Original Petition relate to estimated construction costs that were submitted to the TWDB by [JM], and resultant funding obtained from the TWDB that was allegedly insufficient. The [City]’s criticisms, and the claim asserted by Plaintiff in the lawsuit against [Halff] implicate the acts or omissions of, and are at least in part the responsibility of[ JM].

JM filed a reply, which continued to contend that Norris’s report lacked the specificity required by the statute. The court signed an order on September 9, 2024, granting JM’s motion to dismiss Halff’s third-party claims without prejudice and ordering same.

1 See 22 Tex. Admin. Code Ann. § 137.33. That section provides:

(a) The purpose of the engineer’s seal is to assure the user of the engineering product that the work has been performed or directly supervised by the professional engineer named and to delineate the scope of the engineer’s work.

(b) License holders shall only seal work done by them, performed under their direct supervision as defined in §[ ]131.2 of this title, relating to Definitions, or shall be standards or general guideline specifications that they have reviewed and selected. Upon sealing, engineers take full professional responsibility for that work.

Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Halff Associates, Inc. v. Jacob & Martin, LLC, (Tex. Ct. App. 2025).

Halff Associates, Inc. v. Jacob & Martin, LLC (Halff Associates, Inc. v. Jacob & Martin, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Perry Homes v. Cull
258 S.W.3d 580 (Texas Supreme Court, 2008)
Equitable Recovery, L.P. v. Heath Insurance Brokers of Texas, L.P.
235 S.W.3d 376 (Court of Appeals of Texas, 2007)
Walker v. Packer
827 S.W.2d 833 (Texas Supreme Court, 1992)
M-E Engineers, Inc. v. City of Temple
365 S.W.3d 497 (Court of Appeals of Texas, 2012)
Toby Paul Couchman and Pro-Surv v. Elizabeth Cardona
471 S.W.3d 20 (Court of Appeals of Texas, 2015)
CBM Engineers, Inc. v. Tellepsen Builders, L.P.
403 S.W.3d 339 (Court of Appeals of Texas, 2013)
Melden & Hunt, Inc. v. East Rio Hondo Water Supply Corporation
520 S.W.3d 887 (Texas Supreme Court, 2017)
Jaster-Quintanilla & Assocs., Inc. v. Prouty
549 S.W.3d 183 (Court of Appeals of Texas, 2018)