Hale v. RR Donnelley and Sons

729 N.E.2d 1025, 2000 Ind. App. LEXIS 879, 2000 WL 760680
CourtIndiana Court of Appeals
DecidedJune 13, 2000
Docket43A03-9909-CV-362
StatusPublished
Cited by11 cases

This text of 729 N.E.2d 1025 (Hale v. RR Donnelley and Sons) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hale v. RR Donnelley and Sons, 729 N.E.2d 1025, 2000 Ind. App. LEXIS 879, 2000 WL 760680 (Ind. Ct. App. 2000).

Opinion

OPINION

RILEY, Judge

STATEMENT OF THE CASE 1

AppellanL-Plaintiff John Hale (Hale) appeals from the trial court’s order granting summary judgment in favor of Unarco Material Handling, Inc. (Unarco), because Unarco did not owe a duty to Hale.

We affirm.

ISSUE

Hale raises two issues 2 for our review, one of which we find dispositive: whether the trial court erred in finding that Unarco did not owe Hale a duty.

FACTS AND PROCEDURAL HISTORY

The undisputed facts establish that in February 1995, Unarco entered into a contract with R.R. Donnelley & Sons Company (Donnelley) for Unarco to provide “High Bay Storage Racks” to Donnelley. Unarco subcontracted with Structures, Inc. (Structures). Structures agreed to provide all the labor, supervision, equipment and necessary tools to construct and install the storage racks at the Donnelley facility. Structures used the services of Central Temporary Inc. (Central) to employ workers for the construction of the storage system. Hale was one of the workers obtained from Central to construct the storage system. On March 21, 1995, Hale fell while descending the storage system and suffered serious injury. The only Unarco employee present at the work site was a Site Manager responsible for periodic evaluations of the project progression.

On February 26, 1996, Hale filed a complaint for damages against Donnelley and Structures. Thereafter, on September 9, 1996, Hale filed an amended complaint for damages naming Unarco as an additional party. On November 2, 1998, the trial court granted summary judgment in favor of Donnelley. On June 1, 1999, Unarco filed its motion for summary judgment together with designation of materials and memorandum of law in support of the motion. On August 2, 1999, Hale filed a response to Unarco’s motion for summary judgment. On August 16, 1999, Unarco filed its reply to Hale’s memorandum in response to Unarco’s motion for summary judgment and a motion to strike several of Hale’s exhibits submitted in support of its response to Unarco’s motion for summary judgment. On August 24, 1999, Structures filed a motion to dismiss for lack of subject matter jurisdiction, and the trial court held a hearing on Structures’ and Unarco’s summary judgment motions. Thereafter, on August 25, 1999, the trial court entered its order striking Hale’s exhibits and granting Unarco’s motion for summary judgment. Hale’s present appeal involves only the trial court order with respect to Unarco.

DISCUSSION & DECISION

Standard of Review

Summary judgment is appropriate where the evidence shows there is no genuine issue of material fact and the moving party is entitled to a judgment as a matter of law. Ind.Trial Rule 56(C). Our standard of review is well established. Although Hale, the non-moving party, has the burden of persuading us that the grant of summary judgment was erroneous, we carefully assess the trial court’s decision to ensure that he was not improperly denied *1027 his day in court. Mullin v. Municipal City of South Bend, 639 N.E.2d 278, 280-81 (Ind.1994). On summary judgment, all facts and reasonable inferences drawn from those facts are construed in favor of the non-moving party. Wright v. Carter, 622 N.E.2d 170, 171 (Ind.1993). To recover under a theory of negligence, Hale must show three things: (1) Unarco owed a duty of care to Hale at the time he was injured; (2) Unarco failed to conform its conduct to that standard of care; and (3) damages were proximately caused to Hale by the breach. Webb v. Jarvis, 575 N.E.2d 992, 995 (Ind.1991). Because the trial court granted summary judgment on the first element of negligence — duty—we address only that issue. The issue of whether there is a legal duty owed by one party to another in a negligence action is a pure question of law. Williams v. R.H. Marlin, Inc., 656 N.E.2d 1145, 1155 (Ind.Ct.App.1995).

Duty

Hale argues that Unarco, as the general contractor, owed him a duty as an employee of Structures, the independent contractor. Specifically, Hale contends that the duty arises from the language of the contract between Unarco and Donnelley, indicating that Unarco intended to assume a “project-wide duty” of care to employees of independent contractors. Essentially, Hale argues that he is a third party beneficiary to the contract between Unarco and Donnelley.

In Indiana, the long-standing general rule has been that a principal is not liable for the negligence of an independent contractor. Bagley v. Insight Communications Co., L.P., 658 N.E.2d 584, 586 (Ind.1995); Pre st-O-Lite Co. v. Skeel, 182 Ind. 593, 597, 106 N.E. 365, 367 (1914); City of Logansport v. Dick, 70 Ind. 65, 78, 1880 WL 6175 (1880). However, five exceptions to this rule have been recognized. The exceptions are: (1) where the contract requires the performance of intrinsically dangerous work; (2) where the principal is by law or contract charged with performing the specific duty; (3) where the act will create a nuisance; (4) where the act to be performed will probably cause injury to others unless due precaution is taken; and (5) where the act to be performed is illegal. Bagley, 658 N.E.2d at 586.

Hale argues that the second exception applies to this case. Specifically, Hale contends that pursuant to the contract between Unarco and Donnelley, Unarco agreed to a project wide duty of providing a safe working environment, and that this duty required Unarco to assure that the subcontractors complied with required safety procedures and regulations. Hale, in his argument, relies on the following contractual language from the “Equipment Purchase Agreement by and Between R.R. Donnelley & Sons Company ... and Unarco Material Handling ... ”: (R. 392). 3

Q. INSTALLATION
>Jc
Unarco shall provide the services of an experienced, qualified installer. The installer shall unpack, install, startup, operate and give instructions in the operation of the EQUIPMENT.
6. RULES OF WORK
Unarco agrees that, while its personnel are on R.R. Donnelley premises, they will abide by R.R. Donnelley’s normal rules of work and its standard practice governing behavior of its own employees .... Also, Unarco agrees to require such personnel to work in a manner which will comply with the Occupational Safety and Health Act of 1970.

(R. 400-401). 4

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Capitol Construction Services, Inc. v. Gray
959 N.E.2d 294 (Indiana Court of Appeals, 2011)
Illinois Bulk Carrier, Inc. v. Jackson Ex Rel. Jackson
908 N.E.2d 248 (Indiana Court of Appeals, 2009)
Stumpf v. Hagerman Construction Corp.
863 N.E.2d 871 (Indiana Court of Appeals, 2007)
Merrill v. Knauf Fiber Glass GmbH
771 N.E.2d 1258 (Indiana Court of Appeals, 2002)
P.T. Barnum's Nightclub v. Duhamell
766 N.E.2d 729 (Indiana Court of Appeals, 2002)
Spudich v. Northern Indiana Public Service Co.
745 N.E.2d 281 (Indiana Court of Appeals, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
729 N.E.2d 1025, 2000 Ind. App. LEXIS 879, 2000 WL 760680, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hale-v-rr-donnelley-and-sons-indctapp-2000.