Haigler v. Adams

63 S.E. 715, 5 Ga. App. 637, 1909 Ga. App. LEXIS 93
CourtCourt of Appeals of Georgia
DecidedFebruary 16, 1909
Docket1185
StatusPublished
Cited by8 cases

This text of 63 S.E. 715 (Haigler v. Adams) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Haigler v. Adams, 63 S.E. 715, 5 Ga. App. 637, 1909 Ga. App. LEXIS 93 (Ga. Ct. App. 1909).

Opinion

Hill, C. J.

The questions in this case arise in a suit on a contractor’s bond for the construction of a house. The judgment ef the trial court, in refusing to allow an amendment to the petition and in sustaining a demurrer thereto, was reversed by the Supreme Court. Adams v. Haigler, 123 Ga. 659 (51 S. E. 638). Subsequently the casé was before this court on exceptions to the award of a nonsuit, and that judgment was reversed. Adams v. Haigler, 2 Ga. App. 99 (58 S. E. 320). It is now before this court on exceptions to the refusal of the trial court to allow certain amendments of the answers, and to the judgment overruling the defendants’ motion for a new trial. We will consider the exceptions in so far as we regard them material and meritorious.

When the case was first before this court, we held, construing the decision of the Supreme Court, that the defenses that could be made to the suit in the then state of the pleadings were three: (1) that the delay in completing the work was due to alterations and additions made by the plaintiff, and not to the fault of the •contractors; (3) that there were material changes in the contract, not embraced in the admitted changes set out in the petition, and which were not consented to by the defendant Bazemore, and which increased his risk as surety; (3) the separate defense of Frey, one of the contractors, that with the consent of Haigler, the •other contractor, the plaintiff had released him from compliance with the contract. On the last trial Haigler, one of the principal defendants, offered an amendment to his original answer, by which amendment he in effect set up that the plaintiff and himself had entirely abrogated the original contract on which the suit was predicated, and had substituted therefor a new and entirely differ[639]*639cnt contract. In this amendment he specifically set out all the terms and conditions of the new contract, and averred that by ■this contract he had been discharged and released from liability .as contractor on the original contract; he alleged that with Frey, his partner, he undertook the construction of a house for the plaintiffi, according to plans and specifications prepared by an architect; that shortly after commencing the work, the plaintiff, without consulting him, and of his own motion, forced Frey to abandon the work, by driving him away from the premises and warning him not to return; that the plaintiff expressed great dissatisfaction with ■the work as it was then proceeding, and that it was finally agreed between the plaintiff and himself that the former should from that time on have full control of the work, furnishing all material, labor, services, tools, scaffolding, implements, and power of every kind necessary for a full completion of the work, and should have ■full right and arithority to suggest alterations and additions in the plans, and that he, this defendant, should cease to be a contractor, but would supervise the construction of the house, superintend the labor, and attend to paying for the same, the money for the materials and pay-rolls being furnished to him by the plaintiff; that in pursuance of this second agreement, he acted through-nut as superintendent in charge of the work for the plaintiff, and was under the absolute control and direction of the plaintiff in ■purchasing materials, finding labor, and carrying out suggestions ■of the plaintiff as to .alterations and additions, and that he was ■paid for such services a per-diem wage by the plaintiff. lie alleged that under this second contract, which was substituted for the original contract, the cost of construction of the house was .greatly increased, exceeding the amount sued for, and that this increased cost was due entirely to' the control exercised over such •construction by the plaintiff, and to the additions and alterations made by him. This amendment was objected to by the plaintiff .and was disallowed by the court; and to this ruling exceptions pendente lite were taken.

Bazemore, who was sued as surety on the original contract, ■offered the following amendment to his original answer: that Haigler and Frey jointly began the construction of the house named in the petition; that a few days thereafter, one of the contractors, 'Frey, was driven from the premises by the plaintiff, and warned [640]*640not to return; that shortly after this the other contractor, Haigler, for some cause not actually known to this defendant, threatened to. abandon, and did in fact abandon, the contract altogether; whereupon the plaintiff agreed with Haigler that from that time on he (the plaintiff) would purchase all the materials and find all the labor, etc., necessary to complete the work, and would furnish all the money for the pay-rolls, if Haigler would superintend the. construction of the house; and thereafter all the material that went into the house was purchased by the plaintiff, all the labor was paid for by the plaintiff, and everything necessary for the completion of the house was furnished by the plaintiff, and Haigler was paid by the plaintiff a per-diem wage for superintending the work for the plaintiff. He alleged that this new arrangement between Haigler and the plaintiff was' entirely unknown to, and was entered into without the consent of, this defendant, and. that' he was released from all liability on his bond, given for the performance of the first contract, by this substitution of another contract. He further alleged that he was not notified of Haigler’s' threatened and entire abandonment of the contract, and that he-was never given an opportunity to advance money for him, if needed, or to complete the construction of the house himself, but that the completion thereof was left wholly in the hands of the-owner. He further alleged that the material' changes and alterations in the manner of carrying on the work, the dispensing with the supervision of the architect, the finding of the material, and the paying of the labor by Adams were all without his knowledge- or consent, and greatly increased his risk as surety, and greatly increased the cost of construction of the house, and that by these-material changes and alterations he was discharged, from liability on his bond. This amendment was, on objection of the plaintiff,, rejected by the court, and exceptions pendente lite were filed by Bazemore.

These amendments are elaborated with great detail, but it will, be seen that in substance they set up, as defenses: First, thatHaigler, one of the original' contractors, was released from that-contract by the second contract or agreement which he made with, the plaintiff; in other words, that this second contract under which the house was constructed was accepted by the plaintiff and by Haigler as a substitution for the original contract, and for this. [641]*641reason Haigler was released and discharged from all liability on the original contract. Second, that Bazemore, as surety on the original contract, was released and discharged from all liability as such surety, (1) because of the second contract, made without his knowledge or consent, by the plaintiff and Haigler, under which the house was constructed; and (2) because, even if there was not a complete substitution, there were material changes and alterations in the contract, made by Haigler and the plaintiff without his knowledge or consent as surety, which greatly increased his risk, and released him from all liability.

1, 2. The proposed amendments to the answers of the defendants Haigler, principal, and Bazemore, surety, should have been allowed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hurt v. Hartford Fire Insurance
178 S.E.2d 342 (Court of Appeals of Georgia, 1970)
Kuniansky v. Williams
115 S.E.2d 204 (Court of Appeals of Georgia, 1960)
Davidson v. Consolidated Quarries Corp.
108 S.E.2d 495 (Court of Appeals of Georgia, 1959)
Dowling v. Southwell
96 S.E.2d 903 (Court of Appeals of Georgia, 1957)
Smith v. Georgia Battery Co.
169 S.E. 381 (Court of Appeals of Georgia, 1933)
Tice Co. v. Evans
123 S.E. 742 (Court of Appeals of Georgia, 1924)

Cite This Page — Counsel Stack

Bluebook (online)
63 S.E. 715, 5 Ga. App. 637, 1909 Ga. App. LEXIS 93, Counsel Stack Legal Research, https://law.counselstack.com/opinion/haigler-v-adams-gactapp-1909.