Adams v. Haigler

58 S.E. 330, 2 Ga. App. 99, 1907 Ga. App. LEXIS 286
CourtCourt of Appeals of Georgia
DecidedMay 28, 1907
Docket75
StatusPublished
Cited by4 cases

This text of 58 S.E. 330 (Adams v. Haigler) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Adams v. Haigler, 58 S.E. 330, 2 Ga. App. 99, 1907 Ga. App. LEXIS 286 (Ga. Ct. App. 1907).

Opinion

Hill, C. J.

Adams brought suit on a contractor’s bond against Haigler and Frey as principals and Bazemore as surety. Demurrers were filed by the defendants to. the petition, and were sustained by the trial court. On exceptions to this judgment, the Supreme Court reversed the judgment, and held that the “allegations in the original petition and the amendment seem to set forth a complete cause of action upon the bond,” and that “the petition was not subject to any of the objections set forth in the demurrers.” Adams v. Haigler, 123 Ga. 659, 51 S. E. 638. The opinion of the Supreme Court is comprehensive, and fully settles the law of the case relating to the allegations of the petition. Me do not think any profitable purpose would be accomplished by making an extended statement of the case, as that has been done by the Supreme Court. The case is now before this court on exceptions to the refusal of the court to strike certain pleas, and to the granting of a nonsuit.

The defendants filed separate answers, denying the allegations of the plaintiff, except as to the execution of the contract. Haigler pleaded: (3) That at the time of entering into that contract another contract was made by Frey and himself with the plaintiff, in which it was agreed that the plaintiff should purchase the lumber and other things necessary in the construction of the house; (4) that after the signing of the original contract it was agreed between the plaintiff and himself that they would not carry out all its terms, and it was not carried out in all its terms, in that the plaintiff agreed to buy and to furnish to him certain lumber, and the plaintiff instructed him that it was not necessary to live up [100]*100to paragraph 5 of the contract, and not necessary .for him to see the architect and get a written estimate, bnt that he (Haigler) conld come to him (the plaintiff) when in need of money; (5) that it was agreed between the plaintiff and himself that paragraph 3 of the contract should not be carried out; (6) that it was agreed between them that no written direction from the architect was necessary for alterations in the plans or for extra work; (12) that in good faith he (Haigler) performed his work as far as” possible, and the plaintiff was not damaged in any amount, for he was not subjected to any loss, and he got more than his money’s1 worth. Other parts of Haigler’s pleading were stricken on demurrer. The demurrer as to the foregoing paragraphs was overruled.

Frey, in his answer, repeated the foregoing averment of Haigler as to the agreement that the plaintiff should furnish lumber, etc.,, and set up further: (4) That after the signing of the contract he (Frey), with the consent of the plaintiff and of Haigler, withdrew from “said partnership” and the contract, and was released from an}' further interest or connection therewith; and (5) that up to-the time of said withdrawal he had not failed or refused to carry out his contract, and it was at the suggestion of the plaintiff (he has learned since his withdrawal) that he gave up the contract, and. it was admitted by the plaintiff as being satisfactory that he should withdraw. A demurrer to each of these paragraphs, as well as; to the entire answer of Frey, was overruled.

Bazemore pleaded: (3) That at the time the contract attached to the petition was made he “knew of no other contract being signed between the parties thereto, and he never consented in any way to the change, abrogation, or alteration of said contract in. any wa}', nor to the signing of any other contract in reference thereto;” (4) that “he is discharged by law from any liability on said bond, for the reason that said averments in the declaration admit said contract was abrogated, altered, and changed by the parties thereto by mutual consent, and without the knowledge and consent of” this defendant; (5) that “he is discharged from liability on said bond as surety, for the further reason that said changes, alterations, and abrogations of said contract increased the risk of said defendant as suretj', and exposed the defendant to greater liability thereon, without his knowledge or consent;” (6) [101]*101that he is discharged as surety because the plaintiff purchased the material used in the construction of the building, 'in violation of the contract, defendant being willing to risk the judgment and experience of the parties whose faithful'performance he guaranteed, but unwilling to accept and risk the judgment of the plaintiff in purchasing material, owing to the plaintiff’s lack of experience in •that line; (7) that he is discharged because the plaintiff violated paragraph 7 of the contract, “in that he purchased said material ■without giving five days’ notice as required thereby, and without .any notice or consent to or of this defendant;” (8) that he is discharged because the plaintiff failed to have the said lumber delivered at the proper times, which delay increased 'the cost of the '.building several hundred dollars, and which delay and purchases ■above set out increased the risk and liability of this defendant as surety, .and since the filing of this suit he has learned that the plaintiff admitted that there were such delays, and put in a claim against the parties from whom the material was purchased, for a certain sum as damages for the delay; (9) that he is discharged because the plaintiff, without his knowledge or consent, paid out money in a different way and mode from that required by the contract; (10) that he is discharged because, without his knowledge ■or consent, the plaintiff consented to Frey’s withdrawal from the ■contract, which consent increased the risk of the surety and exposed him to greater liability; (11) that he is discharged because the plaintiff accepted the house from the contractors; (12) that he is discharged because the plaintiff, in his declaration, avers that the said additions and alterations in. the plan of work were made without, being directed in writing by the architect, and without the consent or knowledge of the surety, as required by the contract, which likewise increased the risk of this defendant as surety; and (13) that he is not liable to the plaintiff in any amount, for the reason that the plaintiff has not been damaged, but has received more than his money’s worth for every expense incurred. The plaintiff demurred generally and specially to Bazemore’s • answer, .and the demurrer was overruled.

1. We will consider the pleas and demurrers in so far as we think the judgment of the court was erroneous thereon. The demurrer to paragraph 3 of Haigler’s answer should have been sustained; the alleged change of the contract in the particular mentioned hav[102]*102ing been the result of an agreement by all the parties thereto, as stated in this paragraph. Such consent novation could not be 'set up as a sufficient and valid defense by the contractors. The demurrer to paragraph 4 of Haigler’s answer should have been sustained. It was wholly immaterial from whom Adams, the plaintiff, purchased the lumber to be used in building the house; it having been agreed, as alleged in paragraph 3, that he should purchase the “lumber and other things necessary in the construction of the house.” Paragraph 5 of the contract provides how the contractors shall be paid, to wit, that the architect shall make an esti • mate of the material and labor put into the building during the preceding month, and this estimate shall be paid by the owner, de-ducting lo per cent, to be paid on the completion and acceptance of the work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Firemen's Insurance v. Oliver
167 S.E. 909 (Court of Appeals of Georgia, 1933)
Blackburn v. Morel
79 S.E. 492 (Court of Appeals of Georgia, 1913)
Self v. Adel Lumber Co.
64 S.E. 112 (Court of Appeals of Georgia, 1909)
Haigler v. Adams
63 S.E. 715 (Court of Appeals of Georgia, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
58 S.E. 330, 2 Ga. App. 99, 1907 Ga. App. LEXIS 286, Counsel Stack Legal Research, https://law.counselstack.com/opinion/adams-v-haigler-gactapp-1907.