Hahl v. Deutsch

94 S.W. 443, 42 Tex. Civ. App. 1, 1906 Tex. App. LEXIS 182
CourtCourt of Appeals of Texas
DecidedFebruary 12, 1906
StatusPublished
Cited by7 cases

This text of 94 S.W. 443 (Hahl v. Deutsch) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hahl v. Deutsch, 94 S.W. 443, 42 Tex. Civ. App. 1, 1906 Tex. App. LEXIS 182 (Tex. Ct. App. 1906).

Opinion

GILL, Chief Justice.

Richard Deutsch brought this suit to re *2 cover of C. W. Hahl $1,012, the alleged contract price for sinking a well for. Hahl. He pleaded the contract of employment, the performance of the work, and prayed to recover the contract price. He also pleaded that the contract as first made was modified on account of the nature of a part of the strata through which he drilled, and the size of the casing was thereby reduced from ten to eight inches. That he completed 250 feet of the well with eight inch casing, but was prevented by defendant from completing the 60 feet next to the surface by failure of defendant to furnish eight inch casing, and by defendant’s insistence that the last 50 feet be finished in ten inch casing. He also alleged that through this and other acts of defendant he was prevented from making an agreed test.

He prayed that if the court could not allow him the contract price per foot for the well, that he be allowed to recover upon a quantum meruit the value of the work he had done.

The answer of defendant was a general denial.

A trial to the court without a jury resulted in a judgment for plaintiff for $562.50, and the defendant has appealed.

By the first assignment appellant assails the finding of the trial court to the effect that the well in question was sunk under a verbal contract as alleged, and not under a written contract of date February 16, 1903. The point made is that the finding is against the great weight and preponderance of the evidence. The facts bearing upon the issue are in substance as follows: On February 16, 1903, Alfred Meurer for the Southwestern Engineering Company, entered into the following written contract with C. W. Hahl:

“State of Texas, )

Parish of Harris, )

Houston, Texas, 2-16, 1903.

This agreement, entered into by and between the Southwestern Engineering Co., Ltd., of Jennings, La., party of the first part, and C. W. Hahl, of Houston, Texas, party of the second part, for the purpose of boring one (1) ten in. (9 5-8) well, said well when completed shall furnish good quantity of water. Party of the second part shall furnish all casing, and necessary feet. Screen delivered at well when test hole is completed. It is further agreed that party of the second part shall pay party of the first part $2.25 per foot for each and every well wtien completed; and to pay all cash. Party of the first part agrees to make thorough test of the well with P. IL Wood pump, and to furnish at least (500) five hundred gallons of water per minute. Also have well completed by April 1, 1903. (Signed) Southwestern Engineering Co., per Alfred Meurer, C. W. Hahl.” The company was a partnership composed of Meurer and the plaintiff Deutsch.

This contract provided for the digging of but one well, and its terms do not disclose the place where it was to be sunk. The provision that each and every well when completed should be paid for in cash at $2.25 per foot is too general to apply to more than the one well, unless supplemented by further agreement, and is obviously not an undertaking on the part of the company to sink more than one well. In pursuance of this contract, Deutsch shipped his machinery to Texas and, according *3 to his testimony, completed a well on what is designated as the Hahl and Juda place within the time limit, and the well was accepted and paid for. Defendant denied this, and adduced his and other testimony to show that the Hahl and Juda well was sunk under a special arrangement made because the engines had not been placed on the Cornthwaite place when Deutsch’s machinery arrived. That the Cornthwaite place was where the well was to be sunk under the written contract. It is undisputed, however, that the Hahl and Juda well was sunk and completed for the price, within the time and according to the terms of the written contract.

The Cornthwaite well is the basis of this suit, and was begun after April 6, 1903, and therefore after the time fixed for the completion of the well provided for in. the written contract.

The plaintiff testified, in effect, that the Hahl and Juda well was sunk and completed in fulfillment of the written contract. That after its completion he advised plaintiff (defendant?) that he would dig no more wells under its provisions as his partner had made changes in their printed contract forms which did not suit plaintiff, and he would proceed no further thereunder. That thereupon, on April 6, 1903, he individually entered into a verbal contract with Hahl whereby he undertook to dig a well for him on the Cornthwaite place, by the terms of which he was to sink a “test hole” six inches in diameter for which he was to receive $1.00 per foot whether he found water or not. He was to go a depth of 500 feet unless water was found at a less depth. That if water was found in quantities which justified it, he was to ream out the hole for ten inch casing (to be furnished by Hahl), place the casing, and test the well for. Hahl with a “P. K. pump,” also to be furnished by Hahl. If after the digging of the test hole it was decided to complete the well, he was to receive an additional $1.33 per foot for enlarging the well, placing the casing and testing it. That he bored one test hole 300 feet, but found no water, and found the rock so hard and thick it would be impossible to complete it. That at Hahl’s insistence he sunk another test hole and found water in good quantity at 312 feet, whereupon it was determined between him and Hahl that it should be reamed out, cased and tested. That thereupon he reamed it to a depth of fifty feet and found that a boulder at the side of the hole at that depth rendered it impossible to carry a ten inch casing past that point. Hahl being anxious for water modified the contract and agreed to the placing of an eight inch casing, furnished 250 feet of casing of that diameter, and plaintiff placed it in the well, and the well could have been effectively completed with eight inch casing, but Hahl insisted that the 60 feet next the top be completed with ten inch casing. Plaintiff protested it was impracticable. Hahl then sent down a man named Dixon who procured about 60 feet of ten inch casing, reduced it to eight inches at the lower end so as to connect with the eight inch casing and made threads thereon to effect the connection. Plaintiff protested that the eight inch casing was not long enough; that the threads on the ten inch casing were not properly cut and would not hold, and that on account of deficiency of length there would be ten feet of uncased space in the well, notwithstanding his protest the ten inch piece was sunk, and Hahl’s agents in an effort to connect it with the eight inch twisted *4 off the connection, and the uncased space was left as plaintiff predicted. On account of quicksand the casing could not thereafter be safely withdrawn. Notwithstanding the defect the water rose to within six feet of the surface, and a day’s baling with a ten foot sand bucket did not reduce the water level below 36 feet from the surface of the ground. Hahl failed to supply the “P. K. pump,” so that test was not made. In the verbal contract the quantity of water was not guaranteed.

At this point plaintiff demanded his pay, and defendant declined on the ground that the well had not been completed. Plaintiff did nothing further.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Herron v. Lackey
554 S.W.2d 708 (Court of Appeals of Texas, 1977)
Melody Home Manufacturing Co. v. Morrison
502 S.W.2d 196 (Court of Appeals of Texas, 1973)
Buie v. Hofheinz
254 S.W.2d 852 (Court of Appeals of Texas, 1953)
Jordan Drilling Co. v. Starr
232 S.W.2d 149 (Court of Appeals of Texas, 1949)
Smith v. Patterson
294 S.W. 984 (Court of Appeals of Texas, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
94 S.W. 443, 42 Tex. Civ. App. 1, 1906 Tex. App. LEXIS 182, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hahl-v-deutsch-texapp-1906.