Haber v. Gutmann

64 A.D.3d 1106, 882 N.Y.S.2d 780
Appellate Division of the Supreme Court of the State of New York·Decided July 30, 2009·Published·Cited by 24 cases

Opinion

Kane, J.

Appeals (1) from a decision of the Supreme Court (Work, J.), entered July 7, 2008 in Ulster County, in favor of defendant, and (2) from the judgment entered thereon.

After plaintiff purchased property containing a custom-built, Adirondack-style house in a state of disrepair, he and defendant discussed renovations to the house. In June 1992, defendant wrote plaintiff a letter generally outlining the procedures for renovations if defendant were involved. Defendant was not eager to resume business as a contractor, so plaintiff hired another individuad, John Byer, to perform the renovations. When plaintiff became dissatisfied with Byer’s work, plaintiff and defendant again discussed the renovation project. In October 1993, plaintiff wrote to defendant and enclosed a check for defendant to start working on renovations to the house. Defendant cashed [1107] the check and began working on the house in May 1994. The parties’ agreement required plaintiff to prefund the project.

After a temporary work stoppage in July 1994 due mainly to defendant’s concerns over plaintiffs funding, the parties clarified and revised the terms of their agreement and defendant resumed work in the fall of 1994. Defendant and his crew continued working until January 1995, when he halted work as a result of plaintiffs failure to advance funds. Although the parties corresponded and anticipated resumption of work, in April 1995 defendant removed his equipment from the property. At the time that defendant ceased working, the interior of the house was gutted and the outside shell was temporarily watertight, but lacked flashing around the chimneys and siding. At the time of trial in 2006 and 2007, no further work had been done on the house.

Plaintiff commenced this action in January 2001, alleging, among other things, that defendant breached their contract. Following a bench trial, Supreme Court issued a lengthy decision finding that the parties had entered into two contracts, the first covering work from October 1993 through July 1994 and the second encompassing work from fall 1994 through January 1995. The court found that plaintiffs cause of action was time-barred as to the first contract. As for the second contract, the court found that plaintiff failed to adequately prove damages, requiring dismissal of the breach of contract claim. In the alternative, the court found that if only one contract existed, plaintiff still failed to prove damages. Plaintiff appeals from the decision* and subsequent judgment.

When reviewing a decision following a nonjury trial, this Court independently evaluates the evidence and grants judgment as warranted by the record, giving due deference to the trial court’s credibility determinations concerning witnesses (see Atkinson v State of New York, 49 AD3d 988, 989 [2008]; Poli v Lema, 24 AD3d 981, 983 [2005]; but see Thoreson v Penthouse Intl., 80 NY2d 490, 495 [1992]). The record here discloses that the parties entered into one contract for defendant to renovate plaintiffs house. The June 1992 letter did not constitute an offer, as it was only an outline, did not contain necessary terms and did not disclose an intent by defendant to be bound. Even if that letter was an offer, plaintiff rejected it by hiring Byer to perform the renovations. The October 1993 letter, referencing the parties’ prior conversations, evidenced an [1108] offer which was accepted by defendant when he cashed the enclosed check and began performing renovation work (see Sky-Lift Corp. v Flour City Architectural Metals, 298 AD2d 214, 215 [2002]). Defendant stopped working in July 1994 and only recommenced work after the parties discussed and refined some of the terms, including an increase in defendant’s compensation. Supreme Court considered this the termination of the first contract and an agreement on a second contract. Yet the record reveals that, despite some disagreement in July 1994 concerning billing and funding, both parties envisioned a continuation of their relationship with defendant acting as plaintiffs contractor. That relationship did indeed continue. Thus, the initial contract continued, albeit with some amendments to the original terms. As only one contract existed and work under that contract terminated less than six years prior to the commencement of this action, the statute of limitations did not bar plaintiffs claim concerning any of defendant’s work (see CPLR 213 [2]; City School Dist. of City of Newburgh v Stubbins & Assoc., 85 NY2d 535, 538 [1995]).

Supreme Court correctly dismissed plaintiff’s breach of contract claim. Plaintiff bore the burden of proving damages resulting from defendant’s breach of contract (see Peak v Northway Travel Trailers, Inc., 27 AD3d 927, 928 [2006]; Cotazino v Basil Dev. Corp., 167 AD2d 632, 633 [1990]). In general, the proper measure of damages for breach of a construction contract is the cost to either repair the defective construction or complete the contemplated construction (see Route 7 Mobil v Machnick Bldrs., 296 AD2d 809, 810 [2002]; Thompson v McCarthy, 289 AD2d 663, 664 [2001]; Lyon v Belosky Constr., 247 AD2d 730, 731 [1998]). The damages must be reasonably certain, however, not based upon speculation (see Peak v Northway Travel Trailers, Inc., 27 AD3d at 929).

Here, plaintiffs expert architect, who examined the house in 2003, testified regarding numerous defects in defendant’s work. This expert opined that demolishing the house and rebuilding would cost less than repairing it piecemeal. Plaintiffs expert provided estimates for the overall cost of repairing versus replacing the building, but never testified as to the cost of repairing any specific defects in the house to substantiate his repair estimate (see Feldin v Doty, 45 AD3d 1225, 1227 [2007]; Thompson v McCarthy, 289 AD2d at 665; compare Cotazino v Basil Dev. Corp., 167 AD2d at 633). He also stated that the precise cost of repairs must be based upon a detailed structural analysis, which was admittedly never performed. Defendant’s expert architect, who also examined the house in 2003, opined that [1109] defendant’s construction work was properly done and that the house seemed sound.

Free access — add to your briefcase to read the full text and ask questions with AI

Haber v. Gutmann, 64 A.D.3d 1106, 882 N.Y.S.2d 780 (N.Y. Ct. App. 2009).

64 A.D.3d 1106 (Haber v. Gutmann) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Franco v. Sterling Home Solutions LLC
2025 NY Slip Op 04283 (Appellate Division of the Supreme Court of New York, 2025)
Parris v. Schneider Elec. Mobility NA, Inc.
2021 NY Slip Op 04755 (Appellate Division of the Supreme Court of New York, 2021)
Lapenna Contr., Ltd. v. Mullen
2020 NY Slip Op 06183 (Appellate Division of the Supreme Court of New York, 2020)
Crippen v. Adamao
2018 NY Slip Op 7287 (Appellate Division of the Supreme Court of New York, 2018)
Kelly v. Bensen
2017 NY Slip Op 4926 (Appellate Division of the Supreme Court of New York, 2017)
Shlang v. Inbar
149 A.D.3d 1402 (Appellate Division of the Supreme Court of New York, 2017)
Tobin v. Gluck
684 F. App'x 61 (Second Circuit, 2017)
Casey v. State
148 A.D.3d 1370 (Appellate Division of the Supreme Court of New York, 2017)
Mahoney v. State of New York
147 A.D.3d 1289 (Appellate Division of the Supreme Court of New York, 2017)
Timber Rattlesnake, LLC v. Devine
117 A.D.3d 1291 (Appellate Division of the Supreme Court of New York, 2014)
Fitzpatrick v. Animal Care Hospital, PLLC
104 A.D.3d 1078 (Appellate Division of the Supreme Court of New York, 2013)
Fabi v. Hayes
97 A.D.3d 1049 (Appellate Division of the Supreme Court of New York, 2012)
Hodges v. Cusanno
94 A.D.3d 1168 (Appellate Division of the Supreme Court of New York, 2012)
Ciarelli v. Lynch
69 A.D.3d 1008 (Appellate Division of the Supreme Court of New York, 2010)
In re the Estate of Putnam
68 A.D.3d 1614 (Appellate Division of the Supreme Court of New York, 2009)