H. Grodsky Company v. U.S. Pipe Foundry Co., No. 533533 (Jan. 24, 1996)

1996 Conn. Super. Ct. 969, 16 Conn. L. Rptr. 40
Connecticut Superior Court·Decided January 24, 1996·No. No. 533533·Unpublished

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]MEMORANDUM OF DECISION SUMMARY

This action involves a claim for damages under the Connecticut Product Liability Act, General Statutes § 52-572met seq. The plaintiff's one count complaint alleges that materials purchased from the defendant, which were incorporated into piping installed by the plaintiff, were defective. The plaintiff alleges that the defective materials caused the piping to fail, thereby causing the plaintiff to suffer substantial losses and damages as a result of the leakage of water that ensued. The defendant filed a motion to strike the plaintiff's complaint. The defendant's motion to strike will be granted, because the plaintiff's complaint alleges commercial loss between commercial parties, which is not recoverable under the Product Liability Act.

FACTS

The plaintiff, H. Grodsky Co., commenced this action by filing a one count complaint against the defendant, United States Pipe and Foundry Co., on February 10, 1995. The plaintiff subsequently filed a revised one count complaint on June 25, 1995. The complaint alleges that the plaintiff was engaged in the performance of a contract with the Gilbane Building Company for the installation of underground piping at a Groton, Connecticut, plant being constructed on behalf of Pfizer, Inc., and that prior to February 11, 1993, the plaintiff had purchased materials, such as pipe, sealing rings and bolts, from the defendant to be used in joining and installing such piping. The complaint further alleges that on February 11, 1993, a 24-inch chilled water line that had been installed by the plaintiff incorporating the materials purchased from the defendant failed, causing the plaintiff to suffer $46,015 in damages as a result of additional work and CT Page 970 replacement costs necessitated by a substantial leakage of water. The complaint goes on to allege that the piping failed because the materials supplied by the defendant were defective, and claims that the defendant is liable to the plaintiff under the Connecticut Product Liability Act, General Statutes § 52-572m et seq.

The defendant filed the present motion to strike the plaintiff's complaint on July 6, 1995. The plaintiff filed an objection to the motion on September 21, 1995. Pursuant to Practice Book § 155, both parties also submitted appropriate memoranda of law in support of their respective positions.

DISCUSSION

"The only remedy by which to test the sufficiency of a cause of action or defense, whether stated in one pleading, count or defense, or in a paragraph or paragraphs thereof, is a [motion to strike]." Donovan v. Davis, 85 Conn. 394, 397-98,82 A. 1025 (1912). "In ruling on a motion to strike the trial court is limited to considering the grounds specified in the motion . . . . [Unspecified grounds can] not furnish a basis for [granting the motion]." Merideth v. Police Commission,182 Conn. 138, 140-41, 438 A.2d 27 (1980). "[A] trial court must take the facts to be those alleged in the complaint . . . and cannot be aided by the assumption of any facts not therein alleged." Liljedahl Bros., Inc. v. Grigsby, 215 Conn. 345,348, 576 A.2d 149 (1990). The "facts" include those "facts necessarily implied and fairly provable under the allegations . . . . [They] do not include, however, the legal conclusions or opinions stated in the complaint." S.M.S. Textile v. Brown,Jacobson, Tillinghast, Lahan King, P.C., 32 Conn. App. 786,796, 631 A.2d 340 (1993). "[The court must construe] the facts alleged in the complaint in a light most favorable to the pleader." RK Constructors, Inc. v. Fusco Corp. , 231 Conn. 381,384, 650 A.2d 153 (1994). "The sole inquiry is whether the . . . allegations, if proved, would state a [cause of action]."Doyle v. A P Realty, 36 Conn. Sup. 126, 127, 414 A.2d 204 (1980).

The defendant argues that the plaintiff's complaint fails to state a cause of action upon which relief can be granted, because the allegations therein amount to allegations of commercial loss between commercial parties, which is not recoverable under the Product Liability Act. The defendant's CT Page 971 argument is based on § 52-572m(d) of the Act, which states that "`harm' includes damages to property, including the product itself, and personal injuries including wrongful death. As between commercial parties, `harm' does not include commercial loss." The defendant also relies on the language of § 52-527n(c) of the Act, which states:

As between commercial parties, commercial loss caused by a product is not harm and may not be recovered by a commercial claimant in a product liability claim. An action for commercial loss caused by a product may be brought only under, and shall be governed by, title 42a, the Uniform Commercial Code.

Free access — add to your briefcase to read the full text and ask questions with AI

H. Grodsky Company v. U.S. Pipe Foundry Co., No. 533533 (Jan. 24, 1996), 1996 Conn. Super. Ct. 969, 16 Conn. L. Rptr. 40 (Colo. Ct. App. 1996).

1996 Conn. Super. Ct. 969 (H. Grodsky Company v. U.S. Pipe Foundry Co., No. 533533 (Jan. 24, 1996)) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Donovan v. Davis
82 A. 1025 (Supreme Court of Connecticut, 1912)
Doyle v. a P Realty Corporation
414 A.2d 204 (Connecticut Superior Court, 1980)
Town of Trumbull v. Wales
3 Conn. Super. Ct. 66 (Connecticut Superior Court, 1935)
Meredith v. Police Commission of the Town of New Canaan
438 A.2d 27 (Supreme Court of Connecticut, 1980)
Liljedahl Bros. v. Grigsby
576 A.2d 149 (Supreme Court of Connecticut, 1990)
RK Constructors, Inc. v. Fusco Corp.
650 A.2d 153 (Supreme Court of Connecticut, 1994)