H. G. Hall Construction Co. v. J.E.P. Enterprises

321 S.E.2d 267, 283 S.C. 196, 1984 S.C. App. LEXIS 563
CourtCourt of Appeals of South Carolina
DecidedSeptember 17, 1984
Docket0276
StatusPublished
Cited by14 cases

This text of 321 S.E.2d 267 (H. G. Hall Construction Co. v. J.E.P. Enterprises) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
H. G. Hall Construction Co. v. J.E.P. Enterprises, 321 S.E.2d 267, 283 S.C. 196, 1984 S.C. App. LEXIS 563 (S.C. Ct. App. 1984).

Opinion

Bell, Judge:

H. G. Hall Construction Company commenced this action against J.E.P. Enterprises for breach of a construction contract. J.E.P. admitted the contract but denied any breach thereof. J.E.P. also raised affirmative defenses and counterclaimed for breach of the contract by Hall Construction. The jury returned a verdict of $112,000 for Hall Construction. J.E.P. appeals.

Hall Construction is a Tennessee corporation engaged in general contracting. H. G. Hall, Jr., is president of and owns the corporation. Hall owns another construction company, H. G. Hall and Associates, Inc., which is also a Tennessee corporation. J.E.P. is a South Carolina partnership. Jimmy and Elizabeth Pappas are its partners.

. In June 1977, J.E.P. entered into a contract with Associates, Inc., to construct a Ramada Inn in Beaufort, South Carolina. After it began start up work on the project, Associates, Inc., discovered it had not renewed its contractor’s license for the *199 year 1977 with the South Carolina Licensing Board for Contractors. On September 22,1977, H. G. Hall, Jr., wrote J.E.P. requesting that Hall Construction, which was licensed in South Carolina, be substituted for Associates, Inc., as the contractor on the Beaufort project.

In December 1977, J.E.P., Associates, Inc., and Hall Construction executed an addendum which amended the contract “to read H. G. Hall Construction Co., Inc.... in lieu of H. G. Hall & Associates, Inc.” The addendum further stated that H. G. Hall Construction Co., Inc., agreed “to assume all responsibility for the construction of the project.” Under the addendum, Associates, Inc., guaranteed timely performance by Hall Construction.

Hall Construction commenced work on the project in October 1977 and continued to work until March 10,1978, when J.E.P. terminated the contract because it deemed the work unsatisfactory. On May 14, 1979, Hall Construction filed a petition under Chapter XI of the federal bankruptcy act in the United States Bankruptcy Court in Memphis, Tennessee. After obtaining leave from the bankruptcy court, Hall Construction served J.E.P. with the complaint in the case at bar on April 4,1980.

The complaint stated two causes of action. The first cause of action alleged breach of the contract by J.E.P. and prayed for $150,530.96 in damages. The second cause of actioh alleged unjust enrichment and prayed for a quantum meruit recovery of $150,530.96. ■ '

I.

Prior to trial, J.E.P. moved to have Hall Construction elect whether it would proceed on the contract or in quantum meruit. The trial judge reserved his ruling on the motion until all the evidence had been presented. At the close of Hall Construction’s case in chief, J.E.P. again moved to require an election. The judge once more reserved his ruling. At the close of the evidence, Hall Construction elected to go to the jury on its contract cause of action. J.E.P. excepts to the judge’s refusal to require an election of causes of action prior to the close of the evidence.

In determining whether a plaintiff must elect between causes of action prior to trial, our law draws a distinction *200 between two types of cases. Tzouvelekas v. Tzouvelekas, 206 S. C. 90, 33 S. E. (2d) 73 (1945). The plaintiff may be required to elect between causes of action prior to trial if the complaint states distinct causes which are so inherently repugnant that the assertion of one necessarily constitutes an election and precludes an assertion of the other. Id. However, in cases where the complaint states different causes of action, but only one recovery is sought, and the causes are so stated because of an uncertainty as to which the evidence may establish or on which it may appear that plaintiff is entitled to recover, no election is required. Id.; see also Turner v. Belser, 146 S. C. 369, 144 S. E. 73 (1928) (where only one recovery sought, not error to refuse a motion to require the plaintiff to elect upon which cause of action he will proceed to trial); American Equity Life Insurance Co. v. Miller, 248 S. C. 107, 149 S. E. (2d) 331 (1966) (plaintiff may proceed to trial on inconsistent causes of action). We recently held that a plaintiff who states causes of action on an express contract and in quantum meruit need not elect between causes of action where a single recovery is sought. Harmon v. Jenkins, 318 S. E. (2d) 371 (S. C. App. 1984).

In this case, Hall Construction sought $150,530.96 as payment for work completed before J.E.P. terminated the contract. Although the complaint stated two theories for relief, one undelying transaction was involved and only one recovery was sought. Therefore, the trial judge properly allowed the case to proceed to trial on both causes of action.

J.E.P. cites several cases to support its contention that there cannot be a recovery based on quantum meruit when the complaint is founded on a special contract. 1 These cases are distinguishable. In each case plaintiff based his pleadings on an express contract and failed to prove it. The court consistently held that a plaintiff could not alternatively recover in quantum meruit unless he amended his pleadings to state a cause of action in quantum meruit. Since Hall Construction has pleaded causes of action in both contract and quantum meruit, these cases are inapposite.

*201 II.

J.E.P. next takes exception to the dismissal of its counterclaim on a motion for summary j udgment. The counterclaim sought $565,000 in general and special damages for alleged breaches of the contract by Hall Construction. Among other things, J.E.P. claimed Hall Construction breached the contract by filing for bankruptcy in Tennessee and by failing to be properly licensed as a general contractor in South Carolina. The trial judge dismissed the counterclaim on the ground that J.E.P.’s exclusive remedy was to file its claims in the bankruptcy court. However, the judge permitted the matters raised in the counterclaim to be asserted as affirmative defenses to Hall Construction’s suit.

We find no error in the judge’s ruling. Assuming J.E.P.’s claims were meritorious, 2 it was required to present them to the bankruptcy court.

Bankruptcy courts are vested with broad powers to stay state and federal actions against a Chapter XI debtor. Michaels-Stern & Co., Inc. v. Rice Men’s Shop, Inc., 274 S. C. 44, 260 S. E. (2d) 717 (1979). Under the Bankruptcy Rules in effect when Hall Construction filed its Chapter XI petition, that petition acted as an automatic stay of the “commencement or the continuation of any court ... proceedings against the debtor____” Bankruptcy Rule ll-44(a). However, such a stay does not bar actions brought by the debtor. In re Revere Cooper & Brass, Inc., 32 B. R. 577 (Bankr. S. D. N. Y. 1983); In re Regal Construction Co., Inc., 28 B. R. 413 (Bankr. Md. 1983).

In Michaels-Stern & Co. Inc. v. Rice Men's Shop, Inc., supra, our Supreme Court described the procedure to be followed in a state court action against a bankrupt. The facts in Michaels-Stern

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wells Fargo Home Mortgage v. Holloway
Court of Appeals of South Carolina, 2006
Bezanson v. Hampshire Meadows Development Corp.
742 A.2d 112 (Supreme Court of New Hampshire, 1999)
Wade v. Berkeley County
498 S.E.2d 684 (Court of Appeals of South Carolina, 1998)
Roberts v. Recovery Bureau, Inc.
450 S.E.2d 616 (Court of Appeals of South Carolina, 1994)
Briggs v. Newberry County School District
838 F. Supp. 232 (D. South Carolina, 1992)
Franke Associates v. Russell
368 S.E.2d 462 (Supreme Court of South Carolina, 1988)
Richburg v. Baughman
351 S.E.2d 164 (Supreme Court of South Carolina, 1986)
Harper v. Ethridge
348 S.E.2d 374 (Court of Appeals of South Carolina, 1986)
Aetna Casualty & Surety Co. v. Security Forces, Inc.
347 S.E.2d 903 (Court of Appeals of South Carolina, 1986)
Wessinger v. Rauch
341 S.E.2d 643 (Court of Appeals of South Carolina, 1986)
Jordan v. Jordan
326 S.E.2d 416 (Court of Appeals of South Carolina, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
321 S.E.2d 267, 283 S.C. 196, 1984 S.C. App. LEXIS 563, Counsel Stack Legal Research, https://law.counselstack.com/opinion/h-g-hall-construction-co-v-jep-enterprises-scctapp-1984.