Bezanson v. Hampshire Meadows Development Corp.

742 A.2d 112, 144 N.H. 298, 1999 N.H. LEXIS 113
CourtSupreme Court of New Hampshire
DecidedNovember 18, 1999
DocketNo. 96-686
StatusPublished
Cited by6 cases

This text of 742 A.2d 112 (Bezanson v. Hampshire Meadows Development Corp.) is published on Counsel Stack Legal Research, covering Supreme Court of New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bezanson v. Hampshire Meadows Development Corp., 742 A.2d 112, 144 N.H. 298, 1999 N.H. LEXIS 113 (N.H. 1999).

Opinion

THAYER, J.

The plaintiff, Dennis Bezanson, trustee for Atom Contracting, Inc. (Atom), appeals from a Superior Court (Groff, J.) order issued after a lengthy trial. The court reduced the plaintiff’s damages arising from defendant Hampshire Meadows Development Corporation’s breach of contract by the amount of the defendant’s damages, even though the defendant did not file a claim for recoupment. We affirm in part, reverse in part, and remand.

The following facts were adduced at trial. In March 1990, Atom contracted to provide the defendant labor and materials to construct a housing development. The contract price was $2,895,000. The contract required Atom to pay for inspection fees. It permitted the defendant to withhold payments to Atom on account of, inter alia, unremedied defective work and failure to pay subcontractors. The contract also provided that in the event of the defendant’s breach, Atom, upon seven days written notice, could terminate the contract and recover payment for “[w]ork executed and for proven loss . . . , including reasonable overhead, profit and damages.”

After construction began, a deed restriction was discovered that forced the defendant to modify its plans. Several change orders ensued, increasing the contract price to $3,168,582.

In June 1992, the defendant refused to make further payments until Atom performed certain specified duties. Later that month, Atom ceased all work on the project. Atom subsequently filed for protection under Chapter 11 of the United States Bankruptcy Code. See 11 U.S.C.A. § 301 (West 1993). The defendant filed a proof of claim for damages in Atom’s bankruptcy case alleging defective or incomplete work. The defendant filed a motion for relief from the automatic stay so it could terminate the contract, but never requested relief from the automatic stay to pursue a claim for damages in this case.

[300]*300The plaintiff, as trustee for Atom in bankruptcy, sued the defendant for breach of contract. As damages, the plaintiff sought a percentage of the completed work according to the agreed statement of values in the contract. The defendant did not file a counterclaim or a claim for recoupment. See SUPER. CT. R. 33.

The superior court found that the defendant materially breached the contract by refusing to pay Atom and that any breach by Atom was de minimis. The court held, therefore, that Atom’s cessation of work on the project was justified.

In calculating damages arising from the defendant’s breach, the court found that the plaintiff was entitled to recover damages for all work performed by Atom. The court concluded that the total amount Atom earned under the contract was $1,054,580 and that Atom received $970,585. Thus, the defendant owed the plaintiff $83,995. The court then held that the defendant was “entitled to certain setoffs” for amounts for which the plaintiff was contractually liable. Specifically, the court reduced the amount due to the plaintiff by: (1) amounts the defendant paid to subcontractors; (2) the cost of correcting deficiently completed work; (3) unpaid inspection fees; and (4) the cost to complete work for which Atom billed the defendant, but did not actually perform. Because the court found that the reductions exceeded the amount due to the plaintiff, the plaintiff’s recovery was zero. This appeal followed.

On appeal, the plaintiff argues that the court erred in: (1) allowing the defendant a reduction against damages because the defendant never filed a counterclaim or sought a recoupment; (2) allowing the defendant to deduct the value of defective or unperformed work when the value of such work was part of the defendant’s unsecured bankruptcy claim; (3) ruling that the plaintiff was not entitled to damages for lost profits, overhead, and interest; and (4) calculating the value of Atom’s allegedly defective work. The plaintiff also alleges that the court’s finding concerning the meaning of the contract term used to calculate the amount owed by the defendant’s breach was clearly erroneous and unsupported by the evidence. We address each issue in turn.

I. Reduction of Damages

The plaintiff contends that the trial court’s sua sponte decision to reduce the plaintiff’s damages constituted unfair surprise and prejudiced his ability to present his case. In terms of the trial court’s measure of damages, we are only asked to consider whether the reductions taken were proper. The plaintiff argues that the reductions constitute a recoupment to which the defendant was not [301]*301entitled because it failed to file for such relief. See SUPER. CT. R. 33. The defendant responds that it was not required to file a claim for recoupment because the reductions were integral to assessing the measure of the plaintiff’s damages.

A breach of contract may prevent a loss .... In so far as it prevents loss, the amount will be credited in favor of the wrongdoer.
[W]hen a building contractor is wrongfully prevented from completing construction, the cost of completion that is saved is deducted from the contract price to which full performance would have entitled him; also, . . . when an owner receives a defective or incomplete building, any part of the price that is as yet unpaid is deducted from the cost of completion that is awarded to him ....

5 A. Corbin, Corbin on contracts § 1038, at 236-38 (1964) (emphasis added). This calculation, however, presupposes that the defendant complied with procedural prerequisites. The fact that the reductions are integral to damages does not necessarily obviate the need to file a recoupment. See SUPER. CT. R. S3; cf. Zurback Steel Corp. v. Edgcomb, 120 N.H. 42, 44, 411 A.2d 153, 155 (1980). Although the reductions may have been “integral” to contractual damages, we must determine whether the reductions constituted a defense, requiring no additional filing, or a recoupment.

A recoupment is a type of counterclaim “arisfing] out of the same contract or transaction as that constituting the basis of plaintiffs’ claim.” Varney v. General Enolam Co., 109 N.H. 514, 516, 257 A.2d 11, 13 (1969). The doctrine of recoupment in a contract action permits the defendant to reduce or eliminate the plaintiff’s damages, or seek its own damages in excess of the damages claimed by the plaintiff, either because the plaintiff has not complied with a cross obligation of the contract or because the plaintiff violated another duty under the contract. Zurback Steel Corp., 120 N.H. at 44, 411 A.2d at 155. If recoupment is used merely to defeat the plaintiff’s claim, rather than to recover excess amounts, it is known as “defensive recoupment.” Id. In this case the trial court eliminated the plaintiff’s damages but did not afford the defendant affirmative relief. Therefore, if such reduction constituted i recoupment, it would be a defensive recoupment.

The test of whether the deductions taken by the trial court constitute a defensive recoupment or a defense lies in whether the [302]*302relief sought by the defendant could stand as an independent claim, or would merely defeat the plaintiff’s cause of action. Cf. In Re Marriage of Black,

Related

Inc. v. FirstLight Fiber, Inc.
Supreme Court of New Hampshire, 2023
Gulf Insurance v. AMSCO, Inc.
889 A.2d 1040 (Supreme Court of New Hampshire, 2005)
Strafford Technology, Inc. v. Camcar Division of Textron, Inc.
784 A.2d 1198 (Supreme Court of New Hampshire, 2001)
N.A.P.P. Realty Trust v. CC Enterprises
784 A.2d 1166 (Supreme Court of New Hampshire, 2001)
Royal Oak Realty Trust v. Mordita Realty Trust
777 A.2d 860 (Supreme Court of New Hampshire, 2001)
Klar v. Mitoulas
767 A.2d 401 (Supreme Court of New Hampshire, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
742 A.2d 112, 144 N.H. 298, 1999 N.H. LEXIS 113, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bezanson-v-hampshire-meadows-development-corp-nh-1999.