Gymco Construction Company, Inc. v. Architectural Glass & Windows, Inc.

884 F.2d 1362, 1989 U.S. App. LEXIS 14656, 1989 WL 104770
CourtCourt of Appeals for the Eleventh Circuit
DecidedSeptember 29, 1989
Docket88-8605
StatusPublished
Cited by8 cases

This text of 884 F.2d 1362 (Gymco Construction Company, Inc. v. Architectural Glass & Windows, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gymco Construction Company, Inc. v. Architectural Glass & Windows, Inc., 884 F.2d 1362, 1989 U.S. App. LEXIS 14656, 1989 WL 104770 (11th Cir. 1989).

Opinion

PER CURIAM:

Architectural Glass & Windows (AGW) appeals the district court’s award of damages to Gymco Construction Company (Gymco), on the grounds that AGW breached its contract by failing to install materials for a building fagade. We reverse the award of damages to Gymco, and remand for consideration of AGW’s counterclaim.

I.

FACTS AND PROCEEDINGS BELOW

Gymco was the general contractor for the construction of an exercise salon in Atlanta, Georgia. One of its numerous subcontractors was AGW. On February 21, 1985, the two parties contracted for the installation of a mirrored glass fagade, as well as other glass fixtures, for the building. This contract was in writing and executed by the respective presidents of each company. The contract required AGW to complete its work by May 7, 1985, subject to the receipt of approved shop drawings from Gymco and delivery of materials. One of these drawings was a template showing the locations of holes to be drilled in the glass fagade so that a sign could be anchored to the building. The contract also included a provision requiring any changes to be made by written orders signed by authorized officers of the two companies. The total value of the contract was $108,169, $72,586 of which was for installation of the mirrored fagade.

Gymco contracted with another subcontractor, Maltese Sign Company (Maltese), to supply the template needed by AGW. Although scheduled to arrive by February 27th, this template was not actually delivered until April 4th, five weeks later. By this time, it was impossible for AGW to finish the glass installation by its May 7th deadline. A meeting was held on April 18 *1364 to address the installation problems caused by the delay. At this meeting William Young, an employee of AGW, offered to explore the possibility of switching from mirrored glass to stainless steel, a material that could be furnished and installed more quickly. Young sent Gymco samples of the steel and shop drawings of the building with a stainless steel fagade. No written agreement was executed by the parties documenting this change, nor was there any indication that Young’s superiors at AGW were aware of it.

Throughout May, Young assured Gymco representatives that the steel had been ordered and would be installed soon. On May 31, 1985, Gymco’s president, Blaine Leidy, was supervising the work on the job site. He had been told that AGW would install the steel that day. When no one from the company appeared at the job site, Leidy phoned AGW and spoke with its president, Robert Newbern. Newbern denied any knowledge of an agreement to install stainless steel, and when he learned that Young had agreed to this modification he terminated Young immediately. On June 3rd, Newbern informed Gymco that AGW would not install the stainless steel because it was more expensive than glass, and outside the scope of the company’s expertise. AGW did continue to perform its other contract duties, however, until barred from the job site by Gymco in July 1985.

Gymco then contracted with Louis Hoffman, Inc., to supply and install the steel panels for the building fagade. The contract price was $50,414 higher than the $72,586 allotted in the original contract with AGW. In March, 1986, Gymco filed a breach of contract action against AGW for this difference in price. AGW counterclaimed for damages it claims resulted when Gymco interfered and prevented it from completing its contract obligations.

The district court found that AGW was discharged from its duty to install the mirrored glass fagade by the nonoccurrence of a condition precedent, i.e., the delivery of the template by Maltese by February 27, 1985. The court rejected AGW’s argument that the failure to deliver the template in a timely manner amounted to a breach by Gymco. The court found that the remaining terms of the written contract were still valid, and that Young’s actions created an “oral contract, as to one task only,” the installation of the stainless steel instead of mirrored glass. Thus, the total contract was partially written and partially oral. The court held AGW had breached the agreement by refusing to install the steel, and awarded damages to Gymco. AGW appeals and we reverse.

II.

JURISDICTION

The district court had jurisdiction under 28 U.S.C. § 1332(a) (1982). This court’s jurisdiction rests on § 1291.

III.

STANDARD OF REVIEW

The district court’s interpretation of the original contract is a question of law which we review de novo. Brewer v. Muscle Shoals Bd. of Educ., 790 F.2d 1515, 1519 (11th Cir.1986). The court’s determination that Young had the authority to act as AGW’s agent in modifying the original contract, or making a new contract for substitute performance, is reviewed under the clearly erroneous standard. See Cavic v. Grand Bahama Dev. Co., 701 F.2d 879, 887 n. 4 (11th Cir.1983); Bogue Electric Mfg. Co. v. Coconut Grove Bank, 269 F.2d 1, 4 (5th Cir.1959).

IV.

ANALYSIS

A. Breach of the Written Contract

Despite the terms of the contract, the parties agree that .AGW’s duty to install a mirrored glass fagade was discharged when it failed to receive the template on time. The delivery of the template was a condition precedent to AGW’s duty to install the glass fagade. Under Georgia law, the nonoccurrence of a condition precedent discharges the obligor’s duty to *1365 perform. 1 See Mutual Benefit Health & Accident Ass’n v. Hulme, 57 Ga.App. 876, 883, 197 S.E. 85, 89 (1938); accord Merritt Hill Vineyards, Inc. v. Windy Heights Vineyard, Inc., 61 N.Y.2d 106, 112-13, 460 N.E.2d 1077, 1081, 472 N.Y.S.2d 592, 596 (1984); Restatement (Second) of Contracts § 225(2) (1979). Thus, AGW did not breach the written contract when it failed to install a glass fagade.

We disagree, however, with the district court’s conclusion that Gymco, on its part, did not breach the agreement by failing to deliver the template in a timely fashion. Under the terms of the written contract, Gymco promised to deliver the template to AGW on time. Instead, it arrived over five weeks late. Gymco cannot escape responsibility for this delay by claiming that it delegated this duty to a third party. Gymco’s decision to use a third party to produce the template does not relieve it of its obligation to AGW. See Wood v. Brunswick Pulp & Paper Co., 119 Ga.App. 880, 884, 169 S.E.2d 403, 406 (1969) (Felton, C.J., concurring); 4 A. Corbin, Corbin on Contracts § 866, at 452 (1951).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Landcastle Acquisition Corp. v. Renasant Bank
57 F.4th 1203 (Eleventh Circuit, 2023)
SouthTrust Bank v. Collins Holding Corp.
139 F. App'x 133 (Eleventh Circuit, 2005)
Randall S. Bragg v. Bill Heard Chevrolet, Inc.
374 F.3d 1060 (Eleventh Circuit, 2004)
Henrietta v. Bloomberg
331 F.3d 261 (Second Circuit, 2003)
Henrietta D. v. Bloomberg
331 F.3d 261 (Second Circuit, 2003)
Cook's Pest Control, Inc. v. Rebar
852 So. 2d 730 (Supreme Court of Alabama, 2002)
Southland Distributors Marketing Co. v. S&P Co.
296 F.3d 1050 (Eleventh Circuit, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
884 F.2d 1362, 1989 U.S. App. LEXIS 14656, 1989 WL 104770, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gymco-construction-company-inc-v-architectural-glass-windows-inc-ca11-1989.