Gutheil v. Consolidated Edison of New York Co.

34 Misc. 3d 401
CourtNew York Supreme Court
DecidedJune 20, 2011
StatusPublished
Cited by2 cases

This text of 34 Misc. 3d 401 (Gutheil v. Consolidated Edison of New York Co.) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gutheil v. Consolidated Edison of New York Co., 34 Misc. 3d 401 (N.Y. Super. Ct. 2011).

Opinion

OPINION OF THE COURT

Paul Wooten, J.

Motion sequence Nos. 009 and Oil are hereby consolidated for disposition.

In motion sequence No. 009, defendant Nico Asphalt Paving Inc. (Nico) moves for summary judgment dismissing all claims and cross claims. Defendant Consolidated Edison of New York Company, Inc. (Con Ed) cross-moves for summary judgment dismissing all claims and cross claims. In motion sequence No. 011, plaintiff moves for partial summary judgment on the issue of liability against Nico and Con Ed.

Background

This is a personal injury action. Plaintiff, a former firefighter, brings this action based upon an accident that occurred on January 14, 2005. On that day, plaintiff sustained serious injuries after he descended from a fire truck and tripped or stepped on a spike or metal object embedded in the roadway located ap[403]*403proximately three feet from the curb, near the rear loading dock of 7 Hanover Square, between 85 and 95 Pearl Street, New York, New York.

Plaintiff asserts that Con Ed had left the spike in that area after the completion of work requiring a roadway opening. He claims that when he made contact with the spike, his left knee bowed and he fell to the ground. After being treated by EMS at the scene of the accident, he states that he was treated at Saint Vincent’s Hospital for injuries to his left knee. Due to the severity of his knee injury, plaintiff avers that he has recently retired from the fire department.

Through discovery, plaintiff learned that in October 2003, Con Ed received a permit to do work in the area of the accident and made a street opening approximately 180 feet from the corner of Hanover Square on Pearl Street. Plaintiff hired Stanley Fein (Fein) to do an inspection of the area in question. Fein opined that a spike was embedded in order to secure a temporary roadway cover during the opening of the roadway. Fein claimed that such procedures were customary with those contractors who performed roadway openings. Spikes are said to secure plates to the roadway so that they will not move when run over by traffic. Plaintiff has presented to the court a photograph of the alleged spike, which appears unclear and inconclusive.

Plaintiff also learned that the opening was covered with roadway plates by defendant Felix Equities, Inc. (Felix). He contends that the plates were later removed after the work was completed but the spike remained in the pavement. He argues that defendants violated various statutes when they allegedly failed to restore the roadway to its original condition after the completion of the work.

Plaintiff moves for partial summary judgment on the issue of liability against Con Ed and Nico, a subcontractor of Con Ed, on the ground that these defendants violated section 205-e of the General Municipal Law, and specifically violated 34 RCNY 2-11 (c) (2) and (3), 2-11 (e) (9) (iii), 2-11 (e) (12) (vi), (vii) and (viii), 2-11 (e) (15) (i) and (ii) and 2-11 (f) (4) (iv), and sections 19-109 (a), 19-110 and 19-122 of title 19, chapter 1 of the Administrative Code of the City of New York. Plaintiff argues that these violations were the proximate cause of his injuries. Alternatively, plaintiff argues that these defendants’ violations of the aforesaid codes and regulations constitute some evidence of negligence. With respect to the other defendants, plaintiff has previously received a default judgment against Felix. Plaintiff [404]*404concedes that he does not have a viable claim against defendant City of New York.

Plaintiff refers to General Municipal Law, which permits firefighters to make claims and recover for injuries in the line of duty, provided they demonstrate a reasonable connection between the alleged violation of a relevant statute or regulation and the resulting injury.

Plaintiff specifies that defendants violated the aforesaid regulations. He asserts that the regulations which defendants are alleged to have violated include such matters as the removal of debris and equipment, the contractor’s obligation to restore construction sites on streets to their original level of paving, and other protective measures a contractor must take on an excavation site.

Plaintiff asserts that the General Municipal Law provides a “quasi-penal” remedy to public employees like himself, who are sometimes unable to avoid certain hazards in the line of duty, some of which might include violations of safety codes attributed to property owners and other parties. According to plaintiff, even if defendants are able to argue successfully against his motion, this court should rule that defendants violated the codes at bar in order to reduce the jury issues during the trial. Plaintiff also states that he is under a lesser burden in a General Municipal Law case than in an ordinary negligence case, where violation of a code need not be a primary cause of the injuries. Plaintiff further states that he is entitled to partial summary judgment as to liability because the evidence presented by him is so strong that the inference of defendants’ negligence can be established as a matter of law. Plaintiff contends that he has clearly identified the spike as the source of the injuries, and that the defendants against whom he is moving cannot provide a justification for the spike’s presence on the premises.

In opposition to this motion, Nico first argues that the motion is untimely, pursuant to CPLR 3212 (a). Nico states that all summary judgment motions in this action must be filed within 60 days after the filing of the note of issue. The note of issue was allegedly filed on April 22, 2010, but the motion is dated July 26, 2010. Whereas Nico holds that there is apparently no excuse for the delay, it requests that the court disregard the motion.

Alternatively, Nico argues that it should be dismissed from this action because there is no evidence that it performs roadway openings, or that it installed the alleged spike. Nico [405]*405states that it had installed three inches of asphalt at the site over Felix’s roadway excavation. Nico claims that plaintiff has not shown that his injuries are causally related to the January 14, 2005 incident and not a subsequent incident that occurred on June 3, 2008, which allegedly involved another physical injury. Nico asserts that plaintiff has avoided any evidence in the record of that subsequent incident, which occurred after he was fully restored to regular firefighting duties and thereafter, caused him to be retired on a disability pension. Moreover, Nico avers that the codes allegedly violated are not specific statutory predicates for liability and would only be applicable to Con Ed, the permit holder, or the excavator, Felix.

Nico questions the actual existence of a spike during the roadway opening. Nico disputes the accuracy of Fein’s analysis of the premises. Furthermore, Nico contends that the description of the accident in all contemporaneous medical reports and records contradicts plaintiffs version of what happened at the time of the accident. Plaintiffs deposition testimony is said to contradict that of his medical examiner, Chris Kalingou (Kalingou). Kalingou does not refer to any spike as the cause of the accident. Nico claims that the facts concerning what led to the accident are in such dispute that summary judgment cannot be granted.

Nico argues that the alleged spike may have been placed in the premises by a crane operating company named National Rigger, according to a permit issued by the City of New York, in order to support a crane.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gutheil v. Consolidated Edison of New York Co.
104 A.D.3d 434 (Appellate Division of the Supreme Court of New York, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
34 Misc. 3d 401, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gutheil-v-consolidated-edison-of-new-york-co-nysupct-2011.