Gulick v. Connely

42 Ind. 134
CourtIndiana Supreme Court
DecidedMay 15, 1873
StatusPublished
Cited by20 cases

This text of 42 Ind. 134 (Gulick v. Connely) is published on Counsel Stack Legal Research, covering Indiana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gulick v. Connely, 42 Ind. 134 (Ind. 1873).

Opinion

Buskirk, J.

This was an appeal from a precept issued in favor of the appellant, under an order of the common council of the city of Lafayette, to enforce the payment of certain assessments in favor of appellant, as contractor, for the improvement of Kossuth street in said city.

[135]*135The complaint was full and complete, and no objection was urged thereto in the court below. The appellee answered in three paragraphs. A demurrer was overruled to the third paragraph, and this ruling is assigned for error and presents the first question for our decision.

The substance of such paragraph is, that said contract required the work to be completed on the first day of September, 1869, but that said work was not completed until, to wit, the 17th day of December, 1869, which was more than two months after the time required by said contract for the completion of said work; and defendant avers that by the terms of said contract, five per cent, per month should be deducted from said estimate and assessment against the property of said defendant, on account of said delay in the completion of said work, which deduction has not been made in said estimate and assessment; and the defendant avers that by reason of such delay, he has been greatly damaged thereby, in this, to wit, fifty dollars; and the said defendant says that said plaintiff ought not to have judgment for said assessment.”

That portion of the contract referred to in the above paragraph of the answer is as follows:

“ And it is further understood and agreed that if said party of the first part fails to complete said work within the time specified, and desires an extension of time to complete the same, such extension of time shall be granted only on condition that five per centum per month be deducted from the assessments of all work done after such extension* such deduction to operate for the benefit of the respective property holders in proportion to their assessments; and all damages arising on account of any failure on the part of the party of the first part to comply with the conditions of this contract shall be collected from the party of the first part, without any relief from valuation or appraisement laws.”

The contract, of which the clause above quoted is a part, was entered into between the appellant and the common council of the city of Lafayette. The appellee was not a [136]*136party to the contract. It is manifest that this clause must have been inserted at the instance of the common council, and that its purpose was to secure prompt performance on the part of the appellant. The provision that five per centum per month should be deducted from the assessment of all work done after the extension of the time of the completion of the contract, was in the nature of a penalty, which it was competent for the common council to enforce or not, in their discretion. And if they had chosen to enforce it, the time for them to have done so was when they allowed the last assessment; but it is shown not only by the answer, but by the transcript, that it was not enforced. The work was received by the city engineer, committee on street improvements, and common council, and the final estimate made. It should be observed that the penalty was only to attach on the condition that the contractor desired an extension of time for the completion of the work, when the extension could only be granted on the express condition that five per centum per month should be deducted from the assessment of all work done after such extension. If there was no extension of time asked by the contractor and granted by the common council, then the penalty did not attach, and the parties stood upon their common law liability, as though there was no such provision in the contract. It is not alleged in the answer that an extension of time was asked for and granted, nor is it shown what assessments were made for work done after such extension. Besides, the answer assumes to be in bar of the entire action, when the conclusion shows that it was- only in bar of fifty dollars.

The court erred in overruling the demurrer to the third paragraph of the answer;

By the agreement of the parties, the cause was submitted to the court for trial; and the evidence being heard, the appellant asked the court to state the facts found in writing and the conclusions of law thereon by the court.

The facts so found and the conclusions of law thereon are as follows:

[137]*137“ The city of Lafayette contracted with the plaintiff in accordance with the statute, by which plaintiff agreed to make a partial improvement of Kossuth street in said city (a small part of the street adjoining lands not within the corporation when the contract was made). The question to be decided now is, was the work done according to contract ? The grading and gravelling of the street were done according to specifications, and under the direction of the city engineer, except that for a distance of about half the line of the street; the grading was fifty-eight feet wide, instead of sixty feet; the grading was done, however, to the line of improvement as made, qn each side of the street, under the direction of the city engineer, and but fifty-eight feet were paid for. This I find to be a substantial compliance. The grading is shown to have been well done. By the terms of the contract, the sidewalks were to be made four feet in width, of good, sound, common white pine plank, two inches in thickness, six inches in width, and twelve or sixteen feet in length, laid so as to break joints, on good, sound, white oak scantling, four inches square and four feet long, laid four feet apart transversely to the sidewalks, and to be securely spiked to the same by two four inch spikes in each scantling; the lumber to be free from sap and injurious defects.

“ The improvement was finished, approved by the engineer, and accepted by the council, but the work was not done according to contract, in this: The timber of the sidewalks was not free from sap, and some (the number is not definite) of the cross pieces, to which the plank were nailed, were worm-eaten, having been sawed from dead timber. A part of the lumber which was brought to said improvement was rejected by the engineer, and was not used in the improvement; and the engineer testifies that he knew of no objectionable material being used, but the fact that some, in fact, a considerable amount (but hot a definite amount) of lumber with sap from one to two inches wide was used, is established. The contract is positive that the lumber ‘ must be free from sap.’ Had but a few pieces, but slightly injured [138]*138by sap, been put in the work, I would have regarded the work as substantially done according to the contract, but a violation of so plain a provision of the contract does not, to my mind, justify a recovery. The acceptance by the city of the work is prima facie evidence that the work was done according to contract, but not conclusive. The statute itself shows this. This presumption in the case at bar has been rebutted; the precept should not have been issued; therefore, I find for the defendant.”

The appellant excepted to the conclusions of law drawn by the court upon the facts found.

The appellant moved the court for a new trial, upon written reasons filed, which motion war. overruled, and the appellant excepted.

Thereupon the appellant moved the court for a venire de novo, upon the ground that the findings of the court were imperfect and did not cover all the issues in the cause.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Miller, Etc. v. Ortman, Etc.
136 N.E.2d 17 (Indiana Supreme Court, 1956)
Tri-City Electric Service Co. v. Jarvis
185 N.E. 136 (Indiana Supreme Court, 1933)
Seaside, City of v. Randles
180 P. 319 (Oregon Supreme Court, 1919)
Barber Asphalt Paving Co. v. City of Wabash
86 N.E. 1034 (Indiana Court of Appeals, 1909)
Royse v. Bourne
47 N.E. 827 (Indiana Supreme Court, 1897)
Thompson v. Connecticut Mutual Life Insurance
38 N.E. 796 (Indiana Supreme Court, 1894)
Reeves v. Grottendick
30 N.E. 889 (Indiana Supreme Court, 1892)
Sims v. Hines
23 N.E. 515 (Indiana Supreme Court, 1890)
Ross v. Stackhouse
16 N.E. 501 (Indiana Supreme Court, 1888)
Louisville, New Albany & Chicago Railway Co. v. Thompson
8 N.E. 18 (Indiana Supreme Court, 1886)
Johnson v. Putnam
95 Ind. 57 (Indiana Supreme Court, 1884)
Brunk v. Champ
88 Ind. 188 (Indiana Supreme Court, 1882)
Liberty Township Draining Ass'n v. Brumback
68 Ind. 93 (Indiana Supreme Court, 1879)
Merrick v. State
63 Ind. 327 (Indiana Supreme Court, 1878)
Leeds v. Boyer
59 Ind. 289 (Indiana Supreme Court, 1877)
Whitworth v. Ballard
56 Ind. 279 (Indiana Supreme Court, 1877)
Dehority v. Nelson
56 Ind. 414 (Indiana Supreme Court, 1877)
Peters v. Lane
55 Ind. 391 (Indiana Supreme Court, 1876)
McMahan v. Spinning
51 Ind. 187 (Indiana Supreme Court, 1875)

Cite This Page — Counsel Stack

Bluebook (online)
42 Ind. 134, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gulick-v-connely-ind-1873.