Gulf States Utilities Co. v. Public Utility Commission

947 S.W.2d 887, 1997 WL 35784
CourtTexas Supreme Court
DecidedJuly 31, 1997
Docket94-1229
StatusPublished
Cited by42 cases

This text of 947 S.W.2d 887 (Gulf States Utilities Co. v. Public Utility Commission) is published on Counsel Stack Legal Research, covering Texas Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gulf States Utilities Co. v. Public Utility Commission, 947 S.W.2d 887, 1997 WL 35784 (Tex. 1997).

Opinion

HECHT, Justice,

delivered the opinion of the Court.

In Docket 7195, the Public Utility Commission considered but refused to decide whether Gulf States Utilities Company was entitled to include in its rate base $1,453 billion in costs to construct the River Bend Nuclear Generating Plant, even though the issue was fully litigated. Instead, having allowed some *888 of GSU’s costs, the PUC attempted to defer the issue to a subsequent proceeding. In Coalition of Cities for Affordable Utility Rates v. Public Utility Commission, 798 S.W.2d 560 (Tex.1990), cert. denied, 499 U.S. 983, 111 S.Ct. 1641, 113 L.Ed.2d 736 (1991), we held that res judicata and collateral estop-pel barred relitigation of the issue. The question now before us, not present in Coalition of Cities, is whether the PUC erred in refusing to decide the issue in Docket 7195 so that its final order must be reversed. The district court and court of appeals concluded that the PUC did not err. 883 S.W.2d 739. We disagree.

I

GSU, an electric utility serving customers in southeastern Texas and south central Louisiana, announced its plans to construct River Bend in 1971. The plant was completed at a total' cost of nearly $4.5 billion and began commercial operation in 1986. GSU owns a seventy percent interest in the plant.

GSU applied to the PUC to include some $3 billion of its River Bend construction costs in its cost of service and to increase its rates accordingly. In this proceeding, Docket 7195, after hearing testimony from over 100 witnesses for 132 days, the examiners issued a 395-page report recommending to the PUC that only nine percent — about $274 million— of GSU’s costs “should be excluded from GSU’s rate base as invested capital not used and useful in rendering service to the public”. There was extensive evidence supporting inclusion of all GSU’s costs in its rate base and extensive contrary evidence that most of those costs should be excluded.

The PUC did not adopt the examiners’ report. The Commission agreed that $2,273 billion of River Bend construction costs were reasonably and prudently incurred, and that GSU’s seventy-percent share of those costs, $1,591 billion, should be included in its rate base. But the Commission found that “[t]he evidence is inadequate to support a finding of either prudence or imprudence with regard to construction costs in excess of $2,273 billion [with two minor exceptions].” Despite GSU’s failure of proof, the Commission expressly refused to exclude the balance of GSU’s costs from its rate base. The Commission also apparently rejected the possibility of remanding the case to the examiners, 16 Tex. Admin. Code § 22.262(c) (West 1996), after GSU’s counsel indicated that a remand was “unnecessary”. Instead, the Commission believed it could defer ruling until a later proceeding.

Accordingly, the PUC in its final order found that “GSU’s share of all River Bend capital costs in _ excess of $2,273 billion”— $1,453 billion — “should be excluded from plant in service at this time for lack of sufficient evidence as to the prudence and reasonableness of those costs.” (Emphasis added.) The PUC concluded: “[T]he Commission may reexamine on rehearing or in a subsequent proceeding the prudence and reasonableness of those River Bend construction costs regarding which the evidence is inadequate to support a finding of either prudence or imprudence.” Chairman Thomas dissented from the Commission’s decision “to hold in abeyance $1,453 billion' of the investment in the River Bend Nuclear Power Plant, to allow the Company an opportunity to prove construction prudence on rehearing.” Chairman Thomas would have disallowed $459 million of excess costs and excluded $495 million in costs for excess capacity until that capacity became used and useful.

Three things are clear about the PUC’s final order in Docket 7195. First, the PUC intended that the order would end the proceeding, except for any motions for rehearing. Second, the PUC intended not to decide whether $1,453 billion of River Bend costs should be included in GSU’s rate base. The Commissioners took particular care that no comment during the public hearing be construed as implying a disallowance of the $1,453 billion, rather than a deferral. Third, the PUC contemplated that GSU could initiate a separate proceeding to determine treatment of the $1,453 billion of costs.

GSU and other parties filed motions for rehearing, which were overruled by operation of law when the time expired for the PUC to rule on them. The following parties then sought judicial review in the district court: GSU; Coalition of Cities for Affordable Utility Rates (“CAUR”); the Office of *889 Public Utility Counsel (“OPC”); Cities of Beaumont, et al. (“Cities”); Texas Industrial Energy Consumers (“TIEC”); and the State of Texas. The district court consolidated all the petitions for judicial review.

While those petitions were pending, GSU initiated a new proceeding in the PUC, Docket 8702, to include in its rate base the $1,453 billion costs “held in abeyance” in Docket 7195. When the PUC indicated that it intended to proceed in Docket 8702, CAUR, OPC, and Cities petitioned the district court for declaratory and injunctive relief. The district court declared that res judicata and collateral estoppel barred relitigation of the issues GSU raised in Docket 8702 and enjoined the PUC from going forward in that proceeding.

GSU and the PUC appealed. The PUC argued:

Since the Commission has clearly expressed its reservation of the prudence determination of $1.45 billion of River Bend’s costs, the district court’s attempt to construe the Commission’s order otherwise is an impermissible substitution of its judgment for that of the Commission. The district court is itself essentially determining that $1.45 billion of GSU’s investment in River Bend are permanently disallowed from rate base. It is well settled that a court may not substitute its judgment for that of the administrative agency. As shown above, the Commission’s final order does not state such a finding nor does it operate to permanently exclude $1.45 billion from rate base. The Commission’s conclusion that GSU did not meet its burden of proving that the $1.45 billion were prudent cannot be interpreted as a final determination of the issue. Too many contingencies are left when that conclusion is read alongside other parts of the order.
í}í Hí ❖ * &
The myriad of possibilities as to the amount the Commission would have included in or excluded from rate base had it decided not to defer part of River Bend’s costs precludes the court’s and Appellees’ conjectures as to the possible final outcome.

(Citations and footnotes omitted.) CAUR, OPC, and Cities argued that the PUC’s finding that GSU had failed to meet its burden of proof amounted to an adjudication of the issue regardless of the PUC’s attempt to defer ruling.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Farrakhan v. State
263 S.W.3d 124 (Court of Appeals of Texas, 2007)
Quanell X Abdul Farrakhan v. State
Court of Appeals of Texas, 2006
Mei-Chiao Chen Wu v. City of San Antonio
216 S.W.3d 1 (Court of Appeals of Texas, 2006)
City of Port Neches v. Railroad Commission of Texas
212 S.W.3d 565 (Court of Appeals of Texas, 2006)
Centerpoint Energy Entex v. Railroad Commission of Texas
213 S.W.3d 364 (Court of Appeals of Texas, 2006)
Texas Department of Public Safety v. Alford
154 S.W.3d 133 (Court of Appeals of Texas, 2005)
Entergy Gulf States, Inc. v. Public Utility Commission of Texas
112 S.W.3d 208 (Court of Appeals of Texas, 2003)
Ramirez v. Texas State Board of Medical Examiners
99 S.W.3d 860 (Court of Appeals of Texas, 2003)
Flores v. Employees Retirement System of Texas
74 S.W.3d 532 (Court of Appeals of Texas, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
947 S.W.2d 887, 1997 WL 35784, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gulf-states-utilities-co-v-public-utility-commission-tex-1997.