Gulf Pacific Contracting, LLC

CourtArmed Services Board of Contract Appeals
DecidedSeptember 16, 2021
DocketASBCA No. 61434
StatusPublished

This text of Gulf Pacific Contracting, LLC (Gulf Pacific Contracting, LLC) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gulf Pacific Contracting, LLC, (asbca 2021).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Gulf Pacific Contracting, LLC ) ASBCA No. 61434 ) Under Contract No. FA4417-16-D-0002 )

APPEARANCE FOR THE APPELLANT: Laurence J. Zielke III, Esq. Zielke Law Firm, PLLC Louisville, KY

APPEARANCES FOR THE GOVERNMENT: Jeffrey P. Hildebrant, Esq. Air Force Deputy Chief Trial Attorney Christopher M. Judge-Hilborn, Esq. Maj Michelle E. Gregory, USAF Trial Attorneys

MAJORITY OPINION BY ADMINISTRATIVE JUDGE PROUTY

The Davis-Bacon Act, 40 U.S.C. §§ 3131-3148, is a fact of life in federal government construction contracting. By requiring the payment of local prevailing wages to contractor employees in certain circumstances, it may force contractors to pay their employees more than they might otherwise when they begin contract performance and to further increase wages in the midst of performance or following the exercise of options by the government. The Federal Acquisition Regulation (FAR) provides a contracting officer (CO) multiple ways to address these increased costs through prescribed clauses to be inserted into a contract. One such clause (which we will refer to as “the no-adjustment clause” throughout) takes the approach of informing the contractor that there will be no adjustment to the prices in the awarded contract unless it is provided for elsewhere in the contract, which implies that (unless there is a separate contract provision saying otherwise) the contractor should price its option years to take into account the risk of increased wages. That is the clause that was included in the above- captioned contract (the contract) which is the subject of today’s dispute.

This appeal is before us under the auspices of Board Rule 11, which permits its resolution on the record, without a hearing and live testimony. As detailed below, appellant, Gulf Pacific Contracting, LLC (Gulf Pacific), had a contract to perform various construction-related services at Hurlburt Field in Florida. Coincident with the government’s exercise of its first option year, the Department of Labor (DOL) issued new wage determinations, with the upshot being that Gulf Pacific needed to pay some of its employees more during the option period. Gulf Pacific demanded additional

1 compensation from the government and the CO refused, pointing to the no-adjustment clause, which precluded such additional payment. Gulf Pacific appeals this decision, arguing that it was not on notice that it would be required to absorb this cost in its option pricing and that the no-adjustment clause is defective.

Judge Clarke agrees with Gulf Pacific, contending that the FAR-required no-adjustment clause contained in the contract did not meet the requirements of the policy portion of the FAR which set forth the CO’s options for addressing wage adjustments. We respectfully disagree with Judge Clarke. The drafters of the FAR made the no-adjustment clause consistent with their earlier dictates about how to handle such situations. Gulf Pacific also argues that the no-adjustment clause is ambiguous. It is not. Gulf Pacific, as discussed below, is entitled to no additional compensation.

FINDINGS OF FACT

On September 26, 2016, the United States Air Force 1st Special Operations Contracting Squadron awarded to Gulf Pacific the contract, a firm-fixed-price, indefinite- delivery indefinite-quantity (IDIQ) construction contract, to paint the interior of facilities, paint the exterior of facilities, and stripe runway pavement at Hurlburt Field in Florida (R4, tab 4 at 1-4). The base period of performance was one year, with four option years (id. at 5-6).

As part of the solicitation that led to the award of the contract, offerors were required to provide prices for the base year and each option year, and those prices were to come from a “Line Item List” attached to the solicitation that the contractor was to fill out (app. supp. R4, tab 14 at 4-6). The Line Item List is an extensive 15-page document and includes services that may be ordered under separate contract line items, estimated quantities of those services, and space for the contractor to insert its pricing. It includes separate pricing lists for the base year and all four individual option years. (See R4, tab 4a) In its initial bid, Gulf Pacific, in fact, priced some components of its option years 1 differently than the base year (compare R4, tab 11 at 13-15 to R4, tab 11 at 19-21). A number of Gulf Pacific’s prices in the line items went down between the base year and the option years – enough for the government to raise the issue with Gulf Pacific during pre-award discussions. In response to these concerns, Gulf Pacific ascribed the decreased

1 Based on the parties’ discussions during the government’s consideration of Gulf Pacific’s proposal, we can conclude that there were changes in unit pricing between the base year and the option years as well (see R4, tab 2 at 3 (referencing discussions about variance in base and option years)), but the Line Item List for the base year, as completed by Gulf Pacific does not appear to be part of the record for us to report it directly. Apparently, neither party was able to find it during discovery (see gov’t br. at 6 n.1), but this is of no significance since the matter is not in dispute.

2 prices to its anticipated “increased production efficiency” as it performed the contract (R4, tab 2 at 3). To be clear, however, at least one 2 price component increased between option years 1 and 3 (compare CLIN 1004AG, located at R4, tab 11 at 15 to CLIN 3004AG, located at R4, tab 11 at 21).

The contract incorporates by reference FAR 52.222-6, CONSTRUCTION WAGE RATE REQUIREMENTS (MAY 2014) (R4, tab 4 at 14). In part, this provision requires “laborers and mechanics employed or working upon the site of the work will be paid unconditionally . . . at rates not less than those contained in the wage determination of the Secretary of Labor which is attached hereto and made a part hereof.” FAR 52.222- 6(b)(1)

The contract also incorporates by reference FAR 52.222-30, CONSTRUCTION WAGE RATE REQUIREMENTS—PRICE ADJUSTMENT (NONE OR SEPARATELY SPECIFIED METHOD) (MAY 2014) (R4, tab 4 at 14). This is the no- adjustment clause referenced herein. In relevant part, this provision inserts the following text into the contract:

(a) The wage determination issued under the Construction Wage Rate Requirements statute by the [DOL], that is effective for an option to extend the term of the contract, will apply to that option period.

(b) The Contracting Officer will make no adjustment in contract price, other than provided for elsewhere in this contract, to cover any increases or decreases in wages and benefits as a result of [such a wage determination]

FAR 52.222-30.

For the contract at issue here, there is no other mechanism for adjusting the option price to cover increases or decreases in wages caused by wage determinations “provided for elsewhere in th[e] contract” (see R4, tab 4). 3 For unknown reasons, the contract also incorporates by reference FAR 52.216-7, ALLOWABLE COST AND PAYMENT – ALT I (JUN 2013) (see R4, tab 4 at 14). This

2 The government identified this one particular increase, but no others, and we have not compared the remainder of the prices line by line as it is unnecessary for our decision today. 3 Gulf Pacific argues that two particular contract provisions may constitute mechanisms

to pay wage rate increases, which we will address in the Decision section, below, but identifies no provision establishing an entitlement to payment for wage rate increases.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Gulf Pacific Contracting, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gulf-pacific-contracting-llc-asbca-2021.