Gulf Atlantic Towing Corporation v. Dickerson, Inc., Miami Towing Company and Gulf Atlantic Towing Corporation v. Dickerson, Inc.

271 F.2d 542
CourtCourt of Appeals for the Fifth Circuit
DecidedDecember 15, 1959
Docket17533_1
StatusPublished
Cited by8 cases

This text of 271 F.2d 542 (Gulf Atlantic Towing Corporation v. Dickerson, Inc., Miami Towing Company and Gulf Atlantic Towing Corporation v. Dickerson, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gulf Atlantic Towing Corporation v. Dickerson, Inc., Miami Towing Company and Gulf Atlantic Towing Corporation v. Dickerson, Inc., 271 F.2d 542 (5th Cir. 1959).

Opinions

[544]*544TUTTLE, Circuit Judge.

On February 24, 1956, Gulf Atlantic Towing Corporation (GATCO) and Dickerson, Inc., a road contractor, entered into a written contract under which Gateo agreed to haul between 100,000 and 125,000 cubic yards of stone between a jpoint on Lake Okeechobee and one on the St. Lucie River. Dickerson was to pay 400 per cubic yard for the haulage. Both parties agree that the only significant parts of this contract are the following :

“1. Gateo Agrees:
“A. To transport by barges between One Hundred Thousand (100,-000) and One Hundred Twenty-five Thousand (125,000) cubic yards of limestone rock from a point approximately three (3) miles west of Bel Glade, Florida on Lake Okeechobee to a point approximately one-half mile east of St. Lucie Locks about seven (7) miles west of Stuart, Florida.
“B. To provide for such undertaking a minimum of two tugs and four barges. The barges will be such as can be unloaded by regular power crane with clam shell type bucket of one and one-half (1%) cubic yards capacity and shall be provided with protective mats of timbers not less than three by twelve (3 x 12) of sufficient dimensions to allow the unloading equipment to work from the same. To furnish a competent superintendent who shall devote his full time to expediting this project during the period of these presents.
******
“E. To operate the equipment herein described twenty-four (24) hours a day, seven (7) days each calendar week until the entire quantity of material is moved.”
“2. Dickerson Agrees:
“A. To pay Gateo forty (400) cents for each cubic yard of limestone rock moved by Gateo from the loading docks near Bel Glade to the barge berths and/or unloading docks, provided by Dickerson, just east of St. Lucie Locks, payment to be made by the 10th of the month for the quantities moved during the preceding month. The quantities are to be determined by truck count, Dickerson to furnish Gateo with copies of quarry delivery tickets.”

On May 26, 1956, a supplemental written agreement was entered into between the parties. The essential part of this agreement, in the form of a letter from Dickerson to Gateo, provided:

“This will confirm our conference of the 14th.
“In consideration of your providing and maintaining on the project described in the contract dated February 24,1956 between Gulf Atlantic Towing Corporation and Dickerson, Inc., the tugboat Gateo Georgia, or a comparable substitute in addition to the tugs and barges which you now have on such undertaking Dickerson, Inc. will thereafter pay sixty (600) cents per cubic yard instead of forty (400) cents per cubic yard as provided in subparagraph (a) of Paragraph 2 of said contract. Dickerson, Inc. will be permitted to continue or discontinue the use on said project of the tugboat Sampson and the Barge No. 1000 or comparable substitutes at its option.
“The increased rate per cubic yard referred to herein is to commence with the first load of limestone rock moved from the loading docks on the Lake Okeechobee terminus by the Gateo Georgia, or its comparable substitute.”

Alleging failure to perform in accordance with this written contract as amended, Dickerson brought suit for damages. In another proceeding, Miami Towing Company, to which Gateo had assigned part of the contract with Dickerson’s consent, filed suit against Dickerson for payment in accordance with the terms of the same written contract.

The trial court found Gateo and Miami Towing Company in default for failing to carry out the terms of their contract, [545]*545and after allowing credits for amounts not paid for the haulage, assessed net damages of $44,147.96, including interest against Gateo.

The controlling question presented by this appeal is whether in determining the standard of performance imposed on Gateo the court could, as it did, consider negotiations leading up to the signing of the contract and other circumstances surrounding the contractual obligations of Dickerson with third parties which were neither expressly incorporated, nor referred to, in the contracts sued upon.

If the trial court could legally consider these extraneous matters it is clear that the evidence supported (although contrary inferences might well have been drawn from some of the facts) the following findings of fact by the trial court:

“5. Although the writing dated February 24, 1956 did not specify the period of time within which Gateo was to complete the transportation of the limestone rock, at the time the agreement was negotiated and executed, Gateo had been informed by plaintiff and knew that the rock to be transported was that required for the performance of plaintiff’s contract with the Florida State Turnpike Authority, that plaintiff had only 150 calendar days after February 20, 1956, to complete its contract with the Turnpike Authority, that all the rock would have to be transported to the Stuart unloading dock at least thirty days before the expiration of the performance period in order for plaintiff to complete on time its contract with the Turnpike Authority, and that plaintiff was gearing its operations to handle 2,000 cubic yards of rock per day. Gateo represented to plaintiff that it could and would transport the rock in the quantities and within the time required by plaintiff’s needs under plaintiff’s contract with the Turnpike Authority. The agreement of February 20, 1956, was intended and understood by both parties thereto to be a contract for the transportation by Gateo of the rock in the quantities and within the time known by both parties to be required under plaintiff’s contract with the Turnpike Authority.
“6. * * * Soon after Gateo commenced transporting the* rock, it became apparent that the minimum equipment required by the agreement of February 24, 1956 was insufficient to transport the rock in the quantities required and within the time available to perform the job contemplated by Gateo and plaintiff, but Gateo failed to put additional equipment on the job.”

These findings obviously could not be supported if the obligation of the towing company was measured solely by the undertaking expressed in the writings between the parties. This is, of course, emphasized by the part of finding No. 6, “the minimum equipment required by the agreement of February 24, 1956, was insufficient to transport the rock in the quantities required and within the time available to perform the job contemplated by Gateo and plaintiff, but Gateo failed to put additional equipment on the job.” (Italics added.) It is for the failure to put equipment on the job additional to the minimum “required by the agreement” sued on by Dickerson that gave rise to the most substantial part of the damages fixed by the court, for the court held that it was Gatco’s obligation to move the full requirement of some 111,000 cubic yards of rock furnished by Dickerson at the loading ramp by June 15, 1956, because this was the date which the court found the parties “contemplated” when they signed the agreement.

The parties are not in controversy as to the basic principle of law which the courts must apply in a case such as this. In fact both briefs cite the same Florida and United States Supreme Court cases for the statement of the rule. In Ramey v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
271 F.2d 542, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gulf-atlantic-towing-corporation-v-dickerson-inc-miami-towing-company-ca5-1959.