Guardian Pipeline, L.L.C. v. 950.80 Acres of Land

486 F. Supp. 2d 741, 2007 U.S. Dist. LEXIS 33147, 2007 WL 1317175
CourtDistrict Court, N.D. Illinois
DecidedMay 2, 2007
Docket01 C 4696
StatusPublished
Cited by2 cases

This text of 486 F. Supp. 2d 741 (Guardian Pipeline, L.L.C. v. 950.80 Acres of Land) is published on Counsel Stack Legal Research, covering District Court, N.D. Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Guardian Pipeline, L.L.C. v. 950.80 Acres of Land, 486 F. Supp. 2d 741, 2007 U.S. Dist. LEXIS 33147, 2007 WL 1317175 (N.D. Ill. 2007).

Opinion

MEMORANDUM OPINION AND ORDER

MORAN, Senior District Judge.

Guardian Pipeline sought condemnation of numerous parcels of land for permanent and temporary easements for the construction of a pipeline in northeastern Illinois. An injunction was granted allowing Guardian to take immediate possession of the land, subject to Guardian posting a bond for payment of just compensation to the various property owners. The court appointed a commission for the purpose of holding the necessary hearings, which spanned a period of over two years. On July 6, 2006, the commission filed its report. Guardian and several sets of defendants have filed objections to the report. For the following reasons, we overrule those objections and adopt the report in its entirety.

BACKGROUND

On June 21, 2001, plaintiff Guardian Pipeline, Inc. (“Guardian”) filed a complaint for condemnation of easements against the owners of numerous properties in northeastern Illinois for the imposition of a natural gas pipeline pursuant to a certificate from the Federal Energy Regulatory Commission. Guardian amended its complaint six times, filing the Sixth Amended Complaint on February 5, 2003. This filing occurred after Guardian -had been granted condemnation on January 3, 2002, and immediate possession of the land through an injunction of this court on April 4, 2002.

On April 24, 2002, this court proposed the appointment of a commission to determine just compensation awards for defendant property owners, pending objection of the proposed commissioners from the parties. The appointment was confirmed in the court’s order of May 23, 2002, and instructions were issued to the commission. Hearings commenced on July 14, 2003, and concluded on August 30, 2005. There were thirteen attorney teams representing properties, 1 with one defendant representing himself. The owners of six properties did not appear and thus were defaulted.

On July 6, 2006, the Commission issued a 277-page report detailing its findings of just compensation on defendants’ land. Plaintiff Guardian, and the Cinquino, Porter, Figliulo, Ryan, Wormley, Morrissey and McHenry County Conservation District defendants filed objections to the report. Since the dates of those filings, the McHenry County Conservation District and the Ryan defendants have settled with Guardian, and so we do not consider their objections. 2

ANALYSIS

As five sets of defendants and Guardian have made objections, we attempt to consolidate similar objections, where possible, and deal with those general objections first. We then move on to objections re *745 lating to individual parcels of land. 3 For the sake of brevity, we note that we have omitted much of the factual background relating to each individual tract and only discuss those facts relevant to the specific objections. 4

Standard of Review

The parties do not agree on the standard of review. Some of the defendants claim that the standard of review is “clearly erroneous.” This was the correct standard until 2003, when the Federal Rule of Civil Procedure 53 was significantly amended. Currently, Rule 53(g)(2) states that “this court must decide de novo all objections to findings of fact made or recommended by a master unless the parties stipulate” otherwise. Rule 71A(h) adopts this standard of review for condemnation proceedings. The order of March 27, 2003, accompanying the amendments to the federal rules states that those amendments “take effect on December 1, 2003, and shall govern in all proceedings in civil cases thereafter commenced and, insofar as just and practicable, all proceedings then pending.” This proceeding was pending at the time these amendments took effect, but we find it both just and practicable to apply the de novo standard of review here. 5 Thus, we review de novo the findings of fact and conclusions of law objected to by the parties, and all other findings of fact and conclusions of law may, but need not be, reviewed de novo. Luma Corp. v. Stryker Corp., 2006 WL 285973, *3, 2006 U.S. Dist. LEXIS 7905, *12 (D.W.Va. Feb. 3, 2006) (citing Advisory Committee’s Notes on 2003 Amendments to Rule 53(g)).

Rule 53(g)’s — and thus Rule 71A’s — requirements for de novo review is consistent with the de novo standard of review for a magistrate judge’s report under Rule 72(b), United States v. Fairway Capital Corp., 433 F.Supp.2d 226, 232 (D.R.I.2006). Such review does not require the court to have a separate hearing to redetermine the credibility of parties, nor does it require that we accept additional evidence. De novo review requires more than a determination that the commission’s decisions were not clearly erroneous; it requires the court to find the commission’s decisions to be correct. However, “if following a review of the record the district court is satisfied with the [commission’s] findings ... it may in its discretion treat those Findings and recommendations as its own.” Coffman v. Gross, 59 F.3d 668, 671 (7th Cir.1995) (citing United States v. Raddatz, 447 U.S. 667, 675, 100 S.Ct. 2406, 65 L.Ed.2d 424 (1980)).

Denial of Due Process

Several defendants object to the commission’s hearings and subsequent report as a denial of their right to due process of law. They argue that they were denied an impartial tribunal by the appointment of this commission. First, defendants claim that the head of the commission, Thomas Ewert, should have been removed for a conflict of interest because, according to Martindale-Hubbell, his firm has repre *746 sented numerous pipeline companies throughout the years, including Guardian. We note that Ewert’s firm has not, in fact, represented Guardian. Upon receiving word of this allegation, Ewert researched the Martindale reference and spoke to the other lawyers at his firm. Ewert sent this court a letter stating that neither he nor anyone at his firm had ever represented Guardian, and that he believed the reason why Guardian was listed as a client was because he had been appointed to this commission and Guardian had been the party paying the commissioners’ fees. Thus, he concluded, the person in his office who compiled the list of clients for the website must have mistakenly listed Guardian among them because of Ewert’s role in the commission. We have no reason to doubt Ewert on this point and find no reason to disqualify him as commissioner.

Defendants argue that Ewert’s firm’s representation of various pipeline companies was not disclosed at the time of appointment, and thus he should be disqualified. We do not agree.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
486 F. Supp. 2d 741, 2007 U.S. Dist. LEXIS 33147, 2007 WL 1317175, Counsel Stack Legal Research, https://law.counselstack.com/opinion/guardian-pipeline-llc-v-95080-acres-of-land-ilnd-2007.