Guardian Moving & Storage Co. v. United States

39 Cont. Cas. Fed. 76,683, 31 Fed. Cl. 645, 1994 U.S. Claims LEXIS 147, 1994 WL 410058
CourtUnited States Court of Federal Claims
DecidedAugust 5, 1994
DocketNo. 93-303C
StatusPublished
Cited by2 cases

This text of 39 Cont. Cas. Fed. 76,683 (Guardian Moving & Storage Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Guardian Moving & Storage Co. v. United States, 39 Cont. Cas. Fed. 76,683, 31 Fed. Cl. 645, 1994 U.S. Claims LEXIS 147, 1994 WL 410058 (uscfc 1994).

Opinion

OPINION

ANDEWELT, Judge.

I.

In this government contract action brought pursuant to the Contract Disputes Act (CDA), 41 U.S.C. §§ 601-613, plaintiff, Guardian Moving & Storage Co., Inc., seeks to recover approximately $18,000 in bid preparation costs it incurred in preparing an unsuccessful bid proposal for a Department of Defense (DOD) contract. The contract in issue covered the interstate transportation of household goods of DOD employees based at Fort Meade, Maryland, during 1991. DOD awarded the contract to the low bidder, Eastern Moving & Storage Co., Inc. (Eastern). Plaintiff contends that the contracting officer should have rejected Eastern’s bid and awarded the contract to plaintiff, the second low bidder. Plaintiff alleges that Eastern’s bid was not responsive to the requirements of the bid solicitation and that Eastern was not a responsible bidder. When the United States accepts a bid in response to a solicitation, it enters into an implied-in-fact agreement to consider the bid fairly and honestly. Heyer Products Co. v. United States, 135 Ct.Cl. 63, 69, 140 F.Supp. 409 (1956). If the United States breaches this obligation, the unsuccessful bidder is normally entitled to recover its bid preparation costs. Id.

This action is presently before the court on defendant’s motion for summary judgment. For the reasons set forth below, defendant’s motion is granted.

II.

Plaintiffs criticism of the contracting officer’s award to Eastern focuses on the regulatory requirements of the Interstate Commerce Commission (ICC). Pursuant to 49 U.S.C. § 10921, a carrier must obtain authorization from the ICC for the interstate transportation of goods. The ICC can grant emergency temporary authority and temporary authority to a carrier, but only if there is no other carrier capable of meeting the immediate transportation needs of the area. 49 U.S.C. § 10928. The contract solicitation herein defined the contract area of performance and required the contractor to ship goods “beyond the contract area of performance, not to exceed 50 miles.” The contract shipping area included all or portions of the District of Columbia and the states of Maryland, Virginia, West Virginia, and Delaware. Consequently, the contract required ICC authorization for shipment to these areas.

Amendment 0002 of the solicitation, issued in response to plaintiffs request for clarification of the solicitation, stated that “[i]f [a prospective contractor] indicates that he/she does not hold authorization for interstate transportation for [the contract work], his/ her bid will be rendered nonresponsive.” Prior to award of the contract, Eastern submitted an application to the ICC requesting permanent authority, temporary authority, and emergency temporary authority for the entire contract shipping area except West Virginia. The ICC granted Eastern emergency temporary authority by telephone and later granted Eastern temporary authority. Although Eastern did not include West Virginia in its application, the ICC included West Virginia in its grant of temporary authority.

After bid opening but before contract award, plaintiff notified the contracting officer of its belief that the ICC had improperly granted Eastern emergency temporary authority, and that Eastern had not requested temporary authority for West Virginia. Thereafter, in December 27, 1990, letter, Eastern advised the contracting officer that it had in fact received ICC authority which included West Virginia. In a December 28, 1990, letter, the contracting officer notified plaintiff that he had contacted the ICC and had spoken to Marsha Archibald, Transportation Specialist, who confirmed that Eastern had been granted temporary authority for up to 120 days, and that there was no reason to believe ■ that Eastern would not ultimately obtain permanent authority. On that same day, after determining that Eastern’s bid was responsive and that Eastern was a responsible bidder, the contracting officer awarded Eastern the contract.

[647]*647On January 3, 1991, plaintiff filed a timely formal protest with the contracting officer alleging that Eastern lacked authority to operate in West Virginia and therefore had not submitted a responsive bid. The contracting officer denied plaintiffs protest and noted that the protest involved Eastern’s responsibility rather than responsiveness. In denying the protest, the contracting officer found that the contract would not require services in West Virginia, and in any event, that “responsibility determinations have been approved when necessary licenses and permits were not anticipated until after the award.”

Plaintiff filed several more protests, none of which were timely, and ultimately filed a petition with the ICC requesting reconsideration of its decision to grant Eastern temporary authority. Before denying plaintiffs petition, the ICC granted Eastern permanent authority to operate within the contract area. (The record does not indicate whether the permanent authority included West Virginia.) Upon plaintiffs appeal, on January 14, 1992, the United States Court of Appeals for the District of Columbia Circuit vacated the ICC’s award of emergency temporary authority and temporary authority as inconsistent with ICC regulations. Guardian Moving & Storage Co. v. ICC, 952 F.2d 1428 (D.C.Cir.1992). The court, however, did not overturn the ICC’s grant of permanent authority. The court reached the issue of the validity of the prior temporary grants because the court was concerned that unless it clarified the law, the ICC would continue to disregard its own regulations. Id.

III.

To recover its bid preparation costs, plaintiff must show that the government breached it obligation to consider plaintiffs bid fairly and honestly. Plaintiff must show that the contracting officer acted in an arbitrary and capricious manner when he determined that Eastern’s bid was responsive and that Eastern was a responsible bidder. See National Forge Co. v. United States, 779 F.2d 665, 667 (Fed.Cir.1985); Keko Industries, Inc. v. United States, 192 Ct.Cl. 773, 782, 428 F.2d 1233, 1237 (1970). A showing of simple negligence is not enough to establish that the government’s conduct was arbitrary and capricious. Rather, plaintiff must show that the contracting officer’s decision was “irrational or totally lacking in reason.” Keko Industries, Inc. v. United States, 203 Ct.Cl. 566, 579, 492 F.2d 1200, 1206 (1974).

A grant of summary judgement is appropriate only where there is no genuine issue of material fact (i.e., a fact that might affect the outcome of the suit) and the movant is entitled to judgment as a matter of law. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247, 106 S.Ct. 2505, 2509-10, 91 L.Ed.2d 202 (1986).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

MG Altus Apache Co. v. United States
111 Fed. Cl. 425 (Federal Claims, 2013)
Ncl Logistics Company v. United States
109 Fed. Cl. 596 (Federal Claims, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
39 Cont. Cas. Fed. 76,683, 31 Fed. Cl. 645, 1994 U.S. Claims LEXIS 147, 1994 WL 410058, Counsel Stack Legal Research, https://law.counselstack.com/opinion/guardian-moving-storage-co-v-united-states-uscfc-1994.