Grumman Ecosystems Corp. v. Gainesville-Alachua County Regional Electric, Water & Sewer Facilities Board

402 F. Supp. 582, 10 ERC 1863
CourtDistrict Court, N.D. Florida
DecidedOctober 1, 1975
DocketCiv. A. 75-23
StatusPublished
Cited by4 cases

This text of 402 F. Supp. 582 (Grumman Ecosystems Corp. v. Gainesville-Alachua County Regional Electric, Water & Sewer Facilities Board) is published on Counsel Stack Legal Research, covering District Court, N.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Grumman Ecosystems Corp. v. Gainesville-Alachua County Regional Electric, Water & Sewer Facilities Board, 402 F. Supp. 582, 10 ERC 1863 (N.D. Fla. 1975).

Opinion

OPINION

STAFFORD, District Judge.

This case involves a challenge of bid procedures by an unsuccessful bidder. The plaintiff, Grumman Ecosystems Corporation (Grumman), challenges the award of a construction contract for the Kanapaha Wastewater Treatment Plant by the City of Gainesville, Florida. The defendants are: Norflor Construction Corporation-Sunshine Peninsula, Inc. (Norflor); The City of Gainesville, Florida (City); the Gainesville-Alachua County Regional Electric, Water and Sewer Utilities Board (Regional Board); and Russell E. Train, as Administrator of the Environmental Protection Agency (EPA). The City awarded the construction contract to Norflor, and that award was affirmed by EPA in an administrative appeal taken by Grumman. Grumman here challenges the award to Norflor on three grounds, set forth respectively in Counts I, II and III of its Amended Complaint. First, Grumman contends that Norflor’s bid was unresponsive at the time of bid opening and that the award to Norflor was therefore in violation of EPA regu *584 lations. See 40 CFR 35.938(f),(h). 1 Second, Grumman asserts that the City violated EPA regulations by not providing written findings substantiated by legal and engineering opinions. See 40 CRF 35.939 (a)_. Third, Grumman asserts that EPA violated its own regulations and those of the Comptroller General by notifying the City on August 1, 1975, that it was free to proceed with the execution of the contract with Norflor, when in fact EPA was aware of a pending appeal of its administrative decision to the Comptroller General. See 4 CFR 20.4; 40 CFR 35.939(d). Grumman seeks a declaratory judgment that the City and the Regional Board acted arbitrarily and capriciously in awarding the contract to Norflor, that the award to Norflor is void, that EPA acted arbitrarily in affirming the award, and that EPA violated its own regulations and those of the Comptroller General in subsequently allowing the City to proceed to execution of the contract at a time when an appeal to the Comptroller was pending. Grumman also seeks to enjoin funding and construction of the project and to enjoin the City to either award the contract to Grumman or rebid the contract.

The case is before the Court for final hearing, a temporary restraining order and preliminary injunction having previously been denied, for reasons more fully set forth below.

Before proceeding to findings of fact, a brief history of this litigation is in order, since the course of the litigation bears upon the Court’s judgment.

This case was begun by an application for Temporary Restraining Order on August 7, 1975. The application was on extremely short notice to opposing parties. The parties were orally advised of the hearing one day in advance, but the complaint was not filed until one hour before commencement of the hearing. The complaint then before the Court contained only the matters now set forth in Count I of the Amended Complaint— allegations relating to the unresponsiveness of Norflor’s bid. No mention was made in the complaint or at the hearing of other alleged violations of federal regulations. The application for Temporary Restraining Order was denied for failure to join the City and for failure to present a clear case for such relief.

On August 20, 1975, Grumman served by mail an amended complaint setting forth for the first time Grumman’s contentions concerning procedural irregularities by the City and EPA. Notice of a hearing on Grumman’s application for preliminary injunction was served by mail on August 21.

The hearing was set for August 27, 1975. At that hearing the Court declined to consider the merits of Grumman’s application, for lack of due notice to the defendants under Rule 6 of the Federal Rules of Civil Procedure. Further, the Amended Complaint was not verified nor were supporting affidavits filed, although an officer of Grumman testified as to the status of work then underway on the project in Gainesville. 2 The Court accelerated the matter for fi *585 nal hearing in accordance with Rule 65(a)(2) of the Federal Rules of Civil Procedure. Final hearing was held on September 22, 1975.

Findings of Fact

Prior to May 22, 1975, the City promulgated bidding instructions for the construction of the Kanapaha Wastewater Treatment Plant. The plant was to be constructed in Gainesville, Florida. EPA agreed to fund a major portion of the project by a grant, with the rest of the funding to come from local tax revenues. Of critical importance to the project was a Denitrification Filter System, a relatively new and untested piece of hardware. The City therefore required a process guarantee of five elements of the system from the system manufacturer. Initially, the manufacturer was also to be required to post a $250,000 escrow fund to secure the City for modifications in the system if it proved faulty in operation. Those requirements were contained in paragraph DF-03 of the bid instructions.

During the time when bidders were preparing their bids, the filter system manufacturer informed all bidders and the City that it would not provide the $250,000 escrow fund, and further, that it would not guarantee all of the five system components as specified in paragraph DF-03.

On May 22, the City modified the bid by means of “Addendum No. 6”, which stated in pertinent part:

“Only those bids providing an escrow account and a process guarantee, both in full accordance with par. DF-03 of these specifications, will be considered as being totally responsive. Any deviation from Section DF shall be specifically noted and attached to the Bidder’s Proposal.
“In the event that the filter supplier does not furnish such escrow account to the contractor, the contractor must provide the escrow account.” (emphasis supplied)

When the bids were opened, Norflor had submitted the apparent low bid. Grumman’s bid was $33,000 higher. However, Norflor’s bid contained the following handwritten notation:

“Per Addendum No. 6, page B-6, para. B-ll, sub para. A-7, our proposal deviates from this section as to the process guarantee. See attached process guarantee by Dravo [the manufacturer], pages 16-18. However, the escrow fund will be supplied by the contractor.”

This language is the genesis of the controversy. Grumman contends that by such language Norflor attempted to limit its liability under the escrow fund to those elements of the filter system which the manufacturer would guarantee.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
402 F. Supp. 582, 10 ERC 1863, Counsel Stack Legal Research, https://law.counselstack.com/opinion/grumman-ecosystems-corp-v-gainesville-alachua-county-regional-electric-flnd-1975.