Groves-Watkins Const. v. State, Dept. of Transp.

511 So. 2d 323, 12 Fla. L. Weekly 1465, 1987 Fla. App. LEXIS 10649
CourtDistrict Court of Appeal of Florida
DecidedAugust 4, 1987
DocketBR-163
StatusPublished
Cited by4 cases

This text of 511 So. 2d 323 (Groves-Watkins Const. v. State, Dept. of Transp.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Groves-Watkins Const. v. State, Dept. of Transp., 511 So. 2d 323, 12 Fla. L. Weekly 1465, 1987 Fla. App. LEXIS 10649 (Fla. Ct. App. 1987).

Opinion

511 So.2d 323 (1987)

GROVES-WATKINS CONSTRUCTORS, Appellant,
v.
STATE of Florida, DEPARTMENT OF TRANSPORTATION, Appellee.

No. BR-163.

District Court of Appeal of Florida, First District.

June 11, 1987.
On motion for Rehearing August 4, 1987.

*325 David S. Dee of Carlton, Fields, Ward, Emmanuel, Smith, Cutler & Kent, P.A., Tallahassee, for appellant.

Robert I. Scanlan, Deputy General Counsel, Dept. of Transp., Tallahassee, for appellee.

SMITH, Judge.

We must determine in this contract bid dispute whether the original low bidder on a highway construction project is entitled to award of a contract for the project where the Department of Transportation, after receipt of the initial bids, rejected all bids as excessive and directed that the project be rebid. An administrative hearing officer assigned to hear the case found that the original low bidder, appellant, was entitled to award of the contract; but the department in its final order declined to adopt the decision of the hearing officer, and denied the award. We reverse.

Appellant, Groves-Watkins Constructors (G-W), contends that the Department of Transportation (DOT) erred in two respects in dismissing its administrative bid protest. First, G-W contends that DOT violated section 120.57(1)(b)9, Florida Statutes (1985), by reweighing the evidence, rejecting the hearing officer's findings of fact, and substituting its own findings of fact even though the hearing officer's findings are supported by competent, substantial evidence in the record. Next, G-W contends that DOT committed reversible error when it based its decision to dismiss G-W's bid protest on new legal and factual issues raised by DOT for the first time in its final order.

G-W is a joint venture comprised of two large corporations which joined together for the purpose of bidding on certain DOT projects, among them "Package U", at issue in this case. Package U involves the construction of a complex highway interchange in Broward County which includes a substantial amount of embankment and many bridges, six of which will be built with pre-cast concrete segments. Three joint ventures bid on Project U, and G-W's bid of $54,472,335.15 was the lowest.

DOT's non-rule policy dictates that, for projects valued at more than $250,000, a contract will be automatically awarded if the lowest bid is no more than seven percent (7%) above DOT's estimate of the project's value. If the lowest bid is more than seven percent (7%) above the DOT estimate, the bidding process is reviewed by DOT, and DOT may or may not award the contract, depending on the circumstances. In this case, DOT's bid estimate for Package U was approximately $41.5 million, making G-W's bid twenty-nine percent (29%) over the bid estimate. When DOT notified G-W of its intent to reject G-W's bid because it was too high and more than seven percent above DOT's estimate, G-W filed a formal bid protest, contending that DOT's bid estimate was arbitrarily and unreasonably low. G-W petitioned for and was granted a formal administrative hearing. Thereafter, the hearing officer entered a comprehensive recommended order setting forth extensive findings of fact substantially establishing the correctness of G-W's contentions, and concluding that G-W was entitled to award of the contract. DOT rejected these findings and conclusions and denied the relief sought by G-W. This appeal followed.

The parties agree that there are three items which accounted for most of the discrepancy between DOT's estimate and G-W's bid: (1) the embankment material; (2) the pre-cast concrete bridge segments; and (3) mobilization costs. These discrepancies, in the aggregate, amount to approximately $12.2 million, and account for approximately 95% of the difference between G-W's bid and DOT's estimate.

At the outset, the hearing officer found that G-W has a substantial amount of experience in performing the work involved in Project U and has unique experience in the design, construction, estimating and bidding involving segmented, precast concrete bridges. By contrast, the hearing officer found that DOT had very little experience with segmented bridge construction, especially with regard to the complex-curved segmented bridge construction involved in Package U.

*326 The hearing officer found that G-W arrived at its bid on the embankment fill by using historical data and site-specific data, which was acquired by personally contacting suppliers and subcontractors in the surrounding area of the job site and which was verified only one to two days before the bid submittal. In contrast, the hearing officer found that in arriving at its bid estimate, DOT used historical cost data which involved noncomparable projects, and site-specific data which was outdated. The hearing officer noted that the bids received for embankment on a project known as Package M, a substantially identical interchange located fifteen miles from Package U, were higher than G-W's bid for embankment in Project U, thus corroborating G-W's showing that its embankment bid on Package U was a reasonable one, and based upon the most current market prices, and further, that DOT's estimate was based on out-of-date, not entirely comparable cost information, and is inaccurate. Based on the evidence presented the hearing officer found that DOT underestimated the embankment material costs by $6,000,000.

Next, the hearing officer accepted the expert testimony of Richard Kelly, the executive vice president of Groves, that on a scale of 1 to 10, the bridgework on Package U would rate at least a "9" in difficulty of execution. DOT arrived at its estimate for the bridge segment portion of this project after retrieving historical price data from its computer concerning other Florida bridge construction projects such as the Sunshine Skyway Bridge and the bridges in the Florida Keys. However, the hearing officer found that these bridges did not present difficulties in construction comparable to the bridges in Package U, in that they were built over water, under conditions of light traffic, and were relatively straight bridges as opposed to the curved bridge surfaces in Project U. On the other hand, G-W's bid price for bridge segments was based on actual quotes from local materialman, suppliers and subcontractors and these quotes were evaluated in light of the historical data and experience that G-W has accumulated in working on other segmental bridge projects. G-W based its price for the bridge segments on: (1) the cost of manufacturing the segments, including labor and equipment; (2) the cost of storing and transporting segments once they were cast; (3) the cost of erecting, grouting, and posttensioning the segments; and (4) the cost involved in subcontracting the painting and finishing work on the bridge surfaces after the segments were erected. The hearing officer found that:

The use of these four factors in Groves' arriving at its price for the segmental portion of the project was thus demonstrated to be reasonable and appropriate. DOT did not challenge the propriety of including these four factors in the estimate of the direct cost for the bridge work and offered no evidence suggesting that the costs assigned to these four elements were inappropriate.

He also found:

The evidence does not clearly reveal the specific manner in which DOT formulated its estimate for the bridge segment portion of this project other than its reliance upon historical pricing information for other bridge-interchange construction projects.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mercedes Lighting and Electrical Supply, Inc. v. DEPT. GEN. SERV.
560 So. 2d 272 (District Court of Appeal of Florida, 1990)
DOT v. Groves-Watkins Constructors
530 So. 2d 912 (Supreme Court of Florida, 1988)
Caber Systems, Inc. v. Department of General Services
530 So. 2d 325 (District Court of Appeal of Florida, 1988)
Bayonet Point Reg. Med. Ctr. v. Dhrs
516 So. 2d 995 (District Court of Appeal of Florida, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
511 So. 2d 323, 12 Fla. L. Weekly 1465, 1987 Fla. App. LEXIS 10649, Counsel Stack Legal Research, https://law.counselstack.com/opinion/groves-watkins-const-v-state-dept-of-transp-fladistctapp-1987.