Culpepper v. Moore

40 So. 2d 366, 1949 Fla. LEXIS 1372
CourtSupreme Court of Florida
DecidedMay 6, 1949
StatusPublished
Cited by14 cases

This text of 40 So. 2d 366 (Culpepper v. Moore) is published on Counsel Stack Legal Research, covering Supreme Court of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Culpepper v. Moore, 40 So. 2d 366, 1949 Fla. LEXIS 1372 (Fla. 1949).

Opinions

Suit by Jack Culpepper, as citizen and taxpayer of school district, against Walter T. Moore, Jr., and others, as and constituting the members of the Board of Public Instruction of Leon County, Fla., and A.D. Albritton, operating and doing business under the firm name and style of Albritton-Williams, to have contract between the board and A.D. Albritton for construction of public school building declared invalid, for an accounting from board for moneys paid on contract, and for decree enjoining board from making further payments thereunder. From an adverse decree, the plaintiff appeals.

Decree affirmed. The appeal is from a final decree in favor of the defendants below.

The appellant Culpepper, a general building contractor, was the lowest "dollars-and-cents" bidder at the letting of a contract for the construction of a public school building in Leon County, Florida. After considering all bids submitted, the County Board of Public Instruction rejected the bid submitted by Culpepper and awarded the contract to one A.D. Albritton, the next lowest bidder, whom the Board found to be the "lowest responsible bidder." Albritton began work under his contract and thereafter Culpepper, in the capacity of a citizen and taxpayer of the school district in which the building was being erected, instituted a suit in equity against the members of the Board and Albritton for the purpose of having the contract between the defendants declared invalid, for an accounting from the Board for moneys paid on the contract, and for a decree enjoining the Board from making further payments thereunder.

The amended bill upon which the parties went to trial charged, in substance, that in considering the bids submitted by various contractors the Board had "ignored" the low bid submitted by Culpepper, because of a "vindictive desire to satisfy some pique, peeve or personal spite with and toward" Culpepper; that the Board had announced as the reason for awarding the contract to Albritton that he had agreed to construct the building in a shorter time than that agreed by Culpepper but that the reason given was "a mere pretext or excuse without foundation in law or in fact, and in reckless disregard of the public interest;" that the finding of the Board that Albritton was the "lowest responsible bidder" was contrary to law; and that the award of the contract to Albritton was such an arbitrary and unreasonable abuse of the discretion vested in the Board in respect to such matters as to render the contract nugatory.

On the day fixed for taking testimony before the chancellor the plaintiff amended his amended bill of complaint by alleging that in awarding the contract to Albritton instead of to Culpepper, the Board had improperly considered "as a major and influencing factor" the fact that Albritton had offered to complete the contract in a lesser time than that agreed by Culpepper, but that the "time factor" was not a proper element for consideration in awarding the contract, because of the fact that at the time notice was published of invitations to contractors to bid on the project the plaintiff "was not advised, either by the terms of said invitation for bids or by anyone in authority acting for the defendants School Board, that any preferential consideration would be given to the contractor who would propose and agree to construct said school building under the terms of said contract in a shorter period of time than that required by the invitation for bids; a period of twelve months from the date of the execution of the contract." *Page 368

The defendants filed answers denying the material allegations of the amended bill as amended at the hearing, and evidence was submitted on the issues. At final hearing the chancellor found that the evidence wholly failed to sustain the allegations of the bill with respect to bad faith or improper or illegal motives on the part of the Board; that the Board had acted within its authority and discretion in adjudging Albritton to be the "lowest responsible bidder;" that though the Board had considered the proposed time of completion of the project as an important factor in determining the "lowest responsible bidder" it had not abused its discretion in doing so, in view of the pressing need for an early completion of the building and the fact that the bid forms submitted to contractors on which to make their proposals for contract gave notice on their face that the time element was to be considered as a competitive factor. Based upon these findings the chancellor entered a decree dismissing the bill of complaint.

The first contention made by the appellant on the appeal is that there was no substantial evidence before the Board at the time the contract was let, upon which the Board in the exercise of a lawful and sound discretion could have reached the conclusion that Albritton was the "lowest responsible bidder."

We cannot agree with the appellant in this particular. The hearings in the case were conducted before the chancellor. It was his duty and province to reconcile the conflicts in the evidence and to base his decree upon the evidence he found to be true. There was evidence presented to him that the Board of Public Instruction of Leon County had funds on hand derived from a bond issue, for the purpose of constructing public school buildings in Leon County. The Board advertised for bids to be received on April 28, 1948, for the construction of two schools, one to be known as South City Elementary School (the school involved in this litigation) and the other to be known as Bond Elementary School. The published notice for bid provided "Work shall be commenced within 30 days after contract is executed and shall be completed within 12 months from that date," and also "all work shall be done in accordance with contract, plans, specifications and special provisions provided by the owner. Contract, plans, etc., may be examined at the office of the Board of Public Instruction, Leon County, Florida, at the County Court House, Tallahassee, Florida."

Among the contract documents provided for use in connection with the letting were forms for contractors to use in making bids; the one to be used in connection with the South City Elementary School being worded as follows:

"The undersigned bidder has carefully examined the form of contract, the general conditions, the specifications, the special conditions and the drawings for the construction of South City Elementary School, dated March 20, 1948, and also the site of the work, and will provide all necessary machinery, tools, apparatus, and other means of construction and do all the work and furnish all material called for by said specifications, general conditions, special conditions and drawings in the manner prescribed therein in said contract, and in accordance with the requirements of the Architect for the sum of $ ____.

"Certified check in the amount of $ ____ is enclosed.

"We propose to start the work within ____ days after contract is executed, and to finish the work in ____ days.

____________" Signed

When the sealed bids were opened at the letting on April 28, 1948, Culpepper was found to have submitted the low dollars and cents bid on each of the buildings and accordingly was awarded the contract as to each building.

A few days after the letting the Board executed a contract with Culpepper for the construction of the Bond Elementary School and Culpepper commenced work on the project. As to the South City Elementary School, however, Culpepper advised the Board a few days after notice that he had been awarded the contract that he had made a $10,000 error in calculating the cost of certain materials and hence would not execute a contract or construct the building *Page 369 in accordance with the bid he had submitted.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ago
Florida Attorney General Reports, 2002
Miami-Dade County v. Church & Tower, Inc.
715 So. 2d 1084 (District Court of Appeal of Florida, 1998)
DOT v. Groves-Watkins Constructors
530 So. 2d 912 (Supreme Court of Florida, 1988)
Groves-Watkins Const. v. State, Dept. of Transp.
511 So. 2d 323 (District Court of Appeal of Florida, 1987)
Capeletti Bros., Inc. v. STATE, DEPT. OF GEN. SERVICES
432 So. 2d 1359 (District Court of Appeal of Florida, 1983)
LIBERTY CTY. v. Baxter's Asphalt & Concrete, Inc.
421 So. 2d 505 (Supreme Court of Florida, 1982)
Marriott Corp. v. Metropolitan Dade County
383 So. 2d 662 (District Court of Appeal of Florida, 1980)
VOLUME SERVICES DIV., ETC. v. Canteen Corp.
369 So. 2d 391 (District Court of Appeal of Florida, 1979)
COUCH CONST. CO., INC. v. Department of Transp.
361 So. 2d 184 (District Court of Appeal of Florida, 1978)
HILLSBOROUGH CTY. AV. AUTH. v. Taller & Cooper, Inc.
245 So. 2d 100 (District Court of Appeal of Florida, 1971)
Mayes Printing Company v. Flowers
154 So. 2d 859 (District Court of Appeal of Florida, 1963)
William A. Berbusse, Jr., Inc. v. North Broward Hosp. Dist.
117 So. 2d 550 (District Court of Appeal of Florida, 1960)
City of Pensacola v. Kirby
47 So. 2d 533 (Supreme Court of Florida, 1950)

Cite This Page — Counsel Stack

Bluebook (online)
40 So. 2d 366, 1949 Fla. LEXIS 1372, Counsel Stack Legal Research, https://law.counselstack.com/opinion/culpepper-v-moore-fla-1949.