Grossman v. Sea Air Towers, Ltd.

513 So. 2d 686, 12 Fla. L. Weekly 2116, 1987 Fla. App. LEXIS 12141
CourtDistrict Court of Appeal of Florida
DecidedSeptember 1, 1987
Docket84-1649, 84-1650 and 84-1901
StatusPublished
Cited by14 cases

This text of 513 So. 2d 686 (Grossman v. Sea Air Towers, Ltd.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Grossman v. Sea Air Towers, Ltd., 513 So. 2d 686, 12 Fla. L. Weekly 2116, 1987 Fla. App. LEXIS 12141 (Fla. Ct. App. 1987).

Opinion

513 So.2d 686 (1987)

Melvin GROSSMAN and Bliss & Nyitray, Inc., Appellants,
v.
SEA AIR TOWERS, Limited, Appellee.

Nos. 84-1649, 84-1650 and 84-1901.

District Court of Appeal of Florida, Third District.

September 1, 1987.
Rehearing Denied October 26, 1987.

*687 Carey, Dwyer, Cole, Eckhart, Mason & Spring, Miami, and Mitchell Katler, for appellant Bliss & Nyitray, Inc.

Peters, Pickle, Flynn, Niemoeller & Downs and Steven R. Berger, Miami, for appellant Melvin Grossman.

Steel, Hector & Davis and Patricia A. Seitz, Miami, for appellee.

Before HUBBART, DANIEL S. PEARSON and FERGUSON, JJ.

REVISED OPINION

FERGUSON, Judge.

Defendants, Melvin Grossman, an architect, and Bliss & Nyitray, Inc. (Bliss), structural engineers, appeal from a judgment entered on a jury verdict in favor of plaintiff, Sea Air Towers, Limited (Sea Air), finding the defendants liable for damages caused by a construction "underdesign." Bliss also appeals from an adverse judgment of the court entered on Grossman's cross-claim for indemnity.

Sea Air hired Grossman to design a 357-unit luxury high-rise rental apartment building, to be located in Hollywood, Florida. Grossman hired Bliss to prepare the structural plans and specifications. It is undisputed that a deck of the building, open to heavy service vehicles, was underdesigned to support the traffic load and that as a result the deck eventually collapsed. The first issue at trial was whether the statute of limitations barred Sea Air's cause of action. The issue on the merits, assuming that the action was not time-barred, was who, as between the two defendants, should pay.

The evidence at trial showed that Grossman gave Bliss architectural specifications for the building, which called for a deck to serve as a bridge between the building's entrance and upper level service facilities. The design contemplated that uncompacted garbage would be transported to the outside of the building for street pickup by the city's waste department. The architectural design showed an extremely restricted traffic pattern which would prevent large heavy vehicles from entering and maneuvering on the deck. Bliss completed the structural plans in May, 1969.

In April, 1970, the deck was under construction when the concrete was poured and reinforcing bars were installed. Approximately two months later, and over a year after the structural plans had been completed, Sea Air retained a private garbage collection company. The new service required that 60,000-pound trucks use the deck to Sea Air's service facilities to pick up compacted trash[1] and garbage. Sea Air instructed Grossman to redesign the deck and entranceway to give larger trucks unrestricted access. Testimony was presented that Grossman sent Bliss revised drawings of the entrance changes which called for unrestricted vehicular traffic and that accordingly Bliss made structural revisions for changes to the boiler room and loading area.

*688 In September, 1970, Sea Air received its certificate of occupancy. Very soon thereafter there were cracks in the deck, leakage into the garage area below, and vibrations from the loading ramp area. Bliss made on-site inspections following complaints from Sea Air and concluded: "there is no condition here related to structural adequacy and no evidence of deflection as a result of overloading." The complained of conditions continued over a period of years.

The concrete deck finally collapsed on July 5, 1981. As a result there were interruptions and changes in Sea Air's building operations, particularly garbage disposal, parking, and deliveries. Construction repair work caused noise and dust which Sea Air claimed caused tenants to leave the building, resulting in business losses.

After a six-day trial, the jury returned a verdict in favor of Sea Air in the amount of $540,000 and assessed eighty percent of the fault against Bliss and twenty percent of the liability against Grossman.

Both defendants contend that the jury verdict on the liability question was not supported by the evidence; that the award of damages, based on lost income rather than net loss profits was erroneous; and that the cost to repair the collapsed deck and to increase its load capacity was an incorrect measure of damages. Bliss contends that the court's finding and judgment against it on Grossman's cross-claim for indemnity was contrary to law.

We first address those findings made by the jury which must be affirmed. The factual determination on the statute of limitations question, that Sea Air did not have notice of a latent defect in the underdesigned traffic deck prior to its collapse, is supported by the evidence. See Board of Trustees v. Caudill Rowlett Scott, Inc., 461 So.2d 239 (Fla. 1st DCA 1984), rev. denied, 472 So.2d 1180 & 1182 (Fla. 1985); Perez v. Universal Eng'g Corp., 413 So.2d 75 (Fla. 3d DCA 1982), remanded, 451 So.2d 463 (Fla. 1984). There is also evidence in the record to support the jury's determination that both Grossman and Bliss were liable for Sea Air's loss. A jury verdict which finds support in the record will not be disturbed on review. Helman v. Seaboard Coast Line R.R., 349 So.2d 1187 (Fla. 1977); Underwriters Nat'l Assurance Co. v. Harrison, 338 So.2d 58 (Fla. 3d DCA 1976).

On the first of two damage issues we affirm the judgment as to lost rents. Contrary to the appellants' contentions that the $299,543.33 lost rents award is based on gross rentals alone or speculation, there is evidence in the record, reasonably certain in nature, that the losses were substantial and that the jury deducted operating costs in arriving at the amount. F.A. Conner v. Atlas Aircraft Corp., 310 So.2d 352 (Fla. 3d DCA 1975), cert. denied, 322 So.2d 913 (Fla. 1975).

The second issue on damages is whether the cost of increasing the deck's load-bearing capacity should be an element of damages assessed against the architect and engineer for failing to advise Sea Air of a need for an increased structural capacity after the traffic pattern was redesigned to accommodate heavy service vehicles. It is significant on this point that neither the architectural specifications nor the structural design was deficient for the original intended purpose. The proper measure of damages, therefore, should have been the amount necessary to restore the deck to its original condition plus related losses occasioned by the interruption of or adverse impact on business operations. See Grossman Holdings Ltd. v. Hourihan, 414 So.2d 1037 (Fla. 1982) (for breach of contract to construct a specified product, the injured party can get compensatory damages for all unavoidable harm that builder had reason to foresee when contract was made, less unpaid contract price). Costs incurred in increasing the load capacity of the deck would have been the owners' responsibility even if there had been no negligence on the part of the defendants. See Temple Beth Sholom & Jewish Center, Inc. v. Thyne Construction Corp., 399 So.2d 525 (Fla. 2d DCA 1981) (if in course of making repairs owner adopts a more expensive design, recovery should be limited to what would have been reasonable cost of repair according to original design).

*689 Bliss seeks reversal of the trial court's judgment for Grossman on the latter's cross-claim for indemnity, contending that the jury's finding that Grossman was legally at fault bars indemnity.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Norman v. Ambler
46 So. 3d 178 (District Court of Appeal of Florida, 2010)
CAULKINS INDIATOWN CITRUS CO. v. Nevins Fruit Co., Inc.
831 So. 2d 727 (District Court of Appeal of Florida, 2002)
Bracha Holding, Inc. v. United States Small Administration
800 So. 2d 657 (District Court of Appeal of Florida, 2001)
NBC Aviation, Inc. v. Challenge Air Cargo, Inc.
637 So. 2d 390 (District Court of Appeal of Florida, 1994)
Grodin v. Orange Construction Corp.
627 So. 2d 501 (District Court of Appeal of Florida, 1993)
Nuta v. Genders
617 So. 2d 329 (District Court of Appeal of Florida, 1993)
Executive Elevator Service, Inc. v. Public Health Trust of Dade County
586 So. 2d 427 (District Court of Appeal of Florida, 1991)
Marina v. Leahy
578 So. 2d 382 (District Court of Appeal of Florida, 1991)
Masegian v. Hotelrama Associates
569 So. 2d 811 (District Court of Appeal of Florida, 1990)
Lochrane Engineering, Inc. v. Willingham Realgrowth Inv. Fund, Ltd.
552 So. 2d 228 (District Court of Appeal of Florida, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
513 So. 2d 686, 12 Fla. L. Weekly 2116, 1987 Fla. App. LEXIS 12141, Counsel Stack Legal Research, https://law.counselstack.com/opinion/grossman-v-sea-air-towers-ltd-fladistctapp-1987.