Groedel v. Arsham, 88245 (4-12-2007)

2007 Ohio 1715
CourtOhio Court of Appeals
DecidedApril 12, 2007
DocketNo. 88245.
StatusPublished
Cited by2 cases

This text of 2007 Ohio 1715 (Groedel v. Arsham, 88245 (4-12-2007)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Groedel v. Arsham, 88245 (4-12-2007), 2007 Ohio 1715 (Ohio Ct. App. 2007).

Opinion

JOURNAL ENTRY AND OPINION
{¶ 1} Plaintiff-appellant, Caryn Groedel ("Groedel"), appeals the Shaker Heights Municipal Court's granting of judgment in favor of defendant-appellee, Kenneth Arsham, M.D. ("Arsham"). Finding no merit to the appeal, we affirm.

{¶ 2} On June 14, 2004, Groedel entered into a contract with Arsham for a surgical procedure to be performed on July 2, 2004. Groedel was required to pay the surgical fee of $3,250 in advance. Under the agreement, if Groedel cancelled her surgery between seven and fourteen days before the scheduled date, she would be assessed one-half of the fee or $1,625. In addition, if she cancelled the procedure with less than one week's notice, she would be charged the full fee of $3,250. She did not pay the fee in advance, but nonetheless the surgery was scheduled.

{¶ 3} Groedel maintains that on June 17, 2004 she called Arsham's office to cancel her July 2, 2004 appointment. Arsham contends that it was not cancelled until June 24, 2004. A notarized statement from his answering service indicates that *Page 2 the only call received from Groedel was on June 24, 2004 to reschedule the surgery. There is no dispute that on June 24, 2004, she spoke with an assistant at Arsham's office to reschedule her procedure for August 13, 2004. At that time, Groedel claims that she gave Arsham's office her credit card information for the rescheduled appointment.1 However, Groedel maintains that Arsham's office still charged her credit card $3,250 for the July 2, 2004 surgery, even though she cancelled it on June 17, 2004. Arsham later reimbursed Groedel $1,625 (one-half of $3,250) because she cancelled her procedure eight days prior to the surgery date.

{¶ 4} In June 2005, Groedel filed suit against Arsham, alleging that he breached the contract when he refused to give her a full refund of $3,250. The trial judge issued a verdict in favor of Arsham, finding that Groedel voluntarily signed the contract with full knowledge of the cancellation and refund policy.

{¶ 5} Groedel appeals, raising one assignment of error, in which she claims that the trial court erred in granting judgment in favor of Arsham. She argues that she has provided sufficient evidence to establish that the cancellation and refund policy was a penalty clause and not a clause providing for liquidated damages.

{¶ 6} The cancellation and refund policy provides, in pertinent part: "[i]f you [Groedel] cancel your scheduled surgery between 7 and 14 days of the surgery date, *Page 3 one half of the fee will be refunded. If the surgery is cancelled with less than one weeks [sic] notice, none of the fee will be refunded. If you wish to schedule, cancel or reschedule your surgery, please call the office at * * *." Groedel also argues that, because penalty clauses are unenforceable in Ohio, the cancellation and refund policy provision is unenforceable, and she is therefore entitled to a full refund of $3,250.

{¶ 7} As a general rule in Ohio, "* * * parties are free to enter into contracts that contain provisions which apportion damages in the event of default. `The right to contract freely with the expectation that the contract shall endure according to its terms is as fundamental to our society as the right to write and to speak without restraint. Responsibility for the exercise, however improvident, of that right is one of the roots of its preservation.'" Lake Ridge Academy v.Carney (1993), 66 Ohio St.3d 376, 613 N.E.2d 183, quoting Blount v.Smith (1967), 12 Ohio St.2d 41, 231 N.E.2d 301.2

{¶ 8} The complete freedom to contract, however, is not permitted in certain circumstances for public policy reasons, such as when stipulated damages constitute a penalty. "Punishment of a promisor for having broken his promise has *Page 4 no justification on either economic or other grounds and a term providing such a penalty is unenforceable on grounds of public policy." 3 Restatement of the Law 2d, Contracts (1981) 154, Section 356, Comment a.

{¶ 9} "The characteristic feature of a penalty is its lack of proportional relation to the damages which may actually flow from failure to perform under a contract." Lake Ridge, supra, citingGarrett v. Coast Southern Federal Savings Loan Assn. (1973), 9 Cal.3d 731, 108 Cal.Rptr. 845, 511 P.2d 1197. Accordingly, a penalty is designed to coerce performance by punishing nonperformance. Thus, its principal object is not compensation for the losses suffered by the nonbreaching party. Id.

{¶ 10} However, parties to a contract may provide in advance for damages to be paid in the event of a breach, "as long as the provision does not disregard the principle of compensation." 3 Restatement of Contracts, supra, at 157. These damages are known as liquidated damages. See Lake Ridge, supra.

{¶ 11} Whether a stipulated amount in a damages clause constitutes liquidated damages or a penalty is a question of law for the court to decide. Lake Ridge, supra. Therefore, we apply a de novo standard of review when evaluating this issue. See Cleveland Elec. Illum. Co. v.Pub. Util. Comm., 76 Ohio St.3d 521, 1996-Ohio-298, 668 N.E.2d 889. *Page 5

{¶ 12} In Samson Sales, Inc. v. Honeywell, Inc. (1984),12 Ohio St.3d 27, 465 N.E.2d 392, the Ohio Supreme Court set forth the following three-prong test to determine whether a damages provision should be upheld as liquidated damages:

"Where the parties have agreed on the amount of damages, ascertained by estimation and adjustment, and have expressed this agreement in clear and unambiguous terms, the amount so fixed should be treated as liquidated damages and not as a penalty, if the damages would be (1) uncertain as to amount and difficult of proof, and if (2) the contract as a whole is not so manifestly unconscionable, unreasonable, and disproportionate in amount as to justify the conclusion that it does not express the true intention of the parties, and if (3) the contract is consistent with the conclusion that it was the intention of the parties that damages in the amount stated should follow the breach thereof."

{¶ 13} The reviewing court must step back and examine the damages provision in light of what the parties knew at the time the contract was formed and in light of an estimate of the actual damages caused by the breach.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Robins v. Global Fitness Holdings, LLC
838 F. Supp. 2d 631 (N.D. Ohio, 2012)
Smith v. Locke-Calhoun, 90858 (11-13-2008)
2008 Ohio 5870 (Ohio Court of Appeals, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
2007 Ohio 1715, Counsel Stack Legal Research, https://law.counselstack.com/opinion/groedel-v-arsham-88245-4-12-2007-ohioctapp-2007.