Gritman v. United States Fidelity & Guaranty Co.

83 P. 6, 41 Wash. 77, 1905 Wash. LEXIS 1071
CourtWashington Supreme Court
DecidedDecember 20, 1905
DocketNo. 5718
StatusPublished
Cited by8 cases

This text of 83 P. 6 (Gritman v. United States Fidelity & Guaranty Co.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gritman v. United States Fidelity & Guaranty Co., 83 P. 6, 41 Wash. 77, 1905 Wash. LEXIS 1071 (Wash. 1905).

Opinion

Durbab, J.

This is an action by respondent, who was the owner, against the contractor and appellant, surety on the contractor’s bond, for damage on account of the default of the contractor. The complaint alleged, the execution of the contract; that the contractor had entered upon the performance of the contract and had, during the continuance thereof, abandoned the work; that he had paid divers sums upon the estimate of the architects, and was compelled to pay certain judgments upon materialmen’s and laborers’ .liens, and certain other amounts to complete the building; that the contractor was to pay $10 per day for the time after the 1st day of August; that the building was not completed for thirty-six days thereafter; and that altogether he was damaged in the total sum of $2,787.44. It was not alleged in the complaint that the accounts for expenses incurred by the owner were audited and certified by the architects, as provided by article 5 of the contract.

Appellant demurred to the complaint on general grounds. The demurrer was overruled, issues were joined, and an affirmative defense set up that the contract under which the building was erected was not the contract under which' the bond was given; that the judgments upon the mechanics’ liens were erroneous and void, etc. The respondent replied, denying the affirmative answer. The case was tried in October by a jury, resulting in a verdict for respondent. The verdict was afterwards set aside and a new trial granted. The second trial was by the court. During the first trial the respondent offered in evidence a certificate of the architects by which the correctness of the expenses was certified. To this offer appellant objected on the ground that it was ir[79]*79relevant, incompetent, and immaterial, and there were no allegations in the complaint to justify it. The certificate was admitted in part and excluded in part, the part excluded being held to^ he improperly in the certificate.

After the new trial was granted, the appellant applied for, and was granted, leave to file an amended answer. Respondent asked, and was granted, leave to amend his complaint in certain immaterial particulars, but no effort was made to amend by alleging that the architects had audited and certified as required by the contract. When the case came on for trial the second time:, on the 19th day of February, 1904, it was stipulated that the testimony taken at the former trial should be extended and transcribed, and the parties should offer any additional testimony they desired and interpose additional objections, and the court should consider all testimony taken and objections made at both trials. Again respondent offered the certificate of the ’architects upon the expenses incurred after the default of the contractor. Objection was again made, upon the same ground as in the former trial, and upon the additional ground that it was not in the manner and form contemplated in the contract. In April the case came on for argument upon the objections to testimony and upon the merits. On the 28th day of October, the court signed an order permitting respondent to amend his complaint and, at the same session, signed the findings of fact, conclusions of law, and judgment upon the amended complaint, to all of which appellant objected, and it was allowed an exception. On October 29, the order granting leave to amend, the amended complaint, the findings, conclusions, and judgment were filed with the clerk.

The appellant’s contention is that the court erred in allowing the amendment to the complaint in relation to the architects’ certificate at the time it was made. Conceding, without deciding, that the complaint was not broad enough, to admit the certificate of the architects, the trial court did not [80]*80commit error in granting the motion to make the pleadings conform to the evidence; and if it had not done so> this court, under the liberal provisions of the- statutes and its own uniform decisions, would consider the pleadings amended to conform to the facts proven and necessary to be proven, when such amendment would be in furtherance of justice- and when neither party would be in any wise misled or prejudiced thereby. A very earnest appeal has been made by appellant, by both brief and oral argument, on that question, and it is insisted that injustice has been done it by allowing this amendment. Counsel differ widely as to what actually occurred during the trial of the case, tending to show whether or not objection was made to the introduction of the evidence of the architects’ certificate for the special reason that it was not pleaded. An examination of the record shows that there is room for contention on this proposition. However, the more material question is, has the appellant been in any way-surprised or misled by the action of the court in allowing the amendment? Upon this question the following excerpt from the language of the court, in passing upon the motion to amend, has great weight. The court, in making its ruling on the motion to amend2 among other things, said:

“After the certificate was received in evidence by the court-, counsel for defendant -offered evidence tending to impeach said certificate, all of which was admitted, considered and received by the court; that the court is of the opinion that the allegations of the complaint were broad enough to entitle the plaintiff to introduce in evidence said certificate, and inasmuch as defendants were permitted to introduce evidence for the purpose of impeaching or destroying the force and effect of said certificate the same as if an issue had been made thereon by the answer as well as by the complaint, and as the point of insufficiency of the complaint in this respect with other objections was not argued before the court until several weeks after both parties had introduced their evidence and rested and agreed that the case should be argued after the evidence had been transcribed by the stenographer, and [81]*81the point as to the sufficiency of the complaint is purely technical and no improper advantage could be obtained by the plaintiff and no harm done to defendant by considering the complaint as amended to accord with the proofs, now1 therefore, it is ordered, upon motion of plaintiff, that said complaint be treated as amended with the proofs in the above respect, and further that the plaintiff may, if he desires, file amended complaint as of the time of the second trial of this cause, to wit, February 19, 1904; said amended complaint to contain an allegation as to the execution and delivery by the architects of said certificate and estimate, auditing said account above referred to, and also that the answer of the defendant shall likewise be deemed amended to accord with the proofs so that all testimony and evidence introduced by defendant tending to impeach or destroy the effect of said certificate shall be considered properly in evidence and within the issues in said cause.”

Hot only was this certificate introduced in evidence on the first trial, so that the appellant cannot plead surprise or want of opportunity to prepare controverting testimony, but upon rebuttal the appellant affirmatively proved the giving of the certificate, and attempted to show that it was given without sufficient investigation. This would probably not estop the appellant from urging the inadmissibility of the testimony offered by the respondent, but it goes to show lack of surprise or injury by reason of the order of the court allowing the amendment to the complaint. The whole record brings the case squarely within the rule announced by this court in Green v. Tidhall, 26 Wash. 338, 67 Pac. 84, 55 L. R. A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Ex Rel. Greely v. Mt. Water C
Montana Supreme Court, 1986
R. W. Rhine, Inc. v. City of Tacoma
536 P.2d 677 (Court of Appeals of Washington, 1975)
Adamson Et Ux. v. Brockbank
185 P.2d 264 (Utah Supreme Court, 1947)
Nowell v. Mayor of Monroe
171 S.E. 136 (Supreme Court of Georgia, 1933)
Rosenkranz v. Guaranty Trust Co.
295 P. 487 (Washington Supreme Court, 1931)
Maryland Casualty Co. v. Town of Wellston
1915 OK 121 (Supreme Court of Oklahoma, 1915)
Peterson v. Barry
97 P. 239 (Washington Supreme Court, 1908)

Cite This Page — Counsel Stack

Bluebook (online)
83 P. 6, 41 Wash. 77, 1905 Wash. LEXIS 1071, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gritman-v-united-states-fidelity-guaranty-co-wash-1905.