Griffin v. Drainage Commission

34 So. 799, 110 La. 840, 1903 La. LEXIS 718
CourtSupreme Court of Louisiana
DecidedJune 22, 1903
DocketNo. 14,391
StatusPublished
Cited by28 cases

This text of 34 So. 799 (Griffin v. Drainage Commission) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Griffin v. Drainage Commission, 34 So. 799, 110 La. 840, 1903 La. LEXIS 718 (La. 1903).

Opinion

Statement of the Case.

NICHOLLS, C. J.

Plaintiff prays for judgment for damages against defendant for $4,840, with legal interest from judicial demand, alleging: That he is the owner of a ■certain property on St. Louis street, at the corner of North Liberty, together with the buildings thereon. That. some time in the first part of the year 1899 defendant undertook the excavation of St. Louis street for the purpose of placing a drain conduit thereunder; cutting a trench of great depth and width along said street, and in close proximity to the foundations and walls of his building. That in the performance of the work through their agent, the National Contracting Company, neither the defendants, nor their agent acting- under their instructions, took any of the precautions needful and necessary to assure plaintiff’s property protection from the consequences of such dangerous work, but persistently continued the ■cutting of the ground in close proximity to said building. That the consequence of said reckless and negligent conduct of the defendant was that the foundation of the building, being deprived of its point of resistance, gave way and caved in to a further depth, thus entailing to the building the damages which he complained of in his petition. That the full amount of said damages consequent upon the acts complained of was not realizable at the time, and the proximate and consequent result of said damage had been continuous and increasing up to the filing of his demand. That in the month of April, 1899, the front of the building on St. Louis street had already settled to the extent that the first floor showed a fall of two and three inches towards that street, and there were many cracks in the walls on both sides, caused by the sinking of the foundations of the building, necessarily entailing damages to the interior of the same.

That in the month of April, 1901, the damage was still increasing, owing to the continued sinking- and caving of the foundations of the building. That on various occasions during the time the work of excavation was going on, and since, he had called upon the city engineer, notifying him of the condition of things then existing, asking for some relief in the premises. That he had called upon the late mayor, asking for his intervention in the matter, and all to no avail. That he had repeatedly called upon the defendants and notified them of the damage done to his property, and called upon them to repair the same or to pay some indemnity for said damage, and they had refused to do so.

That while awaiting some relief in the premises he had been forced to expend for the repair of the building certain items of expenditure, which he would thereafter show.

That on May 8, 1901, he was notified in writing by the commissioner of public works that the building must be promptly repaired in a substantial manner, or demolished within three days of the notice. That in compliance with said notice he had undertaken to place the building in such condition of temporary repair and safety as would insure the general public from danger of its collapse or crumbling at any moment, but that the condition of the building was then such that it must be necessarily demolished, and that at an early day. That owing to the condition of the building, due to the damage caused by defendant, he had lost in rental of the same up to the filing of his petition the sum of $200. That for painting, brickwork, and labor expended in repairs to make the house habitable he had paid $40, and he had suffered damages for loss of time and inconvenience in the sum of $100.

That the tearing down and rebuilding of the building, made absolutely necessary by the acts of the defendant, using so much of the material as could be used, would amount to the sum of $4,000. All of items of necessary expenditure in the premises, including loss on rent, inconvenience, etc., amounted to $4,340, and for this amount he prayed judgment against the defendant.

The defendant first pleaded the general issue- It then averred that if, in the exea[844]*844vation of the drainage canal in St. Louis street, any damage was wrongfully done to plaintiff’s building (which was denied), the same was the act of the National Contracting Company, and that the latter was responsible therefor under its contract with it, and it was bound to warrant and defend defendant accordingly. At its instance that company was called in warranty. Judgment was contingently asked against it.

The National Contracting Company answering, pleaded the general issue. In bar of plaintiff’s demand it pleaded the prescription of one year, and in support thereof it averred that the work in front of plaintiff’s building was completed in the year 1898, more than .two years before he brought his suit.

It denied that plaintiff’s building was injured, by any of the work conducted by it as the contractor of the drainage commission, and averred that it was conducted with all due care and precaution. It averred that, if any damage had occurred to plaintiff’s building, it had occurred long since its work was completed, and was the result of the drying of the soil by seepage into the canal, and for damages of that character it was not liable, and not the warrantor of the defendant, and that all such damages were such as had occurred from the execution of the plan of the drainage commission, and was damnum absque injuria.

It denied the damage alleged by the plaintiff, and averred that his house was old and rotten, and had been permitted to go without repairs for years, and that the damages which had occurred, if any, by the seepage of the soil, could be repaired for a very small sum, so as to make the building as good as if was before the canal was built.

The drainage commission subsequently pleaded in bar of plaintiff’s action the prescription of one year, averring that the work of the drainage commission done by the National Contracting Company, complained of by plaintiff, was completed in 1898, more than two years before the present action was brought.

An effort was made by the defendants to have the question of prescription taken up separately from and prior to the hearing upon the merits; but the court, over their objection, refused to do this, and they reserved a bill of exceptions. The case was tried upon the merits. The district court rendered judgment sustaining the plea of prescription filed by the defendants, and rejected plaintiff’s demand.

He applied unsuccessfully for a new trial. In his application he averred: That the judgment was contrary to the law and the evidence. That it was contrary to evidence, in this: That the evidence of the first witness testifying on behalf of the exceptions-proved that the damages to the building were caused by the works complained of, and first manifested their existence during the excavation made by defendants. That although the act complained of in the case, and giving rise to the damage suffered, was committed more than two years before the filing of the suit, the evidence showed conclusively that the damage from that time was continuous, and of a nature so to be the-cause operating the same; i. .e. the disintegration of the stability of the foundations of the building, and the consequent loss of its integrity, set in motion that condition of gradual sinking of the building, causing continuous and successive items of damages to-the same, rendering the same more insecure and dangerous until May, 1901, when he was notified by the city authorities that the building had been condemned and should be demolished.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bernard v. City of Marksville
154 So. 3d 1246 (Louisiana Court of Appeal, 2014)
Glenn Bernard v. City of Marksville
Louisiana Court of Appeal, 2014
Hogg v. Chevron USA, Inc.
45 So. 3d 991 (Supreme Court of Louisiana, 2010)
LEJEUNE BROS. v. Goodrich Petroleum Co.
981 So. 2d 23 (Louisiana Court of Appeal, 2007)
Crump v. Sabine River Authority
737 So. 2d 720 (Supreme Court of Louisiana, 1999)
Wiley v. Wiley
387 So. 2d 1 (Louisiana Court of Appeal, 1980)
Derbofen v. TL James & Co., Inc.
355 So. 2d 963 (Louisiana Court of Appeal, 1978)
Patin v. Stockstill
315 So. 2d 868 (Louisiana Court of Appeal, 1975)
Freestate Industrial Development Co. v. T. & H., INC.
188 So. 2d 746 (Louisiana Court of Appeal, 1966)
Marchand v. Miazza
151 So. 2d 372 (Louisiana Court of Appeal, 1963)
Merrimack Mutual Fire Insurance Co. v. Radalec, Inc.
126 So. 2d 848 (Louisiana Court of Appeal, 1961)
Home Ins. Co. v. Highway Ins. Underwriters
52 So. 2d 449 (Louisiana Court of Appeal, 1951)
In Re Union Cent. Life Ins. Co.
23 So. 2d 63 (Supreme Court of Louisiana, 1945)
Young v. International Paper Co.
155 So. 231 (Supreme Court of Louisiana, 1934)
Gulf Coast Paving Co. v. Gulf Public Service Co.
153 So. 701 (Supreme Court of Louisiana, 1934)
Rhodes v. International Paper Co.
139 So. 755 (Supreme Court of Louisiana, 1932)
Spyker v. International Paper Co.
138 So. 109 (Supreme Court of Louisiana, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
34 So. 799, 110 La. 840, 1903 La. LEXIS 718, Counsel Stack Legal Research, https://law.counselstack.com/opinion/griffin-v-drainage-commission-la-1903.