Griesel v. Dart Industries, Inc.

591 P.2d 503, 23 Cal. 3d 578, 153 Cal. Rptr. 213, 1979 Cal. LEXIS 217
CourtCalifornia Supreme Court
DecidedMarch 8, 1979
DocketL.A. 30838
StatusPublished
Cited by63 cases

This text of 591 P.2d 503 (Griesel v. Dart Industries, Inc.) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Griesel v. Dart Industries, Inc., 591 P.2d 503, 23 Cal. 3d 578, 153 Cal. Rptr. 213, 1979 Cal. LEXIS 217 (Cal. 1979).

Opinion

Opinion

MANUEL, J.

Plaintiff George C. Griesel appeals from a judgment entered on a verdict for defendants Dart Industries, Inc. and Lakeworld, a division of Dart Industries, Inc. (hereinafter referred to as Dart) in an action for damages for personal injuries. 1

Plaintiff contends that the court erred in substituting an alternate juror after seven days of deliberation and in improperly instructing thereon. He also contends that certain instructions were erroneous and that the trial court erred in invoking Labor Code section 6304.5 to exclude evidence of safety order violations and to refuse to instruct on the effect of safety order violations.

Dart was the owner, developer and general contractor of a large residential development in Kern County. Dart contracted with F.T. Ziebarth Company, plaintiff’s employer, to construct a waste water treatment plant which included an underground pump station and a pipeline between the pump station and a holding pond. The work required the excavation of a trench for the pipeline and a square cubicle for the underground pump station. The pipeline trench was to be 20 to 24 feet long of increasing depth to slightly over 9 feet and was to connect with the pump station excavation which was to be about 9 feet deep and 10 or 12 feet square. Dart exercised no control over how the work was to be done but employed a project superintendent, Burley Sizemore, to inspect the work for conformance to the plans and specifications.

*582 Plaintiff had worked for Ziebarth as a laborer for three to four months at the time he was sent to work on this project. Ziebarth hired a backhoe operator to do the excavation work which began the afternoon of April 25, 1972. That afternoon Ziebarth’s superintendent, Charles Bennett, instructed plaintiff to assist the backhoe operator by watching for obstacles. Plaintiff entered the trench a number of times that afternoon to assist the backhoe operator in removing rocks. Bennett, however, saw plaintiff in the trench only once that afternoon when it was still quite shallow.

Burley Sizemore went by the site about 6 p.m. on April 25 after work had stopped for the day and everyone else had gone. Sizemore noticed that the trench had been excavated and was about eight or nine feet at its deepest point. He also noticed that the trench was neither sloped nor shored. He did not recall noticing whether the bottom of the trench had been smoothed over with hand tools. At the time Sizemore saw the trench he considered it unsafe for anyone to be working in it. Sizemore and others testified that customary safety practices called for the shoring or sloping of trenches five feet or more deep in order to avoid the danger of the sides caving in.

On the morning of April 26 plaintiff went into the trench to check the grade of its floor. Bennett had told him to check the grade but had not shown him how to do so without going into the trench. Plaintiff did not know at the time that it was possible to check the grade from the top of the trench and had not been instructed about the danger of the unshored trench or told to stay out of it. Neither Bennett nor the backhoe operator saw plaintiff enter the trench. While he was in the unshored trench, it caved in upon him, inflicting serious injuries.

Although there was some conflict as to how nearly completed the excavation was at the time of the accident, in the normal course of work of this type no one would have entered the trench at the time plaintiff did so. Ordinarily, workmen would not enter the trench until the backhoe excavation was completed and it was time to pour concrete and lay pipe in the trench, at which time it would have been shored against cave-ins.

Plaintiff relied on two theories to establish Dart’s liability. The first theory was Dart’s duty as an owner or possessor of land to warn others of dangers of unreasonable risk of harm present on the land. The second theory was Dart’s duty as an employer of an independent contractor to *583 assure that precautions are taken against any peculiar risk of physical harm likely to arise during the course of the contractor’s work.

The jury deliberated for seven days. On the seventh day, one of the jurors advised the court that she had become too emotionally disturbed as a result of the deliberations to continue. The court informed counsel, interviewed the juror privately in chambers and then ordered her discharged. Plaintiff moved for a mistrial on the ground that the jury had deliberated too long for an alternate juror to become a meaningful and deliberative member of the jury. The court denied the motion and replaced the juror with an alternate. 2 After a little less than four hours of further deliberations the jury returned a nine-to-three verdict for defendant Dart. The recently seated alternate was one of the nine who returned the defense verdict.

I.

Plaintiff contends that the court erred in instructing the jury to “continue with your efforts” and to “continue your consideration of the case” at the time the alternate was substituted for the discharged juror. 3 Plaintiff urges that the court instead should have instructed the jury to begin" deliberations anew. 4 In People v. Collins (1976) 17 Cal.3d 687 [131 *584 Cal.Rptr. 782, 552 P.2d 742], we considered the question whether a statute authorizing the substitution of an alternate juror after commencement of deliberations infringes upon the constitutional right to a juiy trial set forth in article I, section 16 of the California Constitution. We concluded that it does not so long as the statute is construed to require that the court instruct the jury to set aside and disregard all past deliberations and begin deliberating anew. (Id., at p. 694.) This construction was necessary to protect the right to have each juror engage in all of the jury’s deliberations, an essential element of the right to a jury trial. We reasoned that “The requirement that 12 persons reach a unanimous verdict is not met unless those 12 reach their consensus through deliberations which are the common experience of all of them. It is not enough that 12 jurors reach a unanimous verdict if 1 juror has not had the benefit of the deliberations of the other 11. Deliberations provide the jury . with the opportunity to review the evidence in light of the perception and memory of each member. Equally important in shaping a member’s viewpoint are the personal reactions and interactions as any individual juror attempts to persuade others to accept his or her viewpoint. The result is a balance easily upset if a new juror enters the decision-making process after the 11 others have commenced deliberations.” (Id., at p. 693.)

We agree with plaintiff that the principles set forth in Collins apply to civil as well as criminal cases. The right to a juiy trial in civil cases is also guaranteed by article I, section 16 of the California Constitution, 5

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Healy v. Coachella Management Partners CA2/3
California Court of Appeal, 2025
Kasch v. United States
N.D. California, 2025
Thomas v. City of Los Angeles
California Court of Appeal, 2023
People v. Salinas CA5
California Court of Appeal, 2022
Caldwell v. New York City Tr. Auth.
2021 NY Slip Op 07537 (Appellate Division of the Supreme Court of New York, 2021)
Ruckman v. Wildwood Farms CA5
California Court of Appeal, 2021
Paletz v. Adaya CA2/3
California Court of Appeal, 2014
American States Insurance v. Progressive Casualty Insurance
180 Cal. App. 4th 18 (California Court of Appeal, 2009)
People v. Sanborn
35 Cal. Rptr. 3d 592 (California Court of Appeal, 2005)
Tilley v. CZ MASTER ASS'N
32 Cal. Rptr. 3d 151 (California Court of Appeal, 2005)
Elsner v. Uveges
102 P.3d 915 (California Supreme Court, 2004)
Lund v. San Joaquin Valley Railroad
71 P.3d 770 (California Supreme Court, 2003)
Elsner v. Uveges
130 Cal. Rptr. 2d 483 (California Court of Appeal, 2003)
People v. Renteria
113 Cal. Rptr. 2d 287 (California Court of Appeal, 2001)
Mendoza v. Club Car, Inc.
96 Cal. Rptr. 2d 605 (California Court of Appeal, 2000)
Toland v. Sunland Housing Group, Inc.
955 P.2d 504 (California Supreme Court, 1998)
Vomaska v. City of San Diego
55 Cal. App. 4th 905 (California Court of Appeal, 1997)
Owens v. Giannetta-Heinrich Construction Co.
23 Cal. App. 4th 1662 (California Court of Appeal, 1994)
Privette v. Superior Court
854 P.2d 721 (California Supreme Court, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
591 P.2d 503, 23 Cal. 3d 578, 153 Cal. Rptr. 213, 1979 Cal. LEXIS 217, Counsel Stack Legal Research, https://law.counselstack.com/opinion/griesel-v-dart-industries-inc-cal-1979.