Gridsmart Technologies, Inc. v. Marlin Controls, Inc.

701 F. App'x 488
CourtCourt of Appeals for the Sixth Circuit
DecidedJuly 20, 2017
Docket17-5121
StatusUnpublished
Cited by1 cases

This text of 701 F. App'x 488 (Gridsmart Technologies, Inc. v. Marlin Controls, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gridsmart Technologies, Inc. v. Marlin Controls, Inc., 701 F. App'x 488 (6th Cir. 2017).

Opinion

OPINION

BERNICE BOUIE DONALD, Circuit Judge.

This matter arises from an arbitration award that was entered as a result of an alleged distribution agreement breach. Although the distribution agreement contained a mandatory arbitration clause, the district court found that the arbitration provision was terminated when the distribution agreement was terminated. Therefore, the district court submitted a final order and judgment vacating the arbitration award. The issue before this Court is whether the arbitration clause in the distribution agreement survived termination of the agreement. Because we find that the arbitration clause did not survive termination of the distribution agreement and that the district court did not err when it vacated the arbitration award, we AFFIRM the district court’s order and judgment.

I.

The facts that follow are largely derived from the district court orders. Marlin Controls, Inc. (“Marlin”) is in the construction industry and provides traffic-signal equipment to construction projects. R. 22, Page ID #304. Gridsmart Technologies, Inc. (“Gridsmart”) manufactures and sells a camera system to collect data at intersections and on highways. Id. Under a 2014 distribution agreement (the “Distribution Agreement”), Marlin had the exclusive right to distribute the Gridsmart products within a defined region in the United States. Id.

On June 30, 2015, Gridsmart exercised its right to terminate the Distribution Agreement effective July 31, 2015. Id., at Page ID #305. The parties then tried to reconcile how Marlin’s outstanding orders, that were delivered to Marlin on September 30, 2015, would be handled. What followed is disputed. According to, Marlin, its construction contracts did not pan out, so it sent the equipment for those projects back to Gridsmart. Gridsmart then demanded full payment for the returned equipment. Gridsmart argued that the returned equipment had been specially made for Marlin and was obsolete by the time Marlin returned it. Thus, rather than double-dipping, Gridsmart argued that it was trying to recoup the value of the now-worthless equipment.

In January 2016, Gridsmart filed a claim with the American Arbitration Association. Marlin refused to participate. Id. On March 21, 2016, Gridsmart asked the arbitrator to grant it summary judgment. Id. The hearing was set for March 25, 2016. Id. Marlin did not appear at the hearing but filed a responsive letter a week later. Id. On April 8, 2016, the arbitrator granted Gridsmart’s motion for summary judgment and refused to consider Marlin’s responsive letter. Id.

Thereafter, Gridsmart sought to enforce the award by petitioning the Knox County Chancery Court. Marlin timely removed the case to the United States District Court for the Eastern District of Tennessee (the “District Court”). Id. On June 23, 2016, Marlin moved in the district court to vacate the arbitration award. Id. On January 10, 2017, the district court entered a judgment and order granting Marlin’s motion to vacate and denying Gridsmart’s petition to enforce the arbitration award and for associated attorney’s fees. Id. This timely appeal follows.

*490 II.

After Gridsmart filed this action in Tennessee state court, Marlin timely removed the case to the United States District Court for the Eastern District of Tennessee pursuant to 28 U.S.C. § 1441(b) and § 1446. The District Court rightly exercised jurisdiction under 28 U.S.C. § 1332 since the parties are citizens of different states and since the amount in controversy exceeded the jurisdictional threshold amount of $75,000. The appeal arises from the District Court’s final order and judgment entered on January 10, 2017. Grids-mart timely filed its Notice of Appeal on January 31, 2017. This Court has jurisdiction over the appeal of that final judgment pursuant to 28 U.S.C. § 1291.

III.

A district court’s decision whether to compel arbitration under the Federal Arbitration Act (“FAA”), 9 U.S.C. § 1 et seq., is reviewed de novo. Javitch v. First Union Secs., Inc., 315 F.3d 619, 624 (6th Cir. 2003). Similarly, a district court’s decision regarding the arbitrability of a particular dispute is reviewed de novo. McMullen v. Meijer, Inc., 355 F.3d 485, 489 (6th Cir. 2004).

“A longstanding principle of this Circuit is that no matter how strong[ly] the federal policy favors arbitration, ‘arbitration is a matter of contract between the parties, and one cannot be required to submit to arbitration a dispute which it has not agreed to submit to arbitration.’ ” Simon v. Pfizer Inc., 398 F.3d 765, 775 (6th Cir. 2005) (citing United Steelworkers, Local No. 1617 v. Gen. Fireproofing Co., 464 F.2d 726, 729 (6th Cir. 1972)); see also AT & T Techs., Inc. v. Commc’ns Workers of Am., 475 U.S. 643, 648, 106 S.Ct. 1415, 89 L.Ed.2d 648 (1986) (“[Arbitration is a matter of contract and a party cannot be required to submit to arbitration any dis pute which he has not agreed so to submit.”); Bratt Enters., Inc., v. Noble Int’l Ltd., 338 F.3d 609, 612 (6th Cir. 2003); Roney & Co. v. Kassab, 981 F.2d 894, 897 (6th Cir. 1992).

Therefore, the first place to turn is the language of the contract, in this case the language of the Distribution Agreement. “Because arbitration agreements are fundamentally contracts, [this Court] review[s] the enforceability of an arbitration agreement according to the applicable state law of contract formation,” Seawright v. Am. Gen. Fin. Servs., Inc., 507 F.3d 967, 972 (6th Cir. 2007). The Distribution Agreement is government by Tennessee state law. RE-1, Page ID # 17, § 9.1. The Tennessee Uniform Commercial Code (“Tennessee UCC”) applies because the Distribution Agreement is a contract for the sale of goods. Tenn. Code Ann. § 47-2-102.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Straub v. Ford Motor Company
E.D. Michigan, 2021

Cite This Page — Counsel Stack

Bluebook (online)
701 F. App'x 488, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gridsmart-technologies-inc-v-marlin-controls-inc-ca6-2017.