Greyrock v. Collavino N.E. Constr., No. Cv-02-0188647-S (Jan. 6, 2003)

2003 Conn. Super. Ct. 408
CourtConnecticut Superior Court
DecidedJanuary 6, 2003
DocketNo. CV-02-0188647-S
StatusUnpublished

This text of 2003 Conn. Super. Ct. 408 (Greyrock v. Collavino N.E. Constr., No. Cv-02-0188647-S (Jan. 6, 2003)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Greyrock v. Collavino N.E. Constr., No. Cv-02-0188647-S (Jan. 6, 2003), 2003 Conn. Super. Ct. 408 (Colo. Ct. App. 2003).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]

MEMORANDUM OF DECISION
RE: APPLICATION FOR DISCHARGE OR REDUCTION OF MECHANIC'S LIEN This case comes to this court as a hearing on a Motion to Discharge or reduce a Mechanic's Lien.

I. BACKGROUND

In the year 2000, the Plaintiff/Applicant Stamford Greyrock, LLC d/b/a Cappelli-Greyrock, LLC ("Stamford Greyrock") was the owner of certain real property located on Forest Street in Stamford, Connecticut (the "Premises"). Stamford Greyrock retained EF/Walsh, Fuller, LLC ("EF/Walsh") to act as its agent to construct a high rise apartment building known as Greyrock Tower on the Premises. In May of 2000, EF/Walsh sub-contracted with Defendant/respondent Collavino Northeast Construction Co., LLC ("Collavino") to have Collavino act as the structural concrete sub-contractor for Greyrock Tower. In late 2001, a dispute arose between EF/Walsh and Collavino regarding final payment under the contract.

On February 28, 2002, Collavino recorded a Mechanic's Lien against the Premises in the amount of $2,700,000.00. Stamford Greyrock initiated this action to reduce or discharge the lien. Stamford Greyrock and Collavino agreed that the Mechanic's Lien would be replaced by a surety bond in the amount of $1,500,000.00. Stamford Greyrock obtained the surety bond and Collavino released the Mechanic's Lien. Stamford Greyrock now seeks to reduce the amount of the bond to less than $1,500,000.00 or discharge the bond entirely.

The parties presented evidence to this court (Karazin, J.) on August 26, September 4, and September 6, 2003.

II. CLAIMS OF THE PARTIES CT Page 409

Collavino asserts that it has established probable cause to sustain the validity of the bond in the amount of $1,500,000.00. Collavino further asserts that Stamford Greyrock has not established by clear and convincing evidence that the bond should be reduced or that the bond is not valid.

As an aid to the Court, the parties have prepared outlines of their monetary claims which have been submitted as Exhibits 2-A (Collavino's summary of claims) (See Exhibit 2-A attached hereto) and Exhibit A-i (Stamford Greyrock's summary of claims). Although these exhibits are for identification only, the parties have agreed that the court may view those exhibits as an aid. Collavino asserts that it has established probable cause for the court to find that EF/Walsh owes Collavino $2,499,447.91 and therefore the surety bond obtained by the Stamford Greyrock should remain at the amount of $1,500,000.00.

III. FINDINGS OF FACT

The Court finds the following facts:

A. BACKGROUND

1. During the relevant time period of between May 18, 2000 and February 28, 2002, Stamford Greyrock was the owner of certain real property located on Forest Street in Stamford, Connecticut (the "Premises"). (See Application for Discharge or Reduction of Mechanic's Lien dated March 26, 2002 and testimony of John Bernabei.)

2. At some time prior to May 18, 2000, Stamford Greyrock retained EF/Walsh, Fuller, LLC ("EF/Walsh") to act as its agent and as the general contractor for the construction of a highrise apartment building ("Greyrock Tower") on the Premises. (Testimony of Mario Orgera and John Bernabei and see Exhibit One, the subject contract, which names EF/Walsh as agent of the owner.)

3. On May 18, 2000, EF/Walsh as the agent of Stamford Greyrock entered into a subcontract (the "Contract") with Collavino Northeast Construction Co., LLC ("Collavino") in the amount of $11,054,000.00, whereby Collavino agreed to act as the sub-contractor for the structural concrete work at Greyrock Tower. (See Exhibit 1.) The concrete floors would be reinforced by "post tension" cables which would be tightened to add strength to the concrete. Id.

4. Mario Orgera was the manager of the job for Collavino. (Testimony of CT Page 410 Orgera.) John Mallozzi, a professional engineer licensed by the states of Connecticut and New York, acted as a consultant to Collavino and assisted Orgera with the management of the work under the Contract. (Testimony of Mallozzi.) Mario Collavino is the President of Collavino. (Testimony of Mario Collavino.) James Bruno was the job superintendent at Greyrock Tower for EF/Walsh. (Testimony of Orgera.) John Bernabei was a vice-president of EF/Walsh. (Testimony of Bernabei.) John Lundberg was a vice-president of Fox Steel, Inc. which was a subcontractor to Collavino and supplied the post-tension cables. (Testimony of Lundberg.)

5. Collavino began its work under the Contract in May, 2000. (Testimony of Mario Orgera.)

6. The Plaintiff and Defendant agree to certain add-ons to the Contract price. Exhibit 10 is a "spread sheet" containing certain add-ons and deductions from the contract price. The Plaintiff and Defendant agree to the add-ons listed in Exhibit 10 except for item 34 which is a charge for the crane at the Premises in the amount of $84,863.00. Accordingly, the parties agree that there were add-ons of at least $835,586.80.

7. The Plaintiff and Defendant also agree to certain deductions from the Contract price contained in Exhibit 10. The Plaintiff and Defendant agree to the deductions in Exhibit 10 except for item 43 which was a payment made by EF/Walsh to D J Concrete in the amount of $76,025.00. Accordingly, the parties agree that there were deductions of at least $612,840.73.

8. The Plaintiff and Defendant agree that the service of the subject Mechanic's Lien and Notice of Intent to File Mechanic's Lien by the marshal was made on the proper parties. (See Stipulation of Parties dated September 5, 2002.)

9. The Plaintiff and Defendant agree that the content of, and the property description contained in, the subject Mechanic's Lien and Notice of Intent to File Mechanic's Lien are valid. (See Stipulation of Parties dated September 5, 2002.)

10. The Plaintiff and Defendant agree that Plaintiff has validly substituted a surety bond in the amount of $1,500,000.00 in lieu of the subject Mechanic's Lien. (See Stipulation of Parties dated September 5, 2002.) Stamford Greyrock is a principal on the surety bond and Collavino is the obligee. (See Exhibit H, surety bond.)

B. TIMELINESS OF MECHANIC'S LIEN CT Page 411

1. Substantial completion of Collavino's work under the Contract occurred on November 15, 2001. (See Exhibits B and I.) Work continued after November 15, 2001. (Testimony of Bernabei.)

2. Mario Orgera continued working at the job site with men working under him after November 15, 2001 and through December 6, 2001. (Testimony of Orgera.)

3. Between December 7, 2001 and January 7, 2002, Mario Orgera continued to stop at the Premises each work day to see if anything needed to be done regarding the concrete. (Testimony of Orgera.)

4. On January 7, 2002, at the Premises, Bruno hand-delivered to Orgera a letter addressed to Collavino, Exhibit 23. (Testimony of Orgera.)

5. The Bruno letter of January 7, 2002 (Exhibit 23) stated that a cable had blown out of the ceiling of Apartment 1512 and that "[a]ny and all costs, time wise and monetarily will be charged against your contract." The only contract between EF/Walsh and Collavino was the subject Contract. (Testimony of Orgera.)

6. After hand-delivering the January 7, 2002 letter (Exhibit 23) to Orgera, Bruno requested that Collavino repair the damage to apartment 1512. (Testimony of Orgera.)

7.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

F. B. Mattson Co. v. Tarte
719 A.2d 1158 (Supreme Court of Connecticut, 1998)
Blakeslee Arpaia Chapman, Inc. v. El Constructors, Inc.
628 A.2d 601 (Connecticut Appellate Court, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
2003 Conn. Super. Ct. 408, Counsel Stack Legal Research, https://law.counselstack.com/opinion/greyrock-v-collavino-ne-constr-no-cv-02-0188647-s-jan-6-2003-connsuperct-2003.