Gregory Martino v. Pika International, Inc.

600 F. App'x 908
CourtCourt of Appeals for the Fifth Circuit
DecidedJanuary 29, 2015
Docket13-50425
StatusUnpublished
Cited by21 cases

This text of 600 F. App'x 908 (Gregory Martino v. Pika International, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gregory Martino v. Pika International, Inc., 600 F. App'x 908 (5th Cir. 2015).

Opinion

PER CURIAM: *

Gregory Martino appeals the judgment of the district court dismissing his claims with prejudice in favor of defendants Kiewit New Mexico Corporation (“Kiewit”) and Martin Gomez. Martino challenges the adverse summary judgment on his negligence per se claim, the exclusion of evidence at the jury trial of the remaining allegations, and the district court’s decision to overrule two of his objections regarding Kiewit’s expert witness during trial. For the reasons that follow, we AFFIRM.

I. Background

This dispute arose out of a construction worksite accident in which Gomez, one of Kiewit’s employees, ran over Martino with a “skid steer,” a machine Gomez was using to excavate dirt. The construction occurred pursuant to a contract involving the United States Army Corps of Engineers (“USACE”), which retained Kiewit to build a portion of the fence on the United States — Mexico border. Separately, subcontractors — including Zia, Martino’s employer — handled archaeological and environmental monitoring for USACE. On the date of the accident, Gomez ran over Martino’s foot while he was walking along the top of a levee on which Gomez was excavating dirt.

Martino sued multiple parties, claiming negligence, negligence per se resulting from violation of Occupational Safety and Health Administration (“OSHA”) regulations, gross negligence, and negligent hiring, training, and supervision of Gomez. The district court struck from evidence a contract between Kiewit and USACE (“USACE Contract”) because Martino failed to disclose the contract under Federal Rule of Civil Procedure 26(a)(1)(A). The district court eventually dismissed all defendants except Kiewit and Gomez and granted Kiewit’s motion for summary judgment, dismissing all but Martino’s negligence claim. The court concluded that Martino had provided insufficient evidence to support his negligent hiring, training, and supervision claims, and that Fifth Circuit precedent precluded a negligence per se cause of action based on *910 OSHA violations. The district court also denied Martino’s application for more time to designate experts and furnish expert reports because Martino failed repeatedly to meet deadlines in the court’s scheduling orders.

As trial approached, the district court excluded evidence in eight categories pursuant to Kiewit’s motions in limine. Among other evidence excluded was any reference to OSHA standards, any testimony regarding Gomez’s “citizenship, work visa or immigration status,” and any evidence about post-accident training given to Gomez by the U.S. Department of Labor. During trial, the district court overruled Martino’s objection that Kiewit’s expert witness, Dr. Juan Manuel Herrera, had not been offered for a Daubert 1 voir dire, and that Dr. Herrera testified about traffic control plans. Martino timely appealed to this court.

II. Standards of Review

We review a trial court’s evidentiary rulings and decisions to exclude evidence under Rule 37(c) for abuse of discretion. See CQ, Inc. v. TXU Min. Co., L.P., 565 F.3d 268, 277, 279-80 (5th Cir.2009); Burleson v. Tex. Dep’t of Criminal, Justice, 393 F.3d 577, 583 (5th Cir.2004); see generally Fed.R.Civ.P. 26, 37(c). “A trial court abuses its discretion when its ruling is based on an erroneous view of the law or a clearly erroneous assessment of the evidence.” Burleson, 393 F.3d at 583 (citation and internal quotation marks omitted). “We review a district court’s ruling on a motion for summary judgment de novo and apply the same legal standards as the district court.” Exelon Wind 1, L.L.C. v. Nelson, 766 F.3d 380, 394 (5th Cir.2014) (internal citation and quotation marks omitted).

III. Discussion

Martino claims that the district court erred by: (1) striking the USACE Contract for Martino’s failure to disclose it under Rule 26; (2) denying Martino additional time to designate his experts; (3) holding Martino could not make a negligence per se claim based on OSHA on summary judgment; (4) granting Kiewit’s _ motion in limine and excluding various pieces of evidence; (5) overruling Marti-no’s objection that Dr. Herrera had not been offered for a Daubert voir dire; and (6) allowing Dr. Herrera to testify about his prior work with Kiewit on traffic control plans. We examine each issue in turn.

A. Exclusion of the USACE Contract

After an extension to accommodate Martino, the district court set October 1, 2012 as the discovery deadline. On that date, Kiewit filed its motion for summary judgment. Martino responded on October 30, 2012 and attached the USACE Contract. On Kiewit’s motion, the district court struck the USACE Contract as a Rule 37(c) sanction “because Plaintiff wholly failed to comply with the discovery timelines .in this cause and never produced the contract previous to this point” as required by Rule 26. See Fed.R.Civ.P. 26(a)(l)(A)(ii). Martino argues that the district court abused its discretion in striking the USACE Contract because neither Rule 26 nor the scheduling order required production of the contract.

Rule 26(a)(1)(A)(ii) mandates that a party initially disclose “all documents ... that the disclosing party has in its possession, custody, or control and may use to support *911 its claims or defenses, unless the use would be solely for impeachment....” Id. Rule 37(c) states that upon failure to do so, a “party is not allowed to use that information ... to supply evidence on a motion, at a hearing, or at a trial, unless the failure was substantially justified or is harmless.” FedR.CivP. 37(c). In determining whether a district court abused its discretion in excluding evidence under Rule 37(c), we consider four factors: “(1) [Martino’s] explanation for [his] failure to disclose the evidence, (2) the importance of the evidence, (3) the potential prejudice to [Kiew-it] in allowing the evidence, and (4) the availability of a continuance.” CQ, Inc. v. TXU Min. Co., L.P., 565 F.3d at 279-80. Under this four-pronged test (the “CQ Test”), the district court did not abuse its discretion.

Martino’s failure to disclose the USACE Contract under Rule 26 followed a sequence of discovery violations. Martino attempts to justify his nondisclosure by claiming the USACE Contract was a public document, equally available to both parties. However, even if a document is publicly available or in the opposing party’s possession, a party must still disclose it under Rule 26(a)(1)(A) to provide notice of evidence central to its claims or defenses.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
600 F. App'x 908, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gregory-martino-v-pika-international-inc-ca5-2015.