Greenup Industries, LLC v. Five S Group, LLC

District Court, E.D. Louisiana·Decided November 3, 2023·No. 2:22-cv-02203·Unknown

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF LOUISIANA

GREENUP * CIVIL ACTION INDUSTRIES LLC * * NO. 22-2203 VERSUS * * SECTION: “L” (4) FIVE S GROUP, LLC ET AL * *

ORDER AND REASONS Before the Court is Defendants and Counterclaim Plaintiffs’ Five S Group, LLC and Hartford Fire Insurance Company’s Motion for Partial Summary Judgment. R. Doc. 53. Plaintiff and Counterclaim Defendant Greenup Industries, LLC filed a motion in opposition. R. Doc. 63. Defendants and Counterclaim Plaintiffs filed a reply memorandum. R. Doc. 69. Having considered the briefing, relevant law, and oral argument, the Court rules as follows. I. BACKGROUND This case arises from a contract between Greenup Industries, LLC (“Greenup”) the Contractor, and Five S Group, LLC (“Five S”), the Subcontractor, to excavate fill from the Bonnet Carre Spillway and transport it to another site, in fulfillment of a contract Greenup was awarded by the United States Army Corps of Engineers (“USACE”) to complete work related to its Hurricane Storm Damage Risk Reduction Project. Greenup alleges that it entered a subcontract (“Subcontract”) with Five S on October 26, 2020, in which Five S agreed to provide labor and equipment to excavate 1,000,000 cubic yards (“CY”) of fill from the Bonnet Carre Spillway, and that Hartford Fire Insurance Company (“Hartford”) then issued a performance bond on behalf of Five S in the amount of $9,472,000.00. Id. at 2. Both parties note that the Subcontract schedule called for the fill to be excavated over 15 months, requiring that Five S excavate and transport an average of 66,667 CY of fill each month. Id. at 3; R. Doc. 29 at 2. The Subcontract provided that the fill was to be excavated from a “borrow pit,” and moved to a stockpile. R. Doc. 18-1 at 19. Greenup alleges that USACE began raising issues about Five S’s lack of performance in “late 2021.” R. Doc. 1-1 at 3. Among the concerns, Greenup alleges, were broken equipment left

onsite, excessive employee turnover, and a lack of processing equipment that resulted in failed quality tests regarding the moisture content of the fill. Id. at 4. Five S, by contrast, alleges that, while it “mobilized sufficient equipment and labor” to finish the project on schedule, Greenup’s breach of performance caused its inability to meet the Project timeline. R. Doc. 18 at 4. On November 21, 2021, Five S’s area manager, Justin Mibbs, sent Greenup a letter alleging that, despite an initial agreement that Greenup would provide Five S 40-50 trucks a day to transport the fill from the borrow site to the stockpile, “Greenup so far has been providing only about 8 or 9 trucks a day.” R. Doc. 18-3 at 1. In the letter, Mibbs alleged that the small number of trucks provided would delay the project’s completion by four years, and informed Greenup that it was “submitting an application for payment of 85% of our daily cost of keeping equipment and labor

at the borrow pit” until “Greenup increases its number of trucks at the site.” Id. at 2. Greenup’s counsel replied to the letter on November 15, 2021, stating that Greenup viewed the request for daily costs as “outside of the terms of the Subcontract” because “5S agreed to be paid pursuant to the line items set forth in Exhibit B” and that these line items “must be based upon USACE approved calculations of in-place quantities.” R. Doc. 18-4 at 1. Over the next five months, the problems regarding the pace of the work did not abate. Monthly schedule updates issued by Greenup from December 2021 to April 2022 all note delays due to inadequate number of trucks and difficulties “keeping trucks onsite and available.” R. Doc. 29-1 at 2-5. Greenup alleges that, on April 12, 2022, Five S sent a demand letter re-emphasizing its November 1, 2021 request and notifying Greenup that it had de-mobilized from the site and would not resume until Greenup agreed to pay for past and future standby time. R. Doc. 1-1 at 4. Greenup further alleges that Five S demobilized from the site “well before March 15, 2022” and that Five S “made clear its intent to abandon the job well before any ‘declaration’ of alleged

default.” Id. at 5. Five S alleges that it was “excused from further performance under the Subcontract” when Greenup breached its obligations to supply sufficient trucks and to pay Five S for the services it provided under contract. R. Doc. 29 at 5. On May 27, 2022, Greenup sued Five S and its insurer, Hartford, in Orleans Parish Civil District Court, seeking a declaratory judgment that Five S “does not have a legal or contractual basis to put Greenup in default and to discontinue its obligations under the Subcontract” and that any payment to Five S was conditioned upon Greenup’s receipt of USACE funds. R. Doc. 1-1 at 7. Greenup also made claims for breach of contract and indemnity against Five S and repeated its claims for declaratory judgment against Hartford, id. at 7-8, and sought attorneys fees from Hartford. Id. at 9. On July 15, 2022, Five S and Hartford removed the case to federal court under

28 U.S.C. § 1442(a)(1), asserting that removal was proper because Five S acted at the direction of the USACE, and because Greenup’s claims rested on the Miller Act, at 40 U.S.C. § 3133(b)(3), which is under exclusive federal jurisdiction. R. Doc. 1 at 6. On July 22, 2022, Five S and Hartford filed a counterclaim against Greenup and its insurer, which Defendants named as “ABC Insurance Company.” R. Doc. 18 at 9. On September 20, 2022, Five S and Hartford filed an amended counterclaim against Greenup and its actual insurer, Markel Insurance Company. Id. Against Greenup, Five S and Hartford allege breach of contract. Against both Greenup and Markel, Five S and Hartford allege claims under the Miller Act for Greenup’s failure to pay Five S out of the Payment Bond that Markel issued for the work. Five S and Hartford also bring claims against Greenup and Markel under the Louisiana Prompt Payment Act, alleging that Greenup failed to remit payment within 14 days of receiving those funds from the USACE. Id. at 11-12. II. PRESENT MOTION

On October 10, 2023, Defendants Five S and Hartford filed the instant Motion for Partial Summary Judgment. R. Doc. 53. The gist of Movants’ argument is that they are entitled to standby and/or delay damages pursuant to the Miller Act, or alternatively, state law. Id. First, Defendants argue that as subcontractors, they are entitled to delay expenses under the Miller Act because of Plaintiff’s failure to supply enough trucks to the Defendants to complete the project. R. Doc. 53-1 at 4-5. Defendants also argue language in subcontracts waiving delay damages are unenforceable under the Miller Act. Id. at 6-7. In furthering this argument, Defendants cite only persuasive law. Id. at 4-7. Second, Defendants argue that delay damages are recoverable in subcontracts pursuant to La. R.S. § 38:2216(H). Id. at 8. In opposition, Greenup alleges that the clear and unambiguous terms of the Subcontract do

Free access — add to your briefcase to read the full text and ask questions with AI

Greenup Industries, LLC v. Five S Group, LLC, (E.D. La. 2023).

Greenup Industries, LLC v. Five S Group, LLC (Greenup Industries, LLC v. Five S Group, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related