Green Mountain Power Corp. v. General Electric Corp.

496 F. Supp. 169, 1980 U.S. Dist. LEXIS 13261
CourtDistrict Court, D. Vermont
DecidedAugust 14, 1980
DocketCiv. A. 79-112
StatusPublished
Cited by9 cases

This text of 496 F. Supp. 169 (Green Mountain Power Corp. v. General Electric Corp.) is published on Counsel Stack Legal Research, covering District Court, D. Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Green Mountain Power Corp. v. General Electric Corp., 496 F. Supp. 169, 1980 U.S. Dist. LEXIS 13261 (D. Vt. 1980).

Opinion

MEMORANDUM AND ORDER

HOLDEN, Chief Judge.

Competing pretrial motions compose the important question of whether the plaintiff Green Mountain Power Corporation (GMP) may seek to recover for economic loss caused by the alleged negligent performance of a contractual undertaking by the defendant General Electric Corporation (GE) with the Vermont Yankee Nuclear Power Corporation (Vermont Yankee) during the summer of 1978. The diversity of citizenship between the parties and the jurisdictional amount are clearly demonstrated in the complaint; hence the substantive law of Vermont must be applied to the facts developed in the record. Erie Railroad v. Tompkins, 304 U.S. 64, 58 S.Ct. 817, 82 L.Ed. 1188 (1938).

The Facts Alleged

It appears from the record that on April 7, 1978, GE and Vermont Yankee entered a written contract for work to be performed by GE on the Vermont Yankee Nuclear generating facility at Vernon, Vermont. The contract provided that GE would make certain modifications to the suppression chamber (the “torus”) of the generating unit. GE undertook this work in 1978. According to the complaint, during the course of the work, GE negligently damaged the torus, causing the plant to shut down operations. The plant supplied no power to its customers from this source during the period of July 1 to August 14, 1978, as a result of the shutdown.

During the time period under consideration GMP owned twenty percent of the stock in Vermont Yankee. GMP was entitled to purchase twenty percent of the power produced at the Vermont Yankee facility. In 1978 GMP was represented on the *171 board of directors of Vermont Yankee. As a result of the shutdown caused by GE, GMP was unable to purchase any power from the Vernon facility during the whole period of the shutdown. GMP was required to purchase more expensive power to supply the deficiency in its requirements as a consequence of the suspended operation of the Vernon plant.

GMP filed this action on May 29, 1979, asking for damages arising from GE’s negligence in performing the work on the torus. GMP alleges no physical damages to its own property. The only damage complained of is the excess cost of the purchase of alternate replacement power.

By its answer of August 2, 1979, GE challenges the plaintiff’s right to any recovery by asserting as its first affirmative defense the plaintiff’s failure to state a claim upon which relief can be granted.

Plaintiff’s Motion To Strike

Plaintiff promptly moved, pursuant to Rule 12(f), Fed.R.Civ.P., to strike defendant’s first affirmative defense. The defense raises an important and unsettled question of Vermont law as to the sufficiency of the complaint. Courts are reluctant to determine disputed and substantial questions of law on a motion to strike, unless there is a showing of prejudicial harm to the plaintiff. Augustus v. Board of Public Instruction, 306 F.2d 862, 868 (5th Cir. 1962). Where the defense presents a purely legal question, a motion to strike is generally regarded as an inappropriate vehicle to resolve substantial questions of law until after discovery and a hearing on the merits. United States v. 416.81 Acres of Land, 514 F.2d 627, 630 (7th Cir. 1975) (opinion by Justice Clark, sitting by designation); see 5 C. Wright and A. Miller, Federal Practice and Procedure § 1381, at 800-01 (1969).

To sustain the plaintiff’s motion to strike, the court must be convinced that there are no disputed questions of fact, that the questions of law are clear and settled, and that under no circumstances could the defense prevail. Smith, Kline & French Laboratories v. A. H. Robins Co., 61 F.R.D. 24, 33 (E.D.Pa.1973). The question of law presented here is unsettled and its application to the facts alleged has thus far been unresolved in Vermont. Furthermore, legal insufficiencies in the cause of action may develop at trial. Even if the motion to strike were to be granted at this stage, the defendant may raise the same motion for failure to state a claim at the trial, on the merits. Rule 12(h)(2), Fed.R.Civ.P. Moreover, much the same legal points are presented by the defendant’s counter motions to dismiss and for summary judgment. The plaintiff’s motion to strike will be denied.

Defendant’s Motion For Summary Judgment

Defendant has moved, pursuant to Rule 56(b), Fed.R.Civ.P., for summary judgment. The motion properly falls under Rule 56 since the defendant has presented supporting affidavits outside the pleadings.

The defendant contends that the plaintiff’s complaint does not state a cause of action under Vermont law. The defendant’s argument is advanced on two grounds: first, Vermont law denies recovery for economic loss resulting from negligent interference with the plaintiff’s contract rights with Vermont Yankee; second, an exculpatory clause in the repair contract between GE and Vermont Yankee (§ 45(b)) should apply to GMP.

The defendant contends that the plaintiff’s recovery for its economic losses resulting from alleged negligence is precluded by the prevailing law of Vermont, as stated in Baldwin v. State, 125 Vt. 317, 215 A.2d 492 (1965) and Nieberg v. Cohen, 88 Vt. 281, 92 A. 214 (1913). Both cases concerned efforts by married women to recover for wrongful interference with the plaintiff’s marital relationship by wrongful acts of the defendants. Baldwin was for harm caused by negligent personal injury to the husband; Nieberg for the wife’s loss of support and affection caused by the wrongful acts of the defendant in procuring her husband’s conviction of a criminal offense. Recovery by the spouses for loss of their husband’s consortium was denied in both actions.

*172 After the present motions were argued and submitted, the Baldwin case was overruled by the Vermont Supreme Court. See Whitney v. Fisher, 417 A.2d 934 (Vt.Sup.Ct.1980). 1 In Nieberg the Vermont court held that a wife may not recover for wrongful acts inflicted upon her husband unless the offending action was maliciously and intentionally done to harm the wife. Nieberg v. Cohen, supra, 88 Vt. at 289, 92 A. 214.

The doctrine upon which the defendant places reliance relates back to Winterbottom v. Wright, 10 M. & W. 109, 152 Eng.Rep. 402, 403 (1842) wherein the Court of Exchequer held that the breach of a contract to maintain a mail coach in repair conferred no right of action in a passenger in the vehicle who suffered harm in the vehicle’s collapse.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Springfield Hydroelectric Co. v. Copp
779 A.2d 67 (Supreme Court of Vermont, 2001)
Trepanier v. Getting Organized, Inc.
583 A.2d 583 (Supreme Court of Vermont, 1990)
Federal Deposit Ins. Corp. v. Main Hurdman
655 F. Supp. 259 (E.D. California, 1987)
Heraeus-Amersil, Inc. v. United States
600 F. Supp. 221 (Court of International Trade, 1984)
Salcer v. Envicon Equities Corp.
744 F.2d 935 (Second Circuit, 1984)
Armstrong v. Snyder
103 F.R.D. 96 (E.D. Wisconsin, 1984)
Warner v. General Motors Corp.
357 N.W.2d 689 (Michigan Court of Appeals, 1984)
Knickerbocker Toy Co., Inc. v. Winterbrook Corp.
554 F. Supp. 1309 (D. New Hampshire, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
496 F. Supp. 169, 1980 U.S. Dist. LEXIS 13261, Counsel Stack Legal Research, https://law.counselstack.com/opinion/green-mountain-power-corp-v-general-electric-corp-vtd-1980.