Greater Yellowstone Coalition v. Reese

392 F. Supp. 2d 1234, 2005 U.S. Dist. LEXIS 35366, 2005 WL 1863179
CourtDistrict Court, D. Idaho
DecidedAugust 4, 2005
DocketCV-05-258-E-BLW
StatusPublished

This text of 392 F. Supp. 2d 1234 (Greater Yellowstone Coalition v. Reese) is published on Counsel Stack Legal Research, covering District Court, D. Idaho primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Greater Yellowstone Coalition v. Reese, 392 F. Supp. 2d 1234, 2005 U.S. Dist. LEXIS 35366, 2005 WL 1863179 (D. Idaho 2005).

Opinion

MEMORANDUM DECISION AND ORDER

WINMILL, Chief Judge.

INTRODUCTION

The Court has before it a motion for injunctive relief filed by Greater Yellow *1237 stone and a motion to intervene filed by Simplot. The Court heard oral argument on August 1, 2005, and the motions are now at issue. The Court will grant Sim-plot’s motion to intervene for remedy purposes only. For the reasons expressed below, the Court will deny Greater Yellowstone’s motion for injunctive relief.

FACTUAL BACKGROUND

Plaintiff Greater Yellowstone seeks to enjoin implementation of the South Manning Creek Exploration Project, a proposal to build roads and drill exploratory wells in the Caribou-Targhee National Forest and the Sage Creek Roadless Area. Greater Yellowstone claims that federal agencies violated the National Environmental Protection Act (NEPA) in approving this project.

Intervenor Simplot mines phosphate at its Smokey Canyon Mine, located partially within the Caribou-Targhee National Forest. It leases land within the National Forest to mine phosphate. Simplot seeks to expand the mine to include two new excavation areas known as Panel F and Panel G. Panel F is also known as the Manning Creek proposal while Panel G is known as the Deer Creek proposal. Portions of both Panels are within the Sage Creek Roadless Area.

Simplot has leased most of Panel F, and all of Panel G. Both the BLM and the Forest Service have jurisdiction over this area, and Simplot needs to obtain their approval before proceeding. To determine if that approval should be granted, the BLM and the Forest Service began preparing an EIS, which is in the process of being completed.

On December 26, 2001, Simplot filed a lease modification application with the BLM to include the South Manning Creek area in the current Panel F lease. The BLM responded in a letter dated December 17, 2002, stating that it would not “consider enlargement of the lease by modification at this time without further information.” The BLM required further information to answer two questions: (1) Whether sufficient phosphate deposits existed in that area; and (2) Whether water quality would be protected from toxic mining wastes. In that letter, the BLM proposed that the information “can be gathered and is best authorized through an Exploration License” and “a jointly prepared NEPA document.” Simplot responded by proposing an exploratory project that would gather the information by (1) constructing about three miles of “temporary roads,” (2) drilling 25 exploration holes ranging from 100 to 600 feet deep along with two groundwater monitoring wells, and (3) reconstructing 2,000 feet of previously reclaimed road. The project will last about one to two months.

The BLM and Forest Service analyzed this proposal in an EA issued in final form in February, 2005. In that EA, the agencies recognized that they had evaluated a similar lease modification request in 1997. That 1997 proposal, also made by Simplot, included some of the same land included in its present proposal. Described in shorthand metes and bounds, the 1997 proposal included portions of lands in sections 26, 27, 34, and 35, the same sections where the present proposal will take place. The match is not identical — the 1997 proposal included lands just south of the present proposal along with lands lying within the southern part of the present proposal.

In examining the 1997 proposal, the BLM consulted with the Forest Service and asked for its recommendation. Forest Service Supervisor Jerry Reese responded to the BLM in a letter dated February 23, 1998. In that letter, Supervisor Reese approves of leasing land to the north of the present proposal, but expresses concern about the lands at issue here due to the *1238 “sensitive nature and the importance of the surface resources present in [the area].” He recommends against leasing lands lying in Section 26 — where most of the roads will be built in the present proposal — until “it can be demonstrated that there are phosphate reserve present in sufficient quantities to justify mining, and that selenium and other potentially toxic material can be controlled and the downstream effects mitigated to acceptable levels .... ” He also “strongly recommend against any phosphate leasing now or in the foreseeable future for lands within [Sections 27, 34, and 35].”

The 1997 proposal to lease lands in Sections 26, 27, 34, and 35, was eventually rejected by the agencies. This history was recounted in the 2005 EA, which cited Supervisor Reese’s concerns, and concluded that those concerns would be addressed by Simplot’s exploratory project because the project would gather “geologic, hydraulic, and other environmental data....”

Recognizing also that the exploratory project would be conducted in the shadow of the much larger Panel F & G proposal, the 2005 EA conducted a cumulative impacts analysis. That analysis looked at the cumulative environmental impacts over the entire area of the Panel F & G proposal and beyond, an area labeled as the Cumulative Effects Area.

This analysis identified 4,300 acres of past, present, and future mining disturbances in the CEA, along with logging and grazing impacts. Examining the South Manning Creek Exploration Project in light of these surrounding impacts, the EA concluded that since “the Proposed Action would only temporarily disturb approximately 6.8 acres of soil, vegetation, and wildlife[,] ... potential cumulative effects ... within the [Cumulative Effects Area] would be inconsequential.” The EA further found that the project’s impacts would be “minimal and short-term.”

On February 25, 2005, the Forest Service issued a Finding of No Significant Impact (FONSI), thereby declining to proceed with an EIS. This FONSI was issued by Supervisor Reese, the same person who in 1998 had expressed the concerns discussed above. In the FONSI, Supervisor Reese quotes from his 1998 letter identifying the need for more information on phosphate reserves and the protection of water quality. Supervisor Reese then concludes in the FONSI that approving the present exploratory project “will allow Simplot to gather the data needed for this evaluation.” See FONSI at p. 8.

Supervisor Reese goes on to list the following additional reasons for approving the project: (1) the Revised Forest Plan (RFP) allowed for road construction and other activities incident to phosphate mining; (2) there was already an “extensive amount of human intrusion and activity” in the area; (3) the impacts of the exploration project were expected to be “minimal and short-term” because the project would last at most for two months and all roads would be “obliterated and reclaimed;” and (4) no mining activity was being approved — only limited exploratory work. The FONSI also required that all disturbed areas “be stabilized using methods that have been provided in ‘Best Management Practices’ (BMPs) for Mining in Idaho,” and adopted 25 measures to protect water quality. 1

Simplot is set to begin the road-building sometime close to August 8, 2005. Greater Yellowstone brought this action seeking to *1239 enjoin the implementation of the project on the ground that its approval violated NEPA.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Thomas v. Peterson
753 F.2d 754 (Ninth Circuit, 1985)
Idaho Sporting Congress v. Thomas
137 F.3d 1146 (Ninth Circuit, 1998)
Presidio Golf Club v. National Park Service
155 F.3d 1153 (Ninth Circuit, 1998)
Wyoming v. United States Department of Agriculture
277 F. Supp. 2d 1197 (D. Wyoming, 2003)
Blue Mountains Biodiversity Project v. Blackwood
161 F.3d 1208 (Ninth Circuit, 1998)
Oakland Tribune, Inc. v. Chronicle Publishing Co.
762 F.2d 1374 (Ninth Circuit, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
392 F. Supp. 2d 1234, 2005 U.S. Dist. LEXIS 35366, 2005 WL 1863179, Counsel Stack Legal Research, https://law.counselstack.com/opinion/greater-yellowstone-coalition-v-reese-idd-2005.