Great Lakes Gas Transmission Co. v. Grayco Constructors, Inc., and Seaboard Surety Company

506 F.2d 498
CourtCourt of Appeals for the Sixth Circuit
DecidedFebruary 24, 1975
Docket73-1948
StatusPublished
Cited by8 cases

This text of 506 F.2d 498 (Great Lakes Gas Transmission Co. v. Grayco Constructors, Inc., and Seaboard Surety Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Great Lakes Gas Transmission Co. v. Grayco Constructors, Inc., and Seaboard Surety Company, 506 F.2d 498 (6th Cir. 1975).

Opinion

WALINSKI, District Judge.

This is an appeal from a verdict and judgment of $1,838,544.56, recovered by plaintiff from the company to whom it had awarded a contract to construct part of its pipeline project. After the work was completed and the pipeline had been placed in service, the pipeline ruptured for substantial distances on two separate occasions, thereby causing damages which required repairs and which resulted in loss of revenue.

On this appeal, error is charged in the admission of certain opinion evidence and in the rejection by the Court of evidence which would show that plaintiff had recovered substantial benefits in its rate allowance by changing its accounting procedures whereby the loss was passed on to plaintiff’s customers. Appellants also assign as error the lack of competent evidence to support the verdict on the issues of negligence and breach of warrranty; that plaintiff’s witness improperly construed the contract between plaintiff and its gas supplier ; that the verdict is excessive; and that defendant was prejudiced by the trial court’s jury charge. We find it necessary only to discuss the first two contentions.

Plaintiff is a Delaware corporation which was formed as a joint venture by two major North American natural gas distributing and pipeline companies: TransCanada Pipelines, Ltd., and American Natural Gas Company. The company was formed to build and operate a new and larger gas pipeline to extend across northern Minnesota, Wisconsin, the upper peninsula of Michigan, and through the lower peninsula to Sarnia, Michigan, where it would connnect with TransCanada’s facility at the international boundary. The construction of the line was divided into two phases, the first of which was completed in 1967 and ran from Sarnia to Farwell, Michigan. The second phase began in 1968 and' involved several pipeline eonstruc *500 tion companies, one of whom was the defendant.

Defendant Grayco entered into a contract with plaintiff in which Grayco was to build a 60-mile section of the pipeline running from eastern Wisconsin into the upper peninsula of Michigan. Grayco’s obligation extended from unloading the pipe from railroad ears; clearing and excavating the land; welding pipe sections together; cleaning, priming and coating the pipe; laying the pipe into the ground and filling in the trench; final testing and purging of the pipeline; and “all things necessary to completely construct a gas transmission facility ready to be operated * * *.” (Pl. Ex. #2.) The steel pipe used in the line was, under the contract, to be capable of withstanding pressures of 65,000 pounds per square inch without rupturing or being deformed.

Grayco began work in the spring of 1968 and was to complete the section by November 1, 1968. Work was substantially finished by late October, 1968, in spite of unusually wet and cold weather which began in September. As part of its testing procedures, Grayco performed a hydrostatic test of the pipeline at pressures up to 105% of the specified strength with the pressure maintained for a 24-hour period. These tests were successful at the two sites with which we are here concerned, the pipe surviving long tests in excess of 100% of the specified minimum strength. Great Lakes assumed beneficial occupancy of the Grayco section by November 1, 1968, although certain rough cleanup work continued until severe weather conditions forced a halt to this activity on November 13, 1968.

Great Lakes began gradually after November 1, 1968, to build up the pressure in its new line to the allowable maximum. In spite of some “start-up” problems in the first weeks, the pipeline was operating by mid-December so as to enable Great Lakes to meet the requirements of certain gas transmission contracts.

However, on December 27, 1968, the line suddenly ruptured at milepost 403.2 (measured as 403.2 miles from the western terminus of the line) causing approximately 850 feet of pipe to be split and violently thrown out of the ground. Great Lakes immediately began repairs using Grayco equipment which had been stored in the vicinity for the winter. By January 10, 1969, the line had been completely repaired and gas pressure was gradually increased.

Great Lakes’ tranquility was to be short-lived, however. A few hours after gas transmission had resumed, the line ruptured again, this time at milepost 400.2 (nearly three miles west of the first rupture). Approximately 380 feet of pipe was split and thrown out of the ground, again completely severing the pipeline. Repairs were quickly begun, using Grayco equipment still in the area. On January 17, 1969, the line had been completely repaired and was restored to operation.

As a result of these two ruptures, the United States Department of Transportation ordered the operating pressure on the line to be severely limited between the nearest compressor stations on both ends of the Grayco section. Great Lakes undertook to make an internal examination, known as a Linalog survey, of the portion of the pipeline which was now suspect.

While awaiting completion of the necessary preparations for the Linalog survey, Great Lakes sought and was granted permission to raise its operating pressure, although still not near its planned capacity. After the Linalog survey had been completed, all pressure restrictions were completely removed, and the line began operating as planned on May 29, 1969.

When Great Lakes assumed possession of the line on November 1, 1968, it had changed its accounting procedures from the “under construction” mode to an “in-service” mode. After the ruptures occurred, Great Lakes reverted to the “under construction” system until May 29, 1969. The effect of this rever *501 sion was to place all of plaintiff’s costs during the period of repairs and pressure restrictions into its “plant” account, which was in turn used to determine its rate base by the Federal Power Commission.

The case was tried by a jury on three theories: negligence, breach of contract, and breach of implied warranty of fitness. Plaintiff submitted a total damage claim of $2,444,193.94 to the jury which returned a verdict as to all counts of $1,838,544.56, apparently reflecting a decision not to permit recovery of the revenue lost during the period of pressure restriction.

Defendant’s first major ground for appeal is that the district court erred in permitting plaintiff to introduce certain opinion testimony as to the cause of the two ruptures. In this regard, defendant also charges error in permitting the Order of the Department of Transportation of January 17, 1969, to be introduced because it also is alleged to have contained an opinion as to the cause of the ruptures which is assailed as being hearsay. We do not believe that prejudicial error was committed in either instance.

The opinion testimony to which appellant refers is that of the witnesses Holstead and Etchegary. Holstead is the executive vice president and general manager of plaintiff. According to his testimony, he had been in the pipeline business for at least twenty years at the time of the ruptures. He also had nearly ten years experience in the design, engineering and supervision of construction of gas pipelines while he was employed by TransCanada. While Holstead had a bachelor’s degree in civil engineering, he testified that he had acquired through his experience, a working knowledge of metallurgy and fracture mechanics.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
506 F.2d 498, Counsel Stack Legal Research, https://law.counselstack.com/opinion/great-lakes-gas-transmission-co-v-grayco-constructors-inc-and-seaboard-ca6-1975.