Great American Insurance Company v. Johnson Controls, Inc.

District Court, S.D. Ohio·Decided October 15, 2020·No. 1:20-cv-00096·Unknown

Opinion

UNITED STATES DISTRICT COURT SOUTHERN DISTRICT OF OHIO WESTERN DIVISION

GREAT AMERICAN INSURANCE COMPANY,

Plaintiff, Case No. 1:20-cv-96 JUDGE DOUGLAS R. COLE v.

JOHNSON CONTROLS, INC,

Defendant.

OPINION AND ORDER This case has a bit of an odd procedural history. Plaintiff Great American Insurance Company (“Great American”) filed a complaint (the “Complaint”), naming Johnson Controls as the Defendant, and seeking declaratory judgment in a contract dispute. Specifically, the dispute relates to a performance bond that Great American had issued on a building project that went wrong. (Doc. 1). Johnson Controls, which asserts a right to collect under that bond, responded to the declaratory judgment action with a Motion to Compel Arbitration. (Doc. 3). The Court granted that motion, finding that the threshold question of arbitrability—i.e., whether an arbitrator or the Court should resolve the underlying contractual dispute—was itself arbitrable. The Court thus dismissed the suit, without prejudice, to allow the arbitrator to make that determination. The arbitrator determined the matter was not arbitrable. Before Great American could refile suit here, though, Johnson Controls filed its own breach of contract action, raising the identical dispute, in federal court in South Carolina (where the building project at issue took place). In response to that new lawsuit, Great American filed the instant Motion to Set Aside Judgment (“Motion”) under Federal Rule of Civil Procedure 60(b) in this action. (Doc. 14). In the Motion, Great American asks this Court: (1) to revise its

earlier judgment by changing the dismissal without prejudice into a stay; and (2) to find that this suit is thus the earlier filed suit for purposes of the first-to-file rule. For the reasons set forth more fully below, the Court DENIES Great American’s Motion. Although the Court did not contemplate that Johnson Controls would file suit in South Carolina in the circumstances here, the Court nonetheless concludes that granting Great American’s current Motion ultimately would be futile. That is because, as further explained below, even were the Court to reinstate this

action, the Court would still find that transfer or dismissal without prejudice in favor of the South Carolina action is the appropriate course, notwithstanding that this declaratory judgment action was filed first. There is little reason to grant the motion to reinstate this case, only to then immediately stay or dismiss it. FACTUAL BACKGROUND

Great American filed its complaint in this action on February 4, 2020. The complaint asserted claims against Johnson Controls under the Declaratory Judgment Act. As the complaint explains, Great American is an insurer. It issued a performance bond to Structure Cabling Solutions, Inc. d/b/a SCS Technologies (“SCS”) in connection with SCS’s work as a subcontractor on a hospital construction project in Charleston, South Carolina. (Compl., Doc 1, ¶¶ 7-8, #12). Johnson Controls was also a subcontractor on the project, but acted as the upstream subcontractor from SCS. That is, Johnson Controls had entered a subcontract with the general contractor on the hospital project (Robins & Morton Group), under which Johnson Controls agreed do a portion of the work on that project. Then Johnson Controls in turn hired SCS to

do part of that work. Generally speaking, Johnson Controls contracted to provide low voltage cabling work and communications systems for the hospital, including a nurse call- code system and an intercom system. (Mot. to Compel, Ex. A, Doc. 3-1, #65–66). The sub-contract between Johnson Controls and SCS required SCS to install low voltage cabling infrastructure for the data and telephone systems. (Mot. to Compel, Ex. B, Doc. 3-1, #120). Disputes arose between SCS and Johnson Controls regarding SCS’s

performance. Specifically, Johnson Controls claimed that SCS failed to install a number of cabling infrastructures and had effectively “walked off the job.” (Compl., Doc. 1, ¶ 10, #12); (Mot. to Compel, Ex. C, Doc. 3-1, #134–36). SCS later offered to return with a partial crew, but Johnson Controls ultimately replaced SCS with another subcontractor, Symphony Technology Solutions, to complete the work. Johnson Controls also began contacting Great American during that same time

about the performance bond that Great American had issued guaranteeing SCS’s performance. Johnson Controls claimed that SCS’s failure to perform meant that Great American owed substantial sums to cover the increased costs associated with hiring a replacement subcontractor. (Compl. at ¶¶ 18–27, #13–14). The amount of the claimed costs rose over time from a preliminary $100,000 estimate to Johnson Controls’ most recent estimate of $1,146,000. (Id. at ¶¶ 14, 27). Great American, by contrast, claims that its liability on the performance bond is limited to a $125,000 lump-sum amount plus the then-remaining contract balance of $209,000. (Id. at ¶¶ 24, 26). Great American offered to pay that sum (i.e., $334,000)

in full satisfaction of its obligations under the bond, but Johnson Controls declined. At that point, Great American elected to file this declaratory judgment action seeking clarity regarding its obligations under the performance bond. Shortly after Great American brought the declaratory judgment action, Johnson Controls filed a motion to compel arbitration. That motion raised two separate arbitration provisions. The first, contained in the master agreement between the General Contractor and the first line subcontractors (like Johnson

Controls), required arbitration of disputes under that contract, and also mandated that, should the subcontractor execute any sub-subcontracts in connection with the project, the subcontractor must include an arbitration provision in such sub- subcontracts. The second, and more directly applicable, arbitration provision was the one contained in the sub-subcontract between Johnson Controls and SCS. This latter

provision required Johnson Controls and SCS to arbitrate “any dispute that shall arise between [SCS] and [Johnson Controls] in connection with this subcontract.” (Mot. to Compel, Ex. B, Doc. 3-1, #114). Even though Great American was not itself a signatory to that sub-subcontract, Johnson Controls contended that Great American, by issuing a bond guaranteeing a signatory’s (i.e., SCS) performance under that contract, had become subject to that provision. Johnson Controls further argued that the dispute Great American advanced in this case fell within the broad sweep of the arbitration provision. Or, at the very least, it claimed that the arbitration provision made the threshold question of whether this dispute fell within the

arbitration provision (typically referred to as the question of arbitrability) itself a question for the arbitrator. Thus, Johnson Controls requested that the Court send the matter to arbitration, either in its entirety, or at least as to the threshold question. And it also requested that, in the interim, the Court either stay the matter or dismiss it without prejudice pending the arbitrator’s decision. Great American countered that neither the underlying dispute, nor the arbitrability question, were arbitrable under the agreement because it was not a

signatory to the agreement. It further argued that, in any event, the dispute over the performance bond did not fall within the scope of the arbitration provision’s plain language. While Great American argued the merits of the arbitration question, it did not offer an opinion one way or the other on whether a stay or dismissal without prejudice would be more appropriate if the Court found against Great American on the arbitration issue.

Free access — add to your briefcase to read the full text and ask questions with AI

Great American Insurance Company v. Johnson Controls, Inc., (S.D. Ohio 2020).

Great American Insurance Company v. Johnson Controls, Inc. (Great American Insurance Company v. Johnson Controls, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Liljeberg v. Health Services Acquisition Corp.
486 U.S. 847 (Supreme Court, 1988)
Horne v. Flores
557 U.S. 433 (Supreme Court, 2009)
Gonzalez v. Crosby
545 U.S. 524 (Supreme Court, 2005)
Kmart Corp. v. Key Industries, Inc.
877 F. Supp. 1048 (E.D. Michigan, 1994)
Clear! Blue, LLC v. Clear Blue, Inc.
521 F. Supp. 2d 612 (E.D. Michigan, 2007)
Arthur Tyler v. Carl Anderson
749 F.3d 499 (Sixth Circuit, 2014)
Abu-Ali Abdur'Rahman v. Wayne Carpenter
805 F.3d 710 (Sixth Circuit, 2015)
Richard Baatz v. Columbia Gas Transmission
814 F.3d 785 (Sixth Circuit, 2016)
Buck v. Davis
580 U.S. 100 (Supreme Court, 2017)