Grant Contracting Co. v. Murphy

56 N.E.2d 313, 387 Ill. 137
CourtIllinois Supreme Court
DecidedMay 16, 1944
DocketNos. 26911, 26914. Judgments affirmed.
StatusPublished
Cited by17 cases

This text of 56 N.E.2d 313 (Grant Contracting Co. v. Murphy) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Grant Contracting Co. v. Murphy, 56 N.E.2d 313, 387 Ill. 137 (Ill. 1944).

Opinion

Mr. Justice Furton

delivered the opinion of the court:

This case presents a consolidation, to be heard as one cause, of appeals from four orders entered by the circuit court of Cook county affirming decisions of the board of review of the Department of Labor awarding compensation benefits to claimants, Allison, Murphy, Metzger, Largent, Cluney, Smith and Mattern.

Each of the claimants had filed claims with the Department of Labor, pursuant to the provisions of the Illinois Unemployment Compensation Act, for benefits based on their emplo)mient by appellant. The Deputy Claims Administrator denied their claims on the ground that they came within "the provisions of section 2(f)(6)(C) of the Unemployment Compensation Act which provides that the term “employment” shall not include “Service performed as an officer or member of the crew of a vessel on the navigable waters of the United States.” Ill. Rev. Stat. 1943, chap. 48, par. 218.

The referee, to whom appeals were taken, reversed the decisions of the deputy and held that the claimants were not officers or members of the crew of a vessel on the navigable waters of the United States and were, therefore, entitled to benefits under the act. The circuit court of Cook county affirmed the decisions of the referee.

The facts involved are not in dispute. On or about April 1, 1938, the appellant was engaged in performing a dredging operation in the Illinois river under a contract with the McWilliams Dredging Company which was under contract' with the United States Government for improving, deepening and widening established navigation channels of the Mississippi river and its tributary rivers. The appellant performed its work upon a course of the Illinois river from about seventeen miles north of Havana, Illinois, to a point about seventeen miles south thereof and disposed of approximately three million cubic yards of material. In the .performance of this work the appellant used two hydraulic dredges approximately one hundred feet long and twenty-six feet wide. One was documented by the Bureau of Navigation of the Department of Commerce. Both dredges were powered by diesel electric units located on the dredges which operated all of the dredging machinery likewise located on the dredges. The documented dredge was self-propelled and capable of moving under its own power. The other dredge necessitated the use of a barge which was furnished power by the diesel unit aboard the dredge. To move the latter dredge any distance it was necessary to lash it to the barge for propulsion and steering. In the course of the dredging operations the dredge moved approximately five hundred feet during a twenty-four hour period. This was accomplished by a “spudding” process which involved the anchoring of the dredge by wires attached to trees on each side of the river or by wires attached to anchors located ip the river bed and the use of perpendicular shafts at each corner of the stern of the dredge, which shaft was called a “spud” and which could be raised or lowered into the bed of the river by the machinery located upon the dredge. The dredge could be swung laterally, in either direction, and forward by means of loosening and tightening the anchor wires. When this was done one shaft would be dropped into the river bed holding the dredge stationary for the actual dredging operation. A variation of this means enabled the dredge to be swung laterally and forward so that the entire river bed might be covered.

A suction line was attached to the dredge at the end of which was located a revolving cutter head which sheared or tore material from the bed of the river. The loosened material was then sucked up through the suction line by a pump located on the dredge and forced into a sixteen-inch discharge line to disposal areas which were located either in shallow water, on the shore line or bordering the shore line. Floating pontoons extending from the dredge to. the shore carried the discharge lines to the point of disposal. As became necessary, the discharge line was either lengthened or shortened.

A pipe line crew under the supervision of a “Mate” installed, dismantled and maintained the discharge lines which averaged from five to six hundred feet in length during the course of the work. As the dredge moved forward the pipe line crew synchronized the movement of the pipe line with the action of the dredge and made adjustments both on the water and on the shore. This crew likewise attended to the free flow of the discharge line and occasionally dismantled the line to clear chokes which occurred therein. This crew likewise aided in making repairs to the dredge or the equipment thereon located. Upon moving from one place to another the mate and his crew were required to dismantle the discharge line, load the line onto the barge and lash the pontoons into the tow. When it became necessary to install the pipe line onto the shore, it became the duty of the same crew to clear the thickets to facilitate the location of the pipe.

The dredges were in operation twenty-four hours per day and the, claimants were employed by the appellant in eight-hour shifts, approximately ten men to a shift. A captain who normally worked in the daytime only, was in charge of the dredge. His duties were principally supervisory and during long moves he was in charge of the navigation and control of the propelling mechanism. When the captain was not on duty, a dredge operator or lever man was in charge. He operated the dredging pump, cutter head and spuds and controlled the movement of the dredge. His duties were performed exclusively on the dredge.

The claimant Mattern was a diesel engineer and had charge of the diesel engine and the electrical equipment on the dredge.

The claimants Allison, Murphy, Metzger and Smith were called oilers. They assisted the operator or lever man and their duties consisted of taking care of the oiling of the diesel engine, the hoist, ladder and other machinery. They took soundings and generally assisted the operator and the diesel engineer.

The claimant Largent was a motorboat operator who operated an auxiliary boat used in connection with each dredge. This boat was thirty-two feet long and was used as a dredge tender in transporting the crew from the dredge, transporting supplies to and from the dredge, and transporting the mate and his assistants to and from the pontoon lines, and wás used to assist the moving of the pontoon lines and equipment.

The claimant Cluney was called a mate and had supervision of the deck hands or labor. His duties involved the moving of the swinging lines and anchor, opening and closing the pontoon lines, the addition of pipe to the pontoon lines, handling the anchors on the pontoon lines and the location and maintenance thereof, both on the water and on the shore. Each of the claimants were paid wages upon an hourly basis and were not engaged for any definite term. They did not sign Ship’s Articles upon entering their employment, were not licensed seamen, were members of local laborers’ unions and lived and boarded at home.

There was testimony on the part of some of the claimants that the mate was ofttimes called a labor foreman.

The applicable section of the Unemployment Compensation Act is identical in its exception provision to section 907(c)(3) of the Federal Social Security Act (42 U. S. C. A. par.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Haynes v Neshewat
729 N.W.2d 488 (Michigan Supreme Court, 2007)
Jack Bradley, Inc. v. Department of Employment Security
585 N.E.2d 123 (Illinois Supreme Court, 1991)
Louise v. Department of Labor
413 N.E.2d 113 (Appellate Court of Illinois, 1980)
Hernandez v. Board of Review, Department of Labor
398 N.E.2d 879 (Appellate Court of Illinois, 1979)
GRIFFITTS CONSTRUCTION CO., INC. v. Dept. of Labor
390 N.E.2d 333 (Illinois Supreme Court, 1979)
Ross v. Cummins
131 N.E.2d 521 (Illinois Supreme Court, 1956)
Shell Oil Co. v. Cummins
131 N.E.2d 64 (Illinois Supreme Court, 1955)
American Steel Foundries v. Gordon
88 N.E.2d 465 (Illinois Supreme Court, 1949)
State v. Hix
54 S.E.2d 198 (West Virginia Supreme Court, 1949)
Saunders v. Maryland Unemployment Compensation Board
53 A.2d 579 (Court of Appeals of Maryland, 1947)
American Medical Ass'n v. Board of Review
65 N.E.2d 350 (Illinois Supreme Court, 1946)
R. C. Huffman Construction Co. v. Unemployment Compensation Commission
36 S.E.2d 641 (Supreme Court of Virginia, 1946)
Crouch v. Murphy
60 N.E.2d 879 (Illinois Supreme Court, 1945)
Cape Girardeau Sand Co. v. Unemployment Compensation Commission
184 S.W.2d 605 (Supreme Court of Missouri, 1945)

Cite This Page — Counsel Stack

Bluebook (online)
56 N.E.2d 313, 387 Ill. 137, Counsel Stack Legal Research, https://law.counselstack.com/opinion/grant-contracting-co-v-murphy-ill-1944.