Granite Construction Company

CourtArmed Services Board of Contract Appeals
DecidedNovember 1, 2023
Docket62281
StatusPublished

This text of Granite Construction Company (Granite Construction Company) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Granite Construction Company, (asbca 2023).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of - ) ) Granite Construction Company ) ASBCA No. 62281 ) Under Contract No. W9126G-15-C-0037 )

APPEARANCES FOR THE APPELLANT: Michael A. Branca, Esq. Joseph N. Frost, Esq. Peckar & Abramson, P.C. Washington, DC

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Clark Bartee, Esq. Engineer Trial Attorney U.S. Army Engineer District, Galveston

OPINION BY ADMINISTRATIVE JUDGE EYESTER PURSUANT TO BOARD RULE 11

Granite Construction Company (Granite) appeals a decision by the U.S. Army Corps of Engineers (Corps or government) denying Granite compensation for 19 days of a 49-day suspension of work. The Corps concluded that those 19 days were adverse weather delays, which Granite should have anticipated pursuant to the terms of the contract. The Board previously granted Granite partial summary judgment on a contract interpretation issue concerning the interplay of the contract’s unusually severe weather, default, and suspension of work clauses. According to the decision, the only remaining issue for the Board to decide is whether the Corps suspended the work for a reasonable period of time pursuant to the suspension of work clause.

The Board has jurisdiction over the appeal pursuant to the Contract Disputes Act, 41 U.S.C. § 7101. The parties elected to waive a hearing and submit the remaining issue in this appeal on the record pursuant to Board Rule 11. Based on the following, we conclude that the Corps’ suspension of work for 49 days was reasonable and deny Granite’s appeal.

FINDINGS OF FACT

1. On August 31, 2015, the Corps awarded Granite fixed-priced contract No. W9126G-15-C-0037 to perform the construction of new outlet structures and cutoff walls at the Addicks and Barker dams to support the Buffalo Bayou and Tributaries federal flood control project in Houston, Texas (Joint Stipulations of Fact (JSF) ¶ 1; R4, tab 1 at 2574, 2628). 1 The contract incorporated by reference Federal Acquisition Regulation (FAR) 52.242-14, SUSPENSION OF WORK (APR 1984) and FAR 52.249-10, DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984) (R4, tab 1 at 2575).

2. In addition, the contract included SECTION 01 10 00.00 45, Part 1.4, TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER (31 OCT 1989) (ER 415-1-15), which explained how to determine time extensions for unusually severe weather (more severe than the adverse weather anticipated for the project location during any given month) in accordance with the default clause. Part 1.4 included a table showing monthly anticipated adverse weather delays and Granite was required to reflect those delays in its project schedule. For example, the table showed anticipated adverse weather delays (based on a seven-day work week) for the months of August (10), September (13) and October (10), for a combined total of 33 days for those months. The contract also required Granite to record any adverse weather and resulting impact to normally scheduled work on its daily contractor quality control reports. If the actual adverse weather delay days exceeded the number of days anticipated in the schedule, the contracting officer was to convert qualifying delays to calendar days and issue a modification in accordance with the default clause. (R4, tab 1 at 2633)

3. In addition, the contract addressed the release of water from the dams. Specifically, Section 01 00 10, Part 1.4 explained that “under normal conditions” the operational, combined release of water from the Addicks and Barker dams was limited to 2,000 cubic feet per second (CFS) as measured downstream at the Piney Point gauging station (JSF ¶ 4; R4, tab 1 at 2628-29). Section 00 31 33, Paragraph 2.3 of the contract similarly provided that the combined releases could not exceed 2,000 CFS “under normal operating conditions” and that the maximum discharge from one reservoir of 2,000 CFS required the other to be closed (JSF ¶ 5; R4, tab 1 at 2536, 2545). Part 1.4.1 addressed emergency operations at the dams (R4, tab 1 at 2629). The contract explained that when emergency scheduled releases were in effect, releases could reach 8,000 CFS for each dam (id. at 2544).

4. On September 29, 2015, the Corps issued, and Granite acknowledged, a Notice to Proceed. The notice established a required completion date of the contract of May 31, 2019. (JSF ¶ 2; see also R4, tab 2)

1 In their briefs, both parties utilized the Joint Stipulations of Fact filed with the Board on June 12, 2020. The JSF serves as the basis for our Findings of Fact except as noted.

2 5. Almost two years later, on August 25, 2017, Hurricane Harvey made landfall on the coast of Texas bringing rain and flooding to Houston, which included the contract project site at the Addicks and Barker dams (JSF ¶ 6). On or before August 28, 2017, but after the hurricane made landfall, the Corps began releasing water from the Addicks and Barker dams (JSF ¶ 7). At all times relevant to this action, the Corps exercised exclusive control over the operation of the Addicks and Barker dams (JSF ¶ 3).

6. The combined flow rate of the released water increased to over 4,000 CFS (JSF ¶ 7). The Corps continued to increase the combined flows of water from the Addicks and Barker dams through August 29, 2017 (JSF ¶ 8). By August 29, 2017, the combined discharges from the Addicks and Barker dams into the Buffalo Bayou, in conjunction with flows entering the Buffalo Bayou downstream of the dams, caused the measured flow at the Piney Point gauging station to exceed 10,000 CFS (JSF ¶ 9).

7. On September 5, 2017, the Corps issued Serial Letter No. C-0039, directing Granite to “SUSPEND WORK,” retroactively to August 28, 2017 and prospectively through October 15, 2017, on construction of the new outlet structure at the Addicks dam site; construction of cutoff walls and new outlet structure at the Barker dam site; and construction of cutoff walls at the Noble Road site of the Barker dam (JSF ¶ 10; R4, tab 3). The suspension of work, issued pursuant to FAR 52.242-14, did not apply to emergency repairs of damage to the dams (pursuant to contract parts 1.4.1 relating to emergency operations and 1.5 relating to damage to work), repairs to damaged work caused by the Hurricane Harvey floods (pursuant to contract part 1.5 relating to damage to work), construction activities related to recovery and restoration that could be performed safely, and activities not affected by the flooding around the dams (JSF ¶ 11; R4, tab 3 at 3583-84). The total period of suspension ordered by the contracting officer was 49 calendar days (JSF ¶ 12).

8. The alternate administrative contracting officer (AACO) who issued the suspension letter explained in a declaration that he considered the following when calculating the number of days to suspend work: the Tax Day Flood in April 2016; the forecast magnitude for Hurricane Harvey; the projections of conditions for the dams from the Corps’ Water Management System (CWMS) models; and discussions with others including Granite’s project manager (R4, tab G-57 at 3893). The CWMS models provided information on current and projected inflows, outflows, stage levels, and projected dates when the flood waters would be fully discharged from each dam. The AACO also considered the time Granite would need to restore the project site before it could resume work. The AACO explained that the project sites were initially under water due to the record flood and most of the partially constructed work was completely submerged. (Id. at 3894)

9. On November 3, 2017, both Granite and the Corps executed Modification No. A00030, which extended the contract time by 49 calendar days (JSF ¶ 13; R4,

3 tab 4 at 3753-54).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

CEMS, Inc. v. United States
59 Fed. Cl. 168 (Federal Claims, 2003)
George Sollitt Construction Co. v. United States
64 Fed. Cl. 229 (Federal Claims, 2005)
P.J. Dick Inc. v. Principi
324 F.3d 1364 (Federal Circuit, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
Granite Construction Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/granite-construction-company-asbca-2023.