Gragg v. James

1969 OK 58, 452 P.2d 579
CourtSupreme Court of Oklahoma
DecidedMarch 25, 1969
Docket41696
StatusPublished
Cited by26 cases

This text of 1969 OK 58 (Gragg v. James) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gragg v. James, 1969 OK 58, 452 P.2d 579 (Okla. 1969).

Opinion

BERRY, Vice Chief Justice.

Appellants, a copartnership hereafter designated as Gragg, appeals from a judgment rendered in favor of defendant in error, James, referred to as plaintiff, in his action to recover for labor and materials furnished under subcontract for construction of a state road project.

Gragg was a qualified bidder upon state highway construction projects involving federal and state road funds, being bonded by United Pacific Insurance Company, a trial court defendant not involved in this appeal. Paul Kealiher, hereafter the defendant, was a highway construction engineer and contractor, but not qualified to bid projects in his own name. Although both the nature and effect of their relationship is disputed, these parties joined in bidding and performance of highway construction projects under written contract. Upon defendant’s engineering knowledge projects *582 would be bid in Gragg’s name and contracts secured under successful bids then would be assigned to defendant for actual performance. For use of the name in bidding, handling of payrolls and participation or supervision in the project Gragg received 3% of the total contract. Generally defendant handled culvert and bridge work and sublet other portions of the projects with Gragg’s knowledge.

Contracts between Gragg and defendant all contained provisions against subletting of a construction project without written consent. Highway department contracts likewise prohibited assignment except to .a certified contractor, and in no event more than 50% of the contract. This was known to defendant and Gragg, although the department’s rules and regulations were not introduced into evidence. The surety company guaranteed against Gragg’s default upon each of the three projects bid and assigned to defendant. Although this appeal primarily concerns work completed on the Kay County project, necessary reference to collateral matters involved under other contracts will designate the project by name of the county where located.

Plaintiff alleged Gragg secured the Kay County highway contract in March 1963, and then subcontracted this project to defendant. Defendant then contracted in writing with plaintiff to furnish labor and materials for dirt moving at the same price. Plaintiff completed this portion of the work and thereby was entitled to $7,518.50, for which demand had been made upon all defendants but remained unpaid, and judgment was sought for this amount.

Defendant answered by general denial, although admitting Gragg secured the contract and sublet to defendant, who in turn sublet to plaintiff, and that $5,813.65 was due defendant upon the Kay County project. Defendant then cross-petitioned against Gragg claiming $3,070.74 due and owing for defendant’s performance of work under a contract performed in McCurtain County, and the further sum of $6,570.89 due for work performed under contract in Pushma-taha County. Defendant asked judgment for total of $15,455.39 under cross-petition for work performed under three contracts with Gragg.

Gragg generally denied defendant’s allegations, other than admitting Union Pacific’s execution of the bond. Gragg’s cross-petition admitted execution of the written contracts for road construction in the named counties and the agreement to furnish defendant’s payrolls, but asserted contracts were non-assignable without written consent, and there was no contract with plaintiff, or consent for defendant’s subletting, so neither plaintiff nor defendant was entitled to judgment. Additionally, Gragg admitted the amount due defendant on the McCurtain project was unpaid, having been applied against a net loss resulting from the Pushmataha project. Further the amount ($5,813.76) due defendant upon the Kay contract also had been applied against the Pushmataha project loss, thereby leaving total deficit of $54,756.63 for which Gragg asked judgment. Defendant insurer alleged full compliance with terms of the bond as well as the further defense of the statute of limitations.

Defendant replied denying contrary allegations and affirmatively alleged Gragg’s indebtedness under three contracts: Kay $5,900.15; McCurtain $3,070.74; Pushmata-ha $6,570.89. Defendant specifically denied indebtedness for loss on Pushmataha project, asserting any loss was fault of Gragg for assigning all of such contract except culvert work which defendant completed, and after deduction of all credits sum of $6,570.89 was due from Gragg. Further, having tacitly consented to Gragg’s subletting of contract defendant was released from liability for work performed by .another subcontractor (Logan), and was entitled to judgment for $15,541.78 due under three contracts.

At opening of the trial plaintiff was granted leave to amend and show $6,869.59 as the amount claimed. Defendant then amended answer to admit such .amount was due and owing and plaintiff was entitled *583 to judgment for such amount. Early in the trial defendant and Gragg stipulated a profit of $5,813.76 from the Kay project and $3,070.74 from McCurtain project would have been due defendant except for offset claimed on the Pushmataha contract. A further effort to stipulate as to a possible profit due defendant on the latter contract was nullified by Gragg’s refusal upon the ground the entire contract assigned to defendant was a single project and various items of construction costs were not separable.

The issues here involved concern the trilateral rights of those parties who actively engaged in performance of the highway construction contracts. The principle contention is based primarily upon error allegedly resulting from the trial court’s refusal to enforce Gragg’s subcontract with defendant. Several contentions, and much of the supporting argument, principally concern evidentiary matters which necessitates summation of a portion of the evidence.

The three project contracts were identical other than as to dates and construction site. The Pushmataha contract, of principal concern here, in substance provided as consideration for subletting that defendant furnish materials and equipment, discharge all duties and obligations diligently and promptly, and complete all operations imposed upon Gragg by the original contract. For failure, neglect, or discontinuance defendant’s rights were forfeitable without notice or demand, and Gragg could take over and complete the project with defendant remaining liable for completion costs. Any payments by Gragg were reimbursable from and constituted a lien upon contract funds or any assets of defendant, as security for all contractual obligations. Gragg was to pay defendant the full contract price received from the state, less 3% fixed charge. The contract was not to be assigned or sublet without Gragg’s written consent.

In June 1963 Gragg learned the Pushma-taha project was behind schedule. After discussion with defendant, Gragg requested another contractor (Logan) to survey the job. This party ultimately completed the dirt work during the time defendant was completing culverts and bridges on the project. Eventual completion of this project resulted in $54,756.63 loss according to Gragg’s testimony.

Plaintiff’s evidence concerning the contract, performance thereunder, and right to payment was uncontroverted and sufficient to support the allegation of the petition.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Trant v. Oklahoma
874 F. Supp. 2d 1294 (W.D. Oklahoma, 2012)
People ex rel. S.M.A.M.A.
172 P.3d 958 (Colorado Court of Appeals, 2007)
Anderson v. Boeing Co.
222 F.R.D. 521 (N.D. Oklahoma, 2004)
Schlesinger v. Woodcock
2001 WY 120 (Wyoming Supreme Court, 2001)
Hardison v. Balboa Insurance
4 F. App'x 663 (Tenth Circuit, 2001)
Central Plains Construction v. Hickson
1998 OK CIV APP 83 (Court of Civil Appeals of Oklahoma, 1998)
Black v. Baker Oil Tools
Tenth Circuit, 1997
Prough v. Edinger, Inc.
1993 OK 130 (Supreme Court of Oklahoma, 1993)
First National Bank & Trust Co. of Stillwater v. McKown
1993 OK CIV APP 156 (Court of Civil Appeals of Oklahoma, 1993)
Sigma Resources Corp. v. Norse Exploration, Inc.
1992 OK CIV APP 160 (Court of Civil Appeals of Oklahoma, 1992)
Prows v. State
822 P.2d 764 (Utah Supreme Court, 1991)
LeFlore v. Reflections of Tulsa, Inc.
1985 OK 72 (Supreme Court of Oklahoma, 1985)
Martin v. Chapel, Wilkinson, Riggs, and Abney
1981 OK 134 (Supreme Court of Oklahoma, 1981)
Greene v. Circle Insurance Company
1976 OK 173 (Supreme Court of Oklahoma, 1976)
National Zinc Co. v. Moody
1976 OK 156 (Supreme Court of Oklahoma, 1976)
Commercial Solvents Corp. v. Liberty Mutual Insurance
371 F. Supp. 247 (S.D. New York, 1974)
Andrews v. Liberty National Bank & Trust Co.
463 P.2d 953 (Supreme Court of Oklahoma, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
1969 OK 58, 452 P.2d 579, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gragg-v-james-okla-1969.