Gradetech v. City of San Jose CA1/2

CourtCalifornia Court of Appeal
DecidedJanuary 10, 2023
DocketA165825
StatusUnpublished

This text of Gradetech v. City of San Jose CA1/2 (Gradetech v. City of San Jose CA1/2) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gradetech v. City of San Jose CA1/2, (Cal. Ct. App. 2023).

Opinion

Filed 1/10/23 Gradetech v. City of San Jose CA1/2 NOT TO BE PUBLISHED IN OFFICIAL REPORTS California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication or ordered published for purposes of rule 8.1115.

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

FIRST APPELLATE DISTRICT

DIVISION TWO

GRADETECH, INC., Plaintiff and Appellant, v. A165825 CITY OF SAN JOSE, (Santa Clara County Super. Ct. Defendant and Respondent. No. 18CV325319)

Plaintiff Gradetech, Inc. (Gradetech) sued defendant City of San Jose (City) in a single-count complaint alleging breach of contract. Gradetech’s suit seeks to recover compensation for multiple cost overages arising from Gradetech’s construction of a freestyle bike park. The City cross-complained, asserting that Gradetech’s claims for cost overages were false claims within the meaning of the False Claims Act (Gov. Code, §§ 12650 & 950 et seq.), and certain municipal code sections. The City also asserted several breach of contract causes of action and two claims for declaratory relief. Gradetech responded by filing a special motion to strike the entire cross-complaint under Code of Civil Procedure section 425.16 (anti-SLAPP statute). The trial court partially denied and partially granted the motion,

1 and found it moot as to several causes of action the City withdrew. The trial court also denied both parties’ motions for attorneys’ fees. Gradetech now appeals the partial denial of its anti-SLAPP motion, as well as the denial of its motion for attorneys’ fees. It argues the trial court erroneously found certain attorney demand letters it sent the City in advance of its lawsuit were merely prerequisites to being compensated under the terms of the contract; if the trial court had properly construed these letters, Gradetech argues, it would have understood them to be protected speech under the anti-SLAPP statute. We affirm in part and reverse and remand in part. The trial court properly found the City’s breach of contract cross-claims arose out of Gradetech’s performance of the contract, not the litigation process itself, and thus those claims properly survived the anti-SLAPP motion. But the same is not true of the City’s cross-claims arising out of Gradetech’s attorney demand letters. Those letters were protected speech under the anti-SLAPP statute because they were prepared and sent in contemplation of the litigation that Gradetech filed shortly after sending them. We reverse the trial court’s order denying the anti-SLAPP motion as to the claims arising out of the attorney demand letters and remand for the trial court to determine whether the City can prevail at the second step of the anti-SLAPP analysis by demonstrating that its cross-claims predicated upon these letters possess the requisite minimal merit to proceed. In light of our disposition, we vacate the trial court’s ruling on attorneys’ fees. BACKGROUND A. The Project The City and Gradetech executed a $2,208,300 contract (the Contract) to construct the Lake Cunningham Bike Park Construction Project (the

2 Project), effective March 28, 2016. The City’s briefing explains that this Project called for “precision sculpting of hills, curves, grades, jumps, and other park features.” The City further explains that these features require precision construction because of the “physics” involved: these graded features must “sequentially lead[] one into the other” in a particular fashion in order to permit bike riders of different experience levels to safely navigate the park and its features. The contract dispute underlying this case arose after Gradetech incurred multiple cost and time overages in constructing the Project. The City emphasizes that the Contract called for 215 days but the Project was not completed for 540 days. The City offers that the delay and cost overages were attributable to Gradetech’s lack of experience in designing bike parks. Gradetech counters that the delay and cost overages it sustained were attributable to significant “change in quantities” 1 of the movable earth involved: according to its brief, a surveying company “concluded the Project’s dirt jumps quantities more than doubled . . . .” As a result of this change in volume, Gradetech contended it was entitled to additional compensation. B. The September and November Demand Letters and the Government Code Claim Gradetech expressed its view that it was entitled to additional compensation, and that the conditions precedent in the Contract which entitled it thereto were met,2 by means of several letters it sent the City toward the end of 2017. We describe these letters in detail because they

1 The Contract, subject to multiple conditions precedent, entitles Gradetech to additional compensation when changes to the Project cause “a significant change in quantities.” 2 See footnote 7, post.

3 comprise the “protected” activity Gradetech claims the City retaliated against through its filing of its cross-complaint. On September 22, 2017, counsel for Gradetech sent the City a letter notifying it of a potential claim for overages (September letter). Gradetech sought $587,795.07 arising from “additional earthwork and grading operations to change jump dirt grades that were already to grades shown on the plans in the contract documents.” The total amount sought was $587,795.07, consisting of $494,830.57 for “work”; $74,224.50 for “15% markup”; and $18,740 for “survey, etc.” Gradetech emphasizes this letter was sent by legal counsel and that it states: “This letter is prepared in advance of potential litigation . . . .” Then, on November 15, 2017, Gradetech sent another letter to the City (November letter). This letter repeated the same claim for $587,795.07 in cost overage and sought additional compensation in the amounts of $102,042.36, $131,132.94, $593,674, and $439,141.06. The November letter likewise advised the City that it was sent “in advance of potential litigation.” This letter also contained a certification made under penalty of perjury by Gradetech’s president that he “thoroughly reviewed the attached claim . . . and know[s] its contents, and said claim is made in good faith; the supporting data is truthful and accurate; [and] that the amount requested accurately reflects the contract adjustment for which the contractor believes the owner is liable . . . .”3 Finally, on January 23, 2018, Gradetech submitted a verified claim for money damages against the City under Government Code section 905 et seq. 4

We will hereafter refer to the September letter and the November 3

letter collectively as the attorney demand letters. The California governmental liability statutes make all public entities 4

in California liable in tort insofar as declared by statute. (3 Witkin, Cal.

4 and San Jose Municipal Code sections 1.20.010 through 1.20.240 (Government Code claim). The Government Code claim was entitled “Notice of Claim and Claim by Gradetech, Inc.” and was certified by Gradetech’s president under the penalty of perjury, using the same language as in his certification in the November letter. It stated that “[t]he claim concerns . . . the contract balance for the work completed in connection with the construction of Lake Cunningham Bike Park, as well as for increased quantities on the project, potential change orders, the re-grading of jumps, and right-of-way delay.” The 45-day statutory period for the City to respond lapsed and thus the Government Code claim was rejected, in the City’s words, “by operation of law.”5 C. Gradetech’s Complaint Gradetech filed suit against the City on March 21, 2018, asserting a single cause of action for breach of contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Oasis West Realty v. Goldman
250 P.3d 1115 (California Supreme Court, 2011)
Foley v. Interactive Data Corp.
765 P.2d 373 (California Supreme Court, 1988)
Briggs v. Eden Council for Hope & Opportunity
969 P.2d 564 (California Supreme Court, 1999)
City of Pomona v. Superior Court
107 Cal. Rptr. 2d 710 (California Court of Appeal, 2001)
Rothschild v. Tyco Internationall (US), Inc.
99 Cal. Rptr. 2d 721 (California Court of Appeal, 2000)
Church of Scientology v. Wollersheim
42 Cal. App. 4th 628 (California Court of Appeal, 1996)
Neville v. CHUDACOFF
73 Cal. Rptr. 3d 383 (California Court of Appeal, 2008)
ComputerXpress, Inc. v. Jackson
113 Cal. Rptr. 2d 625 (California Court of Appeal, 2001)
Kajima Engineering & Construction, Inc. v. City of Los Angeles
116 Cal. Rptr. 2d 187 (California Court of Appeal, 2002)
Navellier v. Sletten
52 P.3d 703 (California Supreme Court, 2002)
City of Cotati v. Cashman
52 P.3d 695 (California Supreme Court, 2002)
Soukup v. Law Offices of Herbert Hafif
139 P.3d 30 (California Supreme Court, 2006)
Flatley v. Mauro
139 P.3d 2 (California Supreme Court, 2006)
Holguin v. Dish Network LLC
229 Cal. App. 4th 1310 (California Court of Appeal, 2014)
Wilson v. Cable News Network, Inc.
444 P.3d 706 (California Supreme Court, 2019)
Bailey v. Brewer
197 Cal. App. 4th 781 (California Court of Appeal, 2011)
Hecimovich v. Encinal School Parent Teacher Organization
203 Cal. App. 4th 450 (California Court of Appeal, 2012)
City of Costa Mesa v. D'Alessio Investments
214 Cal. App. 4th 358 (California Court of Appeal, 2013)
Laker v. Bd. of Trs. of the Cal. State Univ.
244 Cal. Rptr. 3d 238 (California Court of Appeals, 5th District, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
Gradetech v. City of San Jose CA1/2, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gradetech-v-city-of-san-jose-ca12-calctapp-2023.