Gracepoint Holding Company, LLC v. FJR Sand, Inc.

CourtCourt of Appeals of Texas
DecidedJanuary 7, 2020
Docket01-19-00574-CV
StatusPublished

This text of Gracepoint Holding Company, LLC v. FJR Sand, Inc. (Gracepoint Holding Company, LLC v. FJR Sand, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gracepoint Holding Company, LLC v. FJR Sand, Inc., (Tex. Ct. App. 2020).

Opinion

Opinion issued January 7, 2020

In The

Court of Appeals For The

First District of Texas ———————————— NO. 01-19-00574-CV ——————————— GRACEPOINT HOLDING COMPANY, LLC, Appellant V. FJR SAND, INC., Appellee

On Appeal from the 270th District Court Harris County, Texas Trial Court Case No. 2018-23155

MEMORANDUM OPINION

FJR, Inc. sued Gracepoint Holding Company, LLC for breaching the terms of

a written contract between the parties. Based on an arbitration agreement in the

contract, Gracepoint moved to compel arbitration of FJR’s claims under the Federal Arbitration Act (“FAA”).1 FJR responded, asserting that Gracepoint had waived

arbitration by substantially invoking the judicial process. The trial court denied

Gracepoint’s motion to compel arbitration.

In one issue, Gracepoint appeals the trial court’s order denying its motion.2

Because FJR did not meet its heavy burden to show that Gracepoint impliedly

waived its right to arbitrate under a valid arbitration agreement, we reverse the trial

court’s denial of the motion to compel arbitration and remand to the trial court.

Background

Gracepoint is a residential homebuilder. On July 12, 2012, Gracepoint and

FJR signed an Independent Contractor Agreement (“ICA”). Under the ICA’s terms,

FJR agreed to provide grading services and materials to Gracepoint, and Gracepoint

agreed to pay FJR for its services and materials.

The ICA also contains an arbitration agreement, requiring

any claim, controversy, or dispute of any kind among the parties, now existing or arising in the future, whether relating to the interpretation of any provision of this agreement, the rights and obligations of the parties under this agreement, any other agreement relating to, or arising from, the business of Gracepoint or the Work, shall be submitted to binding arbitration under the Federal Arbitration Act, 9 U.S.C 1 et seq. The arbitration shall be conducted by the American Arbitration Association (“AAA”).

1 See 9 U.S.C. §§ 1–16. 2 See TEX. CIV. PRAC. & REM. CODE § 51.016 (permitting interlocutory appeal from order denying motion to compel arbitration under FAA). 2 In January 2015, FJR filed suit against Gracepoint. FJR alleged that

Gracepoint breached the ICA by failing to pay for $27,138 worth of services

provided to Gracepoint during the period of April 2010 to March 2014.

Six months later, in September 2015, Gracepoint filed a motion to arbitrate

FJR’s claims pursuant to the ICA’s arbitration agreement. FJR agreed to arbitrate its

claims.

The trial court signed an agreed order to arbitrate in October 2015. The court

noted that FJR had agreed to arbitrate “as evidenced by the signature of [FJR’s]

counsel on this Agreed Order.” The agreed order required the parties to “institute

arbitration.” The parties, however, never engaged in arbitration. In November 2017,

two years after the agreed order was signed, FJR nonsuited its claims.

In April 2018, FJR filed the instant suit, asserting the same causes of action

against Gracepoint that it had asserted in its January 2015 petition in the first suit.

As in the first action, FJR claimed that Gracepoint breached the ICA and owed it

$27,138 for services it had provided to Gracepoint. There was, however, a difference

in FJR’s factual allegations. In the earlier 2015 suit, FJR had alleged that it provided

the services between April 2010 and March 2014. In the instant suit, FJR initially

alleged that it provided the services between April 2010 and April 2014.

Gracepoint answered the suit two weeks after suit was filed, generally denying

FJR’s claims, asserting the affirmative defense of limitations, and asserting that

3 FJR’s claims were subject to the ICA’s binding arbitration agreement. To its answer,

Gracepoint attached the affidavit of Randall Birdwell, its company representative.

In the affidavit, Birdwell testified, “The ICA mandates arbitration as the avenue by

which the parties will resolve any disputes.” He specifically quoted the ICA’s

arbitration language. Birdwell concluded his affidavit by stating, “Gracepoint

disputes that FJR is owed any additional money, but there is no question that this

controversy arises from the contract, and therefore should be arbitrated.”

On June 20, 2018, two months after it answered the suit, Gracepoint filed a

motion for summary judgment, asserting that FJR’s claims were barred by

limitations. Gracepoint pointed out that, in the original 2015 suit, FJR had alleged

that it last provided services to Gracepoint in March 2014, but in the instant suit, it

alleged that it had last provided services to Gracepoint in April 2014. Gracepoint

claimed that FJR was attempting to avoid the four-year-statute of limitations by

changing the date of when it last provided services to Gracepoint.

One month later—on July 30, 2018—FJR filed its First Amended Petition.

FJR changed the date that it last provided services to Gracepoint from April 2014

back to March 2014. FJR asserted a new factual allegation, claiming that Gracepoint

had breached the ICA in May 2014 by failing to pay the full amount of FJR’s

invoices. FJR attached the ICA to its First Amended Petition and incorporated it by

reference.

4 That same day, FJR also responded to Gracepoint’s motion for summary

judgment. FJR asserted that its suit was not time-barred because its claims did not

accrue until Gracepoint breached its contractual obligation in May 2014 by failing

to pay the invoices in full. Gracepoint passed on submission of the motion, and the

trial court never ruled on it.

Gracepoint filed a motion to arbitrate in March 2019 and an amended motion

to arbitrate in June 2019. Gracepoint relied on the arbitration agreement in the ICA,

asserting that the parties had agreed to arbitrate disputes arising out of or relating to

the ICA under the FAA. Gracepoint also pointed out that FJR had agreed to arbitrate

its claims in the 2015 suit, which involved the same claims brought in the instant

suit. Gracepoint attached the trial court’s October 2015 agreed order from the earlier

suit, which had ordered the parties to institute arbitration. Gracepoint averred that

FJR “never instituted [the] arbitration proceeding,” but instead nonsuited its claims

two years after the agreed order, in November 2017, when the trial court set the case

for dismissal for want of prosecution.

FJR responded to the motion to compel arbitration, requesting denial of the

motion for four reasons. First, FJR claimed that the FAA did not apply because the

ICA “does not relate to interstate commerce.” Second, “it would be inequitable to

compel arbitration after the parties [had] engaged in substantial discovery.” Third,

Gracepoint had filed a motion for summary judgment, seeking relief on the merits.

5 Finally, FJR claimed that Gracepoint “failed to take any affirmative steps to set up

the arbitration [in the 2015 suit]” and that Gracepoint “refused to communicate with

[FJR’s counsel] when he attempted to set up an arbitration arrangement.” However,

FJR attached no evidence to support any of the arguments it made in the response.

In its reply, Gracepoint pointed out that the parties had expressly selected the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rodriguez v. Transnave Inc.
8 F.3d 284 (Fifth Circuit, 1993)
Keytrade USA, Inc. v. AIN TEMOUCHENT M/V
404 F.3d 891 (Fifth Circuit, 2005)
In Re Vesta Insurance Group, Inc.
192 S.W.3d 759 (Texas Supreme Court, 2006)
Perry Homes v. Cull
258 S.W.3d 580 (Texas Supreme Court, 2008)
In Re Fleetwood Homes of Texas, L.P.
257 S.W.3d 692 (Texas Supreme Court, 2008)
In Re Rubiola
334 S.W.3d 220 (Texas Supreme Court, 2011)
Horizon/CMS Healthcare Corporation v. Auld
34 S.W.3d 887 (Texas Supreme Court, 2000)
In Re Service Corporation Intern.
85 S.W.3d 171 (Texas Supreme Court, 2002)
Chilton Insurance Co. v. Pate & Pate Enterprises, Inc.
930 S.W.2d 877 (Court of Appeals of Texas, 1996)
In Re H&R Block Financial Advisors, Inc.
262 S.W.3d 896 (Court of Appeals of Texas, 2008)
In Re Bruce Terminix Co.
988 S.W.2d 702 (Texas Supreme Court, 1998)
Regency Advantage Ltd. Partnership v. Bingo Idea-Watauga, Inc.
936 S.W.2d 275 (Texas Supreme Court, 1997)
G.T. Leach Builders, LLC v. Sapphire V.P., Lp
458 S.W.3d 502 (Texas Supreme Court, 2015)
John Stephen Philips v. Gail McNease
467 S.W.3d 688 (Court of Appeals of Texas, 2015)
in the Estate of Rosa Elvia Guerrero
465 S.W.3d 693 (Court of Appeals of Texas, 2015)
Richmont Holdings, Inc. v. Superior Recharge Systems, L.L.C.
455 S.W.3d 573 (Texas Supreme Court, 2014)
Fredericksburg Care Co. v. Perez
461 S.W.3d 513 (Texas Supreme Court, 2015)
RSL Funding, LLC v. Pippins
499 S.W.3d 423 (Court of Appeals of Texas, 2016)
Henry v. Cash Biz, LP
551 S.W.3d 111 (Texas Supreme Court, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Gracepoint Holding Company, LLC v. FJR Sand, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/gracepoint-holding-company-llc-v-fjr-sand-inc-texapp-2020.