GP3 II, LLC v. Litong Capital, LLC

35 F.4th 1124
CourtCourt of Appeals for the Eighth Circuit
DecidedJune 3, 2022
Docket21-1443
StatusPublished
Cited by2 cases

This text of 35 F.4th 1124 (GP3 II, LLC v. Litong Capital, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
GP3 II, LLC v. Litong Capital, LLC, 35 F.4th 1124 (8th Cir. 2022).

Opinion

United States Court of Appeals For the Eighth Circuit ___________________________

No. 21-1443 ___________________________

GP3 II, LLC

Plaintiff - Appellee

v.

Litong Capital, LLC

Defendant - Appellant

Bank of the West

Defendant - Appellee ____________

Appeal from United States District Court for the Western District of Missouri ____________

Submitted: January 12, 2022 Filed: June 3, 2022 ____________

Before LOKEN, GRUENDER, and GRASZ, Circuit Judges. ____________

GRASZ, Circuit Judge. The district court1 denied Litong Capital, LLC’s (“Litong”) motion to compel arbitration, holding the person who purportedly signed the arbitration agreement on behalf of GP3 II, LLC (“GP3”) did not have authority to do so. We affirm.

I. Background

The factual background of this lawsuit is complicated and at times puzzling. However, this appeal is about a single contract and whether a man named Ron Green had authority to sign it on behalf of GP3. Thus, we limit this background to the facts relevant to this appeal. 2

GP3 was created by a general contractor as an investment vehicle for a water pipeline project in New Mexico (the “Project”). Litong became involved with the Project by way of this story’s mysterious middleman, Steve Lin. Litong claims Lin contacted its president, Xinhua “Alice” Song, requesting Litong procure pipe for the Project. Song never met Lin but believed Lin was GP3’s broker. Around the same time, Lin began dealing with Michael Heitmann, GP3’s sole member and manager, who testified he believed Lin was an agent of Litong. Heitmann testified he believed Litong was added to the Project to obtain additional financing for the Project. Lin has become unavailable to the parties.

According to Litong, Lin brokered a sales agreement between Litong and GP3 (the “Contract”). Under the Contract, GP3 would pay Litong $19,978,350 to procure specified pipe for the Project. The Contract also included an arbitration provision, which in part specified:

1 The Honorable Beth Phillips, Chief Judge, United States District Court for the Western District of Missouri. 2 For a thorough background of this lawsuit and the events leading thereto, see the district court’s order denying Litong’s motion to compel. GP3 II, LLC v. Bank of the West, No. 20-424, 2021 WL 5514005, at *1–3 (W.D. Mo. Jan. 28, 2021) (unpublished). -2- In case no settlement can be reached, the case may then be submitted for arbitration to the Arbitration committee of the Court of Beijing[,] China. The arbitration shall take place in Beijing[,] China and shall be final and binding on both parties; neither party shall seek recourse to a law court or other authorities for revision of the decision.

The formation of the Contract is at the center of this appeal. Song signed the Contract on behalf of Litong. In the “Buyer” signature block, the name “Ron Green” is signed with Green labeled “Partner” of GP3. Green, who denies he signed the Contract, was the president and manager of New Mexico Regional Water, LLC, the Project’s developer (the “Developer”). Green testified he was neither a member, partner, nor employee of GP3. Green also testified that no person at GP3 ever told him he could sign the Contract, and he did not believe he had such authority. GP3 claims it was not aware of the Contract until after it filed this lawsuit. Song testified she believed Green had authority to sign the Contract because Lin told her Green was a partner of GP3 with signing authority.

The Project eventually fell through, and GP3 sued Litong, along with Bank of the West, to whom Litong assigned its rights to payment due under the Contract, seeking injunctive and declaratory relief against both parties and alleging fraud against Litong. Bank of the West filed an answer which included counterclaims against GP3 for breach of contract, fraud, and negligent misrepresentation and crossclaims against Litong for breach of contract and fraud. Litong moved to compel arbitration under 9 U.S.C. § 4 of the Federal Arbitration Act (the “FAA”), arguing GP3’s and Bank of the West’s claims were subject to the arbitration provision in the Contract. The district court denied Litong’s motion to compel arbitration, holding that even assuming Green signed the Contract, he did not have authority to sign it on behalf of GP3. The district court concluded that because the relied-on arbitration provision is not part of a valid agreement between the parties, neither GP3’s nor Bank of the West’s claims are subject to the provision.

Litong appeals the district court’s denial of its motion to compel arbitration, claiming the district court erred by holding Green lacked authority to enter the -3- Contract on behalf of GP3. Litong also asks this court to compel arbitration of Bank of the West’s claims—even though Bank of the West was not a party to the Contract—under the principles of incorporation by reference and estoppel.

II. Analysis

We review the district court’s denial of a motion to compel arbitration under § 4 of the FAA de novo, though we review the district court’s findings of fact underpinning its arbitrability ruling for clear error. Duncan v. Int’l Mkts. Live, Inc., 20 F.4th 400, 402 (8th Cir. 2021). Under the FAA, “[a] motion to compel arbitration must be granted ‘if a valid arbitration clause exists which encompasses the dispute between the parties.’” M.A. Mortenson Co. v. Saunders Concrete Co., 676 F.3d 1153, 1156–57 (8th Cir. 2012) (quoting 3M Co. v. Amtex Sec., Inc., 542 F.3d 1193, 1198 (8th Cir. 2008)).

A. Arbitrability of Green’s Authority

Before deciding whether Green had authority to sign the Contract for GP3, we address Litong’s argument that the issue of Green’s authority is an issue for arbitration. Litong relies on Supreme Court precedent holding questions over the validity of a contract containing an arbitration provision are for the arbitrator in the first instance. See, e.g., Buckeye Check Cashing, Inc. v. Cardegna, 546 U.S. 440, 444–46 (2006). In Buckeye, the Supreme Court distinguished between two kinds of claims challenging the validity of arbitration agreements. One kind of claim challenges the validity of the arbitration provision itself, and a federal court may adjudicate these challenges. See id. The other type of claim challenges the validity of the contract as a whole, and these challenges are for the arbitrator. See id.

The Court in Buckeye, however, stated that issues of contract formation— specifically, issues related to the authority of a signor—do not necessarily fall in the “validity of the contract as a whole” bucket of claims:

-4- The issue of the contract’s validity is different from the issue whether any agreement between the alleged obligor and obligee was ever concluded. Our opinion today . . . does not speak to the issue . . . [of] whether the signor lacked authority to commit the alleged principal . . . .

Id. at 444 n.1. The Court later affirmed “that where the dispute at issue concerns contract formation, the dispute is generally for courts to decide.” Granite Rock Co. v. Int’l Bhd. of Teamsters, 561 U.S. 287, 296 (2010). Because a signor’s authority to bind a purported principal is an issue of contract formation, see Buckeye, 546 U.S.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jabbok Schlacks v. Neil Chheda
Eighth Circuit, 2026
Landcastle Acquisition Corp. v. Renasant Bank
57 F.4th 1203 (Eleventh Circuit, 2023)

Cite This Page — Counsel Stack

Bluebook (online)
35 F.4th 1124, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gp3-ii-llc-v-litong-capital-llc-ca8-2022.