Gould Electronics Inc. v. Livingston Cnty. Road Comm'n

Court of Appeals for the Sixth Circuit·Decided May 10, 2022·No. 20-2267·Unpublished

Opinion

NOT RECOMMENDED FOR PUBLICATION File Name: 22a0193n.06

Nos. 20-2257/2267

UNITED STATES COURT OF APPEALS FOR THE SIXTH CIRCUIT

)

FILED

GOULD ELECTRONICS INC., May 10, 2022 )

) DEBORAH S. HUNT, Clerk Plaintiff-Appellant/Cross-Appellee, )

v. ) ON APPEAL FROM THE ) UNITED STATES DISTRICT LIVINGSTON COUNTY ROAD COMMISSION, ) COURT FOR THE EASTERN ) DISTRICT OF MICHIGAN Defendant-Appellee/Cross-Appellant. )

)

)

Before: BOGGS, GIBBONS, and NALBANDIAN, Circuit Judges.

BOGGS, Circuit Judge. This case concerns a near-thirty-year dispute about environmental cleanup at the site of the former Roosevelt Street Factory in Livingston County, Michigan. Between 1961 and 1976, the property was owned by Gould Electronics. Immediately adjacent to the prop- erty is a facility owned since 1933 by the Livingston County Road Commission. Both tenants appear to have used the carcinogenic degreasing agent trichloroethylene (TCE) on their properties. In 1993, the Michigan Department of Environment, Great Lakes, and Energy discovered that an area straddling both parcels contained dangerous levels of TCE. The Department identified both tenants as potential polluters. Predictably, each blamed its neighbor and sought to recover costs under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), 42 U.S.C. § 9607(a), and its state equivalent.

In 2009, after the Department ordered Gould to clean up the entire affected area, Gould sued the Commission to apportion liability for any TCE contamination. In 2012, just before trial,

the parties signed a tolling agreement and agreed to stay the litigation while the Department con- sidered who was liable. When the Department finally reached a conclusion in 2017—that it could not tell who was liable—Gould revived the suit. The Commission then moved to amend its answer and file a CERCLA counterclaim under 42 U.S.C. § 9613(f), a request the district court granted. In mid-2020, the court decided not to delay the trial amid the COVID-19 pandemic, instead con- ducting it by online videoconference over the objections of both parties.

After hearing from dueling experts in a seven-day bench trial, the district court found that Gould had been the “sole cause” of the TCE contamination. Using its equitable powers, however, the court considered the Commission’s lack of care with respect to the contamination that had seeped onto its property, as well as its repeated refusal to cooperate with the Department’s inves- tigations, and decided to hold Gould only 95 percent liable for the costs of the cleanup (effectively reducing the Commission’s recovery by 5 percent of Gould’s costs, or $212,664.85). Gould was ordered to pay the Commission a net total of $962,153.07.

Gould now alleges a host of procedural and substantive defects related to the bench trial, and the Commission, cross-appealing, objects to the district court’s apportionment of 5 percent of the cleanup liability. For the reasons below, we affirm the judgment of the district court in its entirety.

BACKGROUND

In 1993, the Michigan Department of Environment, Great Lakes, and Energy identified hazardous substances in the soil at the Roosevelt Street Factory dating from the tenancy of Gould Electronics.1 Gould had used the factory to manufacture pistons and connecting rods between 1961 and 1976, while the factory’s neighbor, the Livingston County Road Commission, operated

1 Unless otherwise noted, the facts in this section are taken from the final opinion and order of the district court dated November 19, 2020.

a facility that since 1933 conducted vehicle repairs and asphalt tests and stored materials for salting roads. The initial contamination was detected on Gould’s property, but near the boundary between the parcels. Upon further investigation, the Department detected large quantities of the toxic chem- ical TCE, which is a carcinogen and was once a common degreasing agent. Gould was ordered to remove enough of the soil to remedy the contamination—but it was not enough. Shortly thereafter, the Department found TCE-contaminated groundwater in the aquifer straddling the factory and the storage facility.

The Department identified both Gould and the Commission as potential sources of the TCE and the site was officially designated a “facility” under CERCLA. Because CERCLA allows prop- erty owners to sue each other for the costs of environmental cleanup, both parties hired consultants to take measurements, prepare reports, and generally contest their liability. Gould then sued the Commission in 2009 to recover response costs,2 alleging that the Commission was at least partly responsible for the TCE contamination. See 42 U.S.C. § 9607(a)(4)(B). Just before trial, in 2012, the parties determined it would be more efficient to allow the Department to complete its assess- ment of liability first; to that end, they signed a tolling agreement that preserved the litigation but stayed it until the Department weighed in. Included in the agreement was a preambulatory clause expressing the parties’ desire “to conserve resources and avoid unnecessary litigation time and expense while simultaneously preserving their current respective rights, defenses and litigation positions.” Five years later—much longer than expected—the Department issued a letter conclud- ing that while none of the TCE released on the Commission’s property was “demonstrated to be directly attributable to [the Commission’s] historic operations,” it “cannot agree or disagree with”

2 Because the contaminated groundwater had been seeping toward nearby Thompson Lake, the Department ordered Gould to undertake a comprehensive environmental cleanup of the entire affected area across both parcels. Gould did this and, in accordance with CERCLA, now contests its liability with respect to cleanup costs after the fact.

the Commission’s theory that Gould was responsible. Gould then revived the litigation as con- templated in the tolling agreement.

This time around, both parties filed motions seeking to file new pleadings that would go beyond the scope of the first case, which the district court denied. The court insisted that in the second case the parties abide by the pleadings as they had been in the first case. Months later, after discovery, the Commission again sought leave to add a CERCLA contribution counterclaim. See 42 U.S.C. § 9613(f). Because the statutory scheme allows such counterclaims to be brought either “during or following” a civil CERCLA claim, ibid., and because of Federal Rule of Civil Procedure 15’s generous pleading standards, the court reversed course and granted the motion. The parties then prepared for trial.

At that point, in mid-2020, the COVID-19 pandemic had forced much of the justice system to slow or halt. Over the objections of the parties, the district court decided to go forward with the bench trial using videoconferencing services. The virtual trial took place over seven days, with each side offering experts and evidence. At its conclusion, the district court issued a 108-page opinion in which it (1) excluded certain evidence presented by Gould on the grounds that it was presented by an expert who was not a specialist in the field and who did not prepare the reports himself; (2) found Gould to be the “sole cause” of the TCE contamination, though only 95 percent liable for the Commission’s costs; and (3) held the Commission 5 percent liable for Gould’s costs because of the Commission’s dilatory tactics and refusal to cooperate with the Department. By then, Gould had spent more than $4.25 million responding to the contamination; the Commission had spent about $1.25 million. After subtracting the Commission’s 5 percent liability from 95 per- cent of its costs, the Commission was awarded $962,153.07. Gould now appeals, and the Commis- sion cross-appeals the reduction of its award.

ANALYSIS

Free access — add to your briefcase to read the full text and ask questions with AI

Gould Electronics Inc. v. Livingston Cnty. Road Comm'n, (6th Cir. 2022).

Gould Electronics Inc. v. Livingston Cnty. Road Comm'n (Gould Electronics Inc. v. Livingston Cnty. Road Comm'n) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Greene v. McElroy
360 U.S. 474 (Supreme Court, 1959)
Goldberg v. Kelly
397 U.S. 254 (Supreme Court, 1970)
Jackson v. Virginia
443 U.S. 307 (Supreme Court, 1979)
Anderson v. City of Bessemer City
470 U.S. 564 (Supreme Court, 1985)
Charles E. Stoner, Jr. v. Dewey Sowders, Warden
997 F.2d 209 (Sixth Circuit, 1993)
United States v. Leon Burke
345 F.3d 416 (Sixth Circuit, 2003)
United States v. Edwing Morales
687 F.3d 697 (Sixth Circuit, 2012)
Key Tronic Corp. v. United States
511 U.S. 809 (Supreme Court, 1994)
Scottsdale Insurance v. Flowers
513 F.3d 546 (Sixth Circuit, 2008)
Howard Holt v. City of Battle Creek
925 F.3d 905 (Sixth Circuit, 2019)