Gonzalez v. O & G Industries, Inc.

341 Conn. 644
Supreme Court of Connecticut·Decided December 30, 2021·No. SC20422·Published·Cited by 7 cases

Opinion

Page 138 CONNECTICUT LAW JOURNAL February 15, 2022

644 FEBRUARY, 2022 341 Conn. 644 Gonzalez v. O & G Industries, Inc.

ELVIRA R. GONZALEZ ET AL. v. O & G INDUSTRIES, INC., ET AL.

(SC 20422)

Robinson, C. J., and McDonald, D’Auria, Mullins and Kahn, Js.

Syllabus

The plaintiffs sought to recover damages for personal injuries sustained in an explosion that occurred at a natural gas fueled power plant as a result of the defendants’ alleged negligence. Prior to construction of the power plant, the defendant K Co., which received approval to build and operate the power plant, entered into an agreement with the defendant O Co., pursuant to which O Co. agreed to serve as the general contractor for the construction project. K Co. also entered into a contract for management and administrative services with the defendant P Co. Prior to completion of the construction project, and before the power generating equipment could be started, the natural gas fuel supply pipelines had to be cleared of construction debris. O Co. and its subcontractors chose to perform ‘‘gas blow’’ procedures over the course of two days in order to clear the debris. The procedure involves the flow of natural gas through the pipes at a higher pressure than during normal operation, whereby the force of the gas propels the debris through the pipes until it is ejected through a nozzle. On the second day of the gas blow procedures , two procedures were conducted with certain irregularities. Most significantly, and unlike with the prior gas blow procedures, the discharge nozzle was oriented horizontally, rather than vertically. Because of this, by the time the second gas blow procedure began, natural gas remained trapped and mixed with air in a partially enclosed area into which the nozzle discharged the gas. During the second gas blow procedure , the natural gas also flowed through the pipes at an unusually high pressure, and, as a result, heated debris ignited the accumulated natural gas and oxygen, causing the explosion. The plaintiffs, two injured individuals and one of their spouses, alleged that the defendants were strictly liable insofar as they engaged in an ultrahazardous activity that caused the plaintiffs’ injuries. The plaintiffs also alleged that their injuries were caused by the defendants’ negligence. The plaintiffs’ claims were resolved in O Co.’s favor, after which the plaintiffs sought relief only from K Co. and P Co. Following an evidentiary hearing, the trial court rendered judgment for K Co. and P Co. on the plaintiffs’ strict liability claims, reasoning that the plaintiffs had failed to satisfy their burden of establishing that the gas blow procedure was abnormally dangerous. Thereafter, K Co. and P Co. filed motions for summary judgment with respect to the plaintiffs’ negligence claims, which the trial court granted. In granting those motions, the trial court concluded, inter alia, that no

February 15, 2022 CONNECTICUT LAW JOURNAL Page 139

341 Conn. 644 FEBRUARY, 2022 645 Gonzalez v. O & G Industries, Inc.

reasonable jury could find that K Co. and P Co. exercised sufficient control over O Co.’s performance of the gas blow procedures, and, therefore, they were not vicariously liable for O Co.’s alleged negligence. The plaintiffs thereafter appealed from the trial court’s judgment in favor of K Co. and P Co. Held:

1. The plaintiffs could not prevail on their claim that the trial court incorrectly concluded that the gas blow procedure was not an abnormally dangerous activity in rendering judgment for K Co. and P Co. on the plaintiffs’ strict liability claims, as this court, relying on prior case law and the factors set forth in § 520 of the Restatement (Second) of Torts for determining whether an activity is abnormally dangerous, determined that the gas blow procedure at issue was not abnormally dangerous: even though the harm resulting from a gas blow procedure is likely to be severe, the inherent risk that any harm will occur from conducting the procedure is generally low, and the gas blow procedures in the present case were not a regular and ongoing part of the power plant’s operation but were conducted only during a specific phase of the construction process and in a relatively uninhabited area; moreover, although the gas blow procedure, which entails the flow of natural gas at higher than normal pressure in large quantities, is not a procedure that is used commonly and added little value to the construction of the power plant given the availability of alternative methods to clear the fuel supply pipelines, the risk and severity of potential harm from the procedure would have been materially reduced if the procedures had been performed utilizing certain precautions that are widely known and generally employed in the construction of natural gas fueled power plants, namely, proper orientation and positioning of the discharge nozzle and careful control of the pressure and volume of gas; furthermore, the plaintiffs’ reliance on the dangerous nature of natural gas, by itself, was unavailing, as the dangerous nature of an instrumentality must be considered alongside the circumstances and conditions of its use.

2. The plaintiffs could not prevail on their claim that the trial court had improperly granted K Co.’s and P Co.’s motions for summary judgment with respect to the plaintiffs’ negligence claims, as that court correctly concluded that K Co. and P Co. did not exercise sufficient control over the performance of O Co. or its subcontractors in conducting the gas blow procedures so as to overcome the general rule that an employer is not vicariously liable for the torts of its independent contractor: a. K Co. and P Co. did not exercise sufficient contractual control over the gas blow procedures to establish the existence of a legal duty, as O Co. had exclusive contractual control over the construction of the power plant and the performance of the gas blow procedures: the agreement between K Co. and O Co. specified that the construction of the power plant was a ‘‘turnkey’’ project, the term ‘‘turnkey’’ was a well-defined type of contract in the construction industry that indicated the parties’ intention that O Co. would have full contractual control over the construc-

Page 140 CONNECTICUT LAW JOURNAL February 15, 2022

646 FEBRUARY, 2022 341 Conn. 644 Gonzalez v. O & G Industries, Inc.

Free access — add to your briefcase to read the full text and ask questions with AI

Gonzalez v. O & G Industries, Inc., 341 Conn. 644 (Colo. 2021).

341 Conn. 644 (Gonzalez v. O & G Industries, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Deer v. National General Ins. Co.
353 Conn. 262 (Supreme Court of Connecticut, 2025)
Rivera v. Convoy, Inc.
D. Connecticut, 2025
Deer v. National General Ins. Co.
Connecticut Appellate Court, 2024
Tran v. Woodworth
Connecticut Appellate Court, 2024
Aviles v. Barnhill
217 Conn. App. 435 (Connecticut Appellate Court, 2023)
In re A'vion A.
Connecticut Appellate Court, 2023
Miller v. Doe
214 Conn. App. 35 (Connecticut Appellate Court, 2022)