Gonzalez, J. v. Sam Midtown Group

Superior Court of Pennsylvania·Decided January 12, 2016·No. 103 EDA 2015·Unpublished

Opinion

NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37

JOSE GONZALEZ I/T/A PHILADELPHIA 4 IN THE SUPERIOR COURT OF CONSTRUCTION AND PHILADELPHIA 4 PENNSYLVANIA CONSTRUCTION

v.

SAM’S MIDTOWN GROUP, INC.

Appellant No. 103 EDA 2015

Appeal from the Judgment Entered November 19, 2014 In the Court of Common Pleas of Philadelphia County Civil Division at No(s): March Term, 2011, No. 1703

BEFORE: GANTMAN, P.J., PANELLA, J., and SHOGAN, J. MEMORANDUM BY PANELLA, J. FILED JANUARY 12, 2016 Appellant, Sam’s Midtown Group, Inc. (“the Company”), appeals from the judgment after a jury verdict found it liable to Appellees, Jose Gonzalez and Philadelphia 4 Construction (“Contractor”),1 on their claims for breach of contract. The Company argues that Contractor was not entitled to relief as it substantially breached the construction agreement prior to the Company’s breach, that the trial court erred in not sanctioning Contractor for discovery

1 At the time of the contract, Appellee Gonzalez traded under the unregistered fictitious name of Philadelphia 4 Construction. After filing the Complaint that initiated this matter, Gonzalez registered the fictitious name. There is no indication in the record that Philadelphia 4 Construction is a limited liability business organization.

violations, and that the evidence at trial did not support the amount of damages awarded by the jury. After careful review, we affirm.

The factual predicate of this litigation is largely undisputed. The Company, desiring to renovate a Philadelphia property in order to operate a restaurant there, hired a project manager to oversee the renovations. The project manager recommended the carpentry services of Contractor, and the Company entered into a written agreement with Contractor. Under the written agreement, Contractor was to submit invoices to the project manager for approval and payment. The written agreement required a detailed breakdown of material and subcontractor costs incurred by the Contractor. Furthermore, Contractor was required to obtain a two million dollar comprehensive insurance policy that covered, inter alia, property damages due to collapse.

Contractor did not strictly comply with the requirements for detailed breakdowns of costs with all of his invoices. Nor did Contractor have a two million dollar comprehensive insurance policy at the time he started working on the project.

Contractor proceeded to perform the renovations listed in the written agreement to the property beginning in August 2008. Shortly thereafter, a structural wall at the site collapsed, causing the collapse of floors and other walls. The damage was repaired, and construction continued. Contractor’s

invoices were submitted to the project manager and were paid through February 2009.

Starting in March 2009, difficulties arose with the project. The project manager quit and left the site, claiming that it had not been paid. The parties agree that Contractor completed the tasks listed in the original, written agreement. However, at this point the parties disagree about what happened.

Contractor presented evidence that he reached an oral agreement with the Company to finish the renovations after the project manager walked off the site. The Company presented evidence that it repeatedly asked Contractor to fix instances of poor workmanship on tasks that it had already completed. Contractor claims that it walked off the site after the Company failed to abide the oral agreement and pay him for finishing the job. The Company claims that Contractor would not address its requests to fix the problems with the Contractor’s previous work and instead just walked away from the job.

Several years later, Contractor instituted this litigation by filing a complaint against the Company for breach of contract, violation of the Contractor and Subcontractor Payment Act2, and unjust enrichment. After lengthy discovery, a jury trial was held resulting in a verdict that the

2 73 P.S. §§ 501-516.

Company had breached its contract with Contractor and was liable for $175,000 in damages. The Company filed post-trial motions, which the trial court denied, and this timely appeal followed.

On appeal, the Company raises three broad issues, which include related sub-issues. In its first issue, the Company argues that the trial court erred in its handling of the Company’s defense premised upon its allegation that Contractor materially breached the agreement first. In its first sub- argument, the Company contends that it was entitled to judgment in spite of the verdict (“JNOV”). We review a decision denying JNOV by the following standard.

A JNOV can be entered upon two bases: (1) where the movant is entitled to judgment as a matter of law; and/or, (2) the evidence was such that no two reasonable minds could disagree that the verdict should have been rendered for the movant. When reviewing a trial court’s denial of a motion for JNOV, we must consider all of the evidence admitted to decide if there was sufficient competent evidence to sustain the verdict. In so doing, we must also view this evidence in the light most favorable to the verdict winner, giving the victorious party the benefit of every reasonable inference arising from the evidence and rejecting all unfavorable testimony and inference. Concerning any questions of law, our scope of review is plenary. Concerning questions of credibility and weight accorded the evidence at trial, we will not substitute our judgment for that of the finder of fact.

If any basis exists upon which the jury could have properly made its award, then we must affirm the trial court's denial of the motion for JNOV. A JNOV should be entered only in a clear case.

Griffin v. Univ. of Pittsburgh Med. Center-Braddock Hosp., 950 A.2d 996, 999 (Pa. Super. 2008) (citation omitted).

Here, the Company contends that it is undisputed that Contractor failed to adhere by the terms of the contract from the very beginning, including poor workmanship, a failure to obtain sufficient insurance, and a failure to properly document costs on his invoices. Generally, a party who has materially breached a contract may not “complain if the other party refuses to perform his obligations under the contract.” Ott v. Buehler Lumber Co., 541 A.2d 1143, 1145 (Pa. Super. 1988) (citation omitted). “[A] material breach of a contract, which is vital to the existence of the contract, relieves the non-breaching party from any continuing duty of performance under the contract.” Umbelina v. Adams, 34 A.3d 151, 159 (Pa. Super. 2011) (citation omitted) (emphasis in original). Thus, the Company argues, it was entitled to judgment as a matter of law.

In contrast, Contractor provided evidence that the initial, written agreement was completed, and that he was fully paid for his work pursuant to the written agreement. See N.T., Trial, 5/5/14, 134-138. Contractor testified that his claims in this matter arose from separate, oral agreements he made with the Company. See id., at 138-142. No evidence was presented to the jury that these oral agreements contained similar conditions as the written agreement. Viewing this evidence in a light most favorable to Contractor, as the verdict winner, we cannot conclude that the Company had established a prior breach of the oral agreement as a matter

of law. Thus, we conclude that the Company is due no relief on this claim on appeal.

In a related sub-issue, the Company argues that the trial court erred in failing to instruct the jury on the law regarding its defense of prior breach. In particular, the Company submitted the following proposed jury instruction prior to trial.

In order for [Contractor] to recover on his breach of contract cause of action, [Contractor] also must not have breached the agreement.

Free access — add to your briefcase to read the full text and ask questions with AI

Gonzalez, J. v. Sam Midtown Group, (Pa. Ct. App. 2016).

Gonzalez, J. v. Sam Midtown Group (Gonzalez, J. v. Sam Midtown Group) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Rohm and Haas Co. v. Lin
992 A.2d 132 (Superior Court of Pennsylvania, 2010)
Eichman v. McKeon
824 A.2d 305 (Superior Court of Pennsylvania, 2003)
Ott v. Buehler Lumber Co.
541 A.2d 1143 (Supreme Court of Pennsylvania, 1988)
George Stash & Sons v. New Holland Credit Co.
905 A.2d 541 (Superior Court of Pennsylvania, 2006)
Schweikert v. St. Luke's Hospital
886 A.2d 265 (Superior Court of Pennsylvania, 2005)
Griffin v. University of Pittsburgh Medical Center-Braddock Hospital
950 A.2d 996 (Superior Court of Pennsylvania, 2008)
James v. Ferguson
162 A.2d 690 (Supreme Court of Pennsylvania, 1960)
Banking v. Gesiorski
904 A.2d 939 (Superior Court of Pennsylvania, 2006)
Umbelina v. Adams
34 A.3d 151 (Superior Court of Pennsylvania, 2011)