Goldblatt v. Ferrigno

16 Conn. Super. Ct. 506, 16 Conn. Supp. 506, 1950 Conn. Super. LEXIS 36
CourtConnecticut Superior Court
DecidedMay 22, 1950
DocketFile 82891
StatusPublished
Cited by2 cases

This text of 16 Conn. Super. Ct. 506 (Goldblatt v. Ferrigno) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Goldblatt v. Ferrigno, 16 Conn. Super. Ct. 506, 16 Conn. Supp. 506, 1950 Conn. Super. LEXIS 36 (Colo. Ct. App. 1950).

Opinion

ALCORN, J.

The plaintiffs seek damages for breach of com tract to build a concrete foundation and the defendant: counter' claims for damages for loss of profits because he was .prevented from completing the contract.

The established facts are as follows: The plaintiff Anna Gold' blatt owned a two'family frame house and lot, which she had purchased in May, 1947, for $10,700. She and her husband, the plaintiff George Goldblatt, conceived the idea of raising and moving the house to the rear of the lot and building a one'Story structure under and in front of it to be used for stores. Plans were secured from an architect and a general contract for the work was entered into by George Goldblatt, who is hereinafter referred to as the plaintiff because throughout the events recited he acted as, and was dealt with as, the owner and sole interested party.

The original contractor raised and moved the house to the rear of the lot ready to receive the new construction and dug a foum dation hole. A dispute arose over his contract price as a result of which his contract was terminated by mutual consent about No' vember, 1947. The cellar hole thereafter stood neglected, col' lecting water, until March, 1948, when the plaintiff decided to resume the building program by letting contracts for the several parts of the work.

*508 The plaintiff was a furniture salesman with no building ex' perience so he engaged one Pandolph to supervise the work. Pandolph was a painter and decorator with no demonstrated building experience, but he undertook to be the plaintiff’s “right hand” to see that the work was properly done. During the events in issue here he was constantly, but ineffectually, on the job.

He suggested the defendant as a competent foundation con' tractor, and on March 23, 1948, the plaintiff entered into a written contract with the defendant to install a concrete founda' tion for $4275. The contract price was payable $2000 when the foundation was installed and the forms removed, $1300 when the exterior walls were waterproofed, and $975 when the floor was completed.

In the meantime, the city building department had been pro' testing to plaintiff’s wife about the hazard to the abutting side' walk and property from earth slides in the excavation. Con' sequently, the plaintiff urged speed in having the foundation in' stalled. The defendant began the work a few days after the con' tract was signed, worked overtime hours, and built the walls in sections to meet the more critical elements of the situation in the order of their importance.

The plaintiff had employed a surveyor to fix the lines of the walls and the defendant asked Pandolph for the points for these lines preparatory to building his forms. Pandolph talked with the surveyor over the phone relative to the north line of the building, relayed this information to the defendant, and pointed out to him the points for fixing the other lines. The defendant built his forms on these lines and poured the con' crete for footings and walls. Neither he nor the plaintiff took the precaution to have the surveyor approve the lines before the forms and walls were in place.

The forms were removed from the walls on April 18, 1948, and a crack was noticed in the northerly portion of the east wall. The walls appeared otherwise proper and satisfactory, and on April 19, 1948, the defendant received the $2000 initial payment on the contract. About a week later, however, the city building department notified the parties that inspection showed the north wall-to be 1.26 feet over the building line at its east end, and the south wall to be off center on its footing one foot, two and a half inches at its west end and six and a half inches at its east end. Because of these conditions instructions were issued that the walls could not be built on.

*509 Conferences followed, participated in by representatives of the city, the architect, the plaintiff, and the defendant, resulting in a plan to remedy the conditions so that the foundation could be used for a building. This plan called for cutting the north wall down below the grade level where it encroached over the building line and constructing piers at certain points on the north and south walls to carry the load of the building on its eccentric line. The defendant thereupon began operations to make these corrections.

At the same time, the city authorities were concerned, because of the extremely poor soil conditions, over the danger to abut' ting property from lack of support. They notified both the plaintiff and the defendant that the walls should be backfilled to half their height immediately to safeguard this condition. No greater depth of backfill was recommended until a building had been placed on the walls because the walls, standing unaided, would not sustain the earth pressure if backfilled to grade. Both parties knew this.

The defendant’s contract did not require him to do the back' filling. The plaintiff requested him to do it, however, and, after some negotiation, the plaintiff and defendant entered into a separate oral contract by which the defendant undertook to do the backfill for $150. Thereupon he proceeded to backfill the east and west walls to grade. The plaintiff, in his anxiety to get the work done, did some backfilling personally on the north wall.

Because of the pressure from the excessive backfilling, the east and west walls were found, on May 17, 1948, to have bulg' ed and cracked. As a consequence, the city authorities con' demned the foundation and forbade its use for any structure to be built.

The defendant, in the meantime, had waterproofed most of the exterior of the walls in accordance with his contract. He had not constructed the base of a chimney or a cellar stair be' cause Pandolph instructed him to omit them. The city’s con' demnation of the work came before column footings and cellar floor, as called for by the contract, were begun.

Following the condemnation by the city authorities, the plain' tiff paid $800 to have the foundation completely filled in and another $450 to have the house lowered in place for use. The south wall of the foundation built by the defendant has been *510 utilized as the front foundation wall of the house and the remainder of the foundation lies buried as a memorial to a badly-executed piece of work for which the parties must share the responsibility.

■ The fact that the contract sued upon was made by the husband, and that all significant acts in issue were his, while the land belonged to his wife, occasions no difficulty. If the established facts made out a breach of contract by the defendant, the plaintiff would be entitled to recover the damages that would arise naturally and generally from that breach, or such as might reasonably be supposed to have been in the contemplation of both parties at the time they made the contract. Cohn v. Norton, 57 Conn. 480, 490. The measure would be such compensation as would leave the plaintiff as well off as he would have been had the contract been fully performed. Raff Co. v. Mur phy, 110 Conn. 234, 242; Lee v. Harris, 85 Conn. 212, 214.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kushwara v. Kaleta
268 A.2d 688 (Connecticut Appellate Court, 1969)
Duffy v. Woodcrest Builders, Inc.
196 A.2d 606 (Connecticut Appellate Court, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
16 Conn. Super. Ct. 506, 16 Conn. Supp. 506, 1950 Conn. Super. LEXIS 36, Counsel Stack Legal Research, https://law.counselstack.com/opinion/goldblatt-v-ferrigno-connsuperct-1950.