Goebel v. Minster

2020 Ohio 5467
CourtOhio Court of Appeals
DecidedNovember 30, 2020
Docket2-20-14
StatusPublished
Cited by3 cases

This text of 2020 Ohio 5467 (Goebel v. Minster) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Goebel v. Minster, 2020 Ohio 5467 (Ohio Ct. App. 2020).

Opinion

[Cite as Goebel v. Minster, 2020-Ohio-5467.]

IN THE COURT OF APPEALS OF OHIO THIRD APPELLATE DISTRICT AUGLAIZE COUNTY

EDWARD GOEBEL, ET AL.,

PLAINTIFFS-APPELLEES, CASE NO. 2-20-14

v.

VILLAGE OF MINSTER,

DEFENDANT-APPELLANT, -and- OPINION

HELMS & SONS EXCAVATING, INC.

DEFENDANT-APPELLEE.

Appeal from Auglaize County Common Pleas Court Trial Court No. 2020 CV 0052

Judgment Affirmed

Date of Decision: November 30, 2020

APPEARANCES:

Jane M. Lynch and Jared A. Wagner for Appellant

Sean R. Alto and Jeffrey T. Kenney for Appellee Case No. 2-20-14

SHAW, P.J.

{¶1} Defendant-appellant, Village of Minster (“Minster”), brings this appeal

from the June 3, 2020 judgment of the Auglaize County Common Pleas Court

denying, in part, its Civ.R. 12(B)(6) motion to dismiss the complaint of Edward and

Lisa Goebel, et al (collectively, “appellees”). On appeal, Minster argues that it was

entitled to sovereign immunity and that the trial court erred by finding that the

appellees had pled facts sufficient that, if believed, would defeat a claim of

sovereign immunity.

Background

{¶2} In early 2019, Minster began soliciting bids from area contractors for a

project known as “Northeast Sanitary Sewer/Second Street Sewer Project.”1 (Doc.

No. 1). “The project was essentially the reconstruction of Second Street and the

sewer systems in that area.” (Id.) Helms & Sons Excavating, Inc. (“Helms”)

submitted the lowest bid, and the bids were discussed at a Minster Council meeting

on April 2, 2019. At that meeting, the Minster Council expressed concerns about

Helms “and the ability to do the work called for in the project based upon negative

feedback from other municipalities.” (Id.) Nevertheless, Minster entered into a

contract with Helms for the reconstruction of Second Street. Minster also hired

1 As this appeal is the review of the denial of a Civ.R. 12(B)(6) motion to dismiss, we cite the factual allegations contained in the complaint because, for the purposes of this appeal only, we must accept them as true.

-2- Case No. 2-20-14

“CTL Engineering” to oversee the progress of the project and the quality of work

performed by Helms.

{¶3} Pursuant to the contract, the work to be performed by Helms “included

the installation of storm sewer modifications, water main, sanitary sewer, service

laterals, sidewalks, curb and gutter, and installation of a sanitary sewer down a

portion of Garfield and Second Streets.” (Id.) Helms began its work on or about

April 22, 2019. During the initial construction phase, Helms discovered what was

described as an abandoned sewer line on Second Street and Helms reported the

discovery to Minster. Thereafter, Minster specifically instructed Helms to remove

the abandoned sewer line.

{¶4} During the removal—or “destruction” as appellees alleged—of the

sewer system, Helms created a “trench box” on Second Street to stop water from

the canal from interfering with work. Appellees alleged that Helms negligently

constructed the trench box.

{¶5} On May 17, 2019, it rained, causing water in the canal to rise. “The

rising water and sediment in the canal entered the pipe that was blocked by the

trench box.” (Id.) According to the complaint,

This negligent construction caused water to flood the trench box and the lift station, which in turn caused the lift station pumps to stop working. Once the pumps at the lift station stopped working, sewage from the lift station flooded into the [appellees’] homes causing substantial damage to the [appellees’] real and personal

-3- Case No. 2-20-14

property, as well as the loss of use of their homes for a substantial period of time.

(Id.)

{¶6} Appellees are a group of individual landowners in Minster who were

impacted by the sewage. On April 15, 2020, appellees filed a complaint against

Minster and Helms alleging negligence in the destruction of a sewer system

pursuant to R.C. 2744.01(G)(2)(d), and breach of contract to a third-party

beneficiary. The appellees sought damages in an amount in excess of $25,000.

{¶7} Helms filed an answer on May 1, 2020, denying negligence, and

asserting that appellees were not third-party beneficiaries and had no privity of

contract in this matter. Further, Helms’ answer stated that Helms

located a server line, which was not on the plans and, pursuant to the Contract, properly reported it to [Minster] and otherwise accepted instructions from [Minster] and Choice One Engineering. Such instructions included an instruction to remove said server line because it was dead and abandoned and no longer in use, which turned out to be incorrect.

(Doc. No. 12).2

{¶8} On May 8, 2020, Minster filed a Civ.R. 12(B)(6) motion to dismiss the

complaint filed by appellees arguing that the factual allegations from the complaint

demonstrated that the alleged negligence that caused damages occurred within the

context of a construction project involving the repair and maintenance of a roadway

2 As this is outside of the complaint, we do not rely on it for anything in this appeal; rather, we use it to provide context to the action.

-4- Case No. 2-20-14

and sewer system, both of which were governmental rather than proprietary

functions. Thus Minster claimed that it was entitled to sovereign immunity pursuant

to R.C. 2744.02, which precluded recovery from Minster in this matter. Further,

Minster argued that even if there was an exception to immunity that existed in this

case, Minster claimed that under R.C. 2744.03(A)(5), immunity should be reinstated

because there were no allegations that the “trench box” was constructed or installed

with malice, bad faith, wantonness, or recklessly. (Doc. No. 14). Finally, Minster

argued that appellees had no grounds to attempt to enforce the contract between

Minster and Helms in the breach of contract claim.

{¶9} On May 26, 2020, appellees filed a memorandum contra to Minster’s

motion to dismiss arguing that pursuant to their allegations and supporting Ohio

case authority, Minster was engaged in a proprietary function for which an

exception to immunity applied, namely the destruction of a sewer system “which is

explicitly identified as a proprietary function under R.C. § 2744.02(G)(2)(d).” [sic]

(Doc. No. 20). Appellees also asserted that Minster was not entitled to reinstatement

of immunity pursuant to R.C. 2744.03(A)(5) merely by “baldly” claiming that the

actions in this matter did not amount to, at least, recklessness. Finally, appellees

argued that they had adequately stated a claim for breach of contract as a third-party

beneficiary based on the plain language of the contract at issue.

-5- Case No. 2-20-14

{¶10} On June 2, 2020, Minster filed a reply memorandum reiterating

previous points and arguing, inter alia, that the “removal” of a “single abandoned

sewer line during the course of [the] project involving the reconstruction of a public

street and the adjacent sewer system” did not transform a governmental function

into a proprietary function. (Doc. No. 24).

{¶11} On June 3, 2020, the trial court filed an entry denying Minster’s

motion to dismiss with regard to the negligence claim, but granting Minster’s

motion to dismiss with regard to the breach of contract claim. The trial court

reasoned as follows.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Goebel v. Minster
2022 Ohio 883 (Ohio Court of Appeals, 2022)

Cite This Page — Counsel Stack

Bluebook (online)
2020 Ohio 5467, Counsel Stack Legal Research, https://law.counselstack.com/opinion/goebel-v-minster-ohioctapp-2020.