Global Heavy Corp. v. Univ. Area Joint Authority

CourtCommonwealth Court of Pennsylvania
DecidedJune 2, 2025
Docket1165 C.D. 2024
StatusUnpublished

This text of Global Heavy Corp. v. Univ. Area Joint Authority (Global Heavy Corp. v. Univ. Area Joint Authority) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Global Heavy Corp. v. Univ. Area Joint Authority, (Pa. Ct. App. 2025).

Opinion

IN THE COMMONWEALTH COURT OF PENNSYLVANIA

Global Heavy Corp., : Appellant : : v. : : No. 1165 C.D. 2024 University Area Joint Authority : Argued: May 6, 2025

BEFORE: HONORABLE RENÉE COHN JUBELIRER, President Judge HONORABLE PATRICIA A. McCULLOUGH, Judge HONORABLE ANNE E. COVEY, Judge

OPINION NOT REPORTED

MEMORANDUM OPINION BY JUDGE COVEY FILED: June 2, 2025

Global Heavy Corp. (Appellant) appeals from the Centre County Common Pleas Court’s (trial court) August 27, 2024 order entering judgment in favor of the University Area Joint Authority (Authority)1 and against Appellant. Essentially, Appellant presents one issue for this Court’s review: whether the trial court erred by entering a compulsory nonsuit.2 After review, this Court affirms.

1 The Authority is a wastewater authority. 2 In its Statement of the Questions Involved, Appellant presents five issues for this Court’s review: whether the trial court erred by entering a compulsory nonsuit: (1) by finding that Appellant did not meet its burden of proving a breach of contract; (2) by finding that Appellant’s failure to appeal from the engineer’s change order denials to the Authority waived the appeal procedures in Article 12 of the Standard General Conditions of the Construction Contract; (3) where the Authority did not establish the enforceability of the contract’s liquidated damages provision; (4) where there was no evidence presented concerning the amount of liquidated damages that the Authority was permitted to assess against Appellant; and (5) when it refused to permit Appellant to introduce expert testimony to quantify the amount of its delay damages. See Appellant Br. at 2-4. Because this Court’s statement of the issue is dispositive, this Court will address it accordingly. Appellant and the Authority entered into a contract (Contract) for the construction of a Biological Odor Control System (System) in September 2018.3 See Reproduced Record (R.R.) Vol. III at 1110a-1116a. The Contract stated that Appellant shall substantially complete the System on or before July 21, 2019, see R.R. Vol. III at 1110a (“The [w]ork will be substantially completed within 320 days after the date when the Contract [t]imes commence to run.”), and fully complete the System 45 days thereafter, see id. (The work will be “completed and ready for final payment . . . within 365 days after the date when the Contract [t]imes commence to run.”). The Contract further provided that if Appellant did not substantially complete the System by that date, the Authority would be entitled to liquidated damages in a preset amount. See R.R. Vol. III at 1111a (“Contractor shall pay Owner $1,300.00 for each day that expires after the time . . . for [s]ubstantial [c]ompletion until the [w]ork is substantially complete[,]” and “Contractor shall pay Owner $135.00 for each day that expires after such time until the [w]ork is completed[.]”). The Standard General Conditions of the Construction Contract (General Conditions) contain the procedure for changing the Contract times or price.4 See R.R. Vol. III at 1198a-1199a. Appellant failed to substantially complete the System by July 21, 2019, and did not fully avail itself of the General Conditions’ procedures to change the substantial completion date. Appellant initiated a start-up of the System in February 2020. Appellant did not substantially complete the final start-up until June 24, 2020. When Appellant substantially completed the System and sought payment of the Contract balance of $468,413.46, the Authority did not pay Appellant because Appellant did not substantially complete the System by July 21, 2019, and, thus,

3 Appellant presented the Contract at trial, and the trial court accepted it into evidence. See Reproduced Record Vol. II at 576a (Ex. P-12). 4 Appellant presented the General Conditions at trial, and the trial court accepted it into evidence. See R.R. Vol. II at 717a (Ex. D-99). 2 owed the Authority liquidated damages. Appellant never fully completed the System. On September 9, 2020, Appellant filed a Complaint against the Authority and Herbert, Rowland & Grubic, Inc. (HRG) for breach of contract.5 The trial court held a jury trial that began on January 22, 2024. The trial was not held on January 23, 2024, due to an ice storm, and the trial resumed on January 24, 2024. At the conclusion of Appellant’s case-in-chief, the Authority moved for a compulsory nonsuit (Motion for Nonsuit), which the trial court granted. On February 1, 2024, Appellant filed post-trial motions, which the trial court denied on August 20, 2024. The trial court entered judgment in favor of the Authority and against Appellant on August 27, 2024. Appellant appealed to this Court.6 On September 18, 2024, the trial court directed Appellant to file a Concise Statement of Errors Complained of on Appeal pursuant to Pennsylvania Rule of Appellate Procedure (Rule) 1925(b) (Rule 1925(b) Statement). On October 4, 2024, Appellant filed its Rule 1925(b) Statement. On October 15, 2024, the trial court filed its opinion pursuant to Rule 1925(a) (Rule 1925(a) Opinion).

5 HRG is the Authority’s consulting engineer firm. On August 3, 2022, the trial court entered an order granting the parties’ stipulation to dismiss HRG from the case with prejudice. 6 In reviewing the entry of a nonsuit, [an appellate court’s] standard of review is well[ ]established: we reverse only if, after giving appellant the benefit of all reasonable inferences of fact, we find that the fact[-]finder could not reasonably conclude that the essential elements of the cause of action were established. Indeed, when a nonsuit is entered, the lack of evidence to sustain the action must be so clear that it admits no room for fair and reasonable disagreement. The fact-finder, however, cannot be permitted to reach a decision on the basis of speculation or conjecture. Munoz v. Children’s Hosp. of Phila., 265 A.3d 801, 805-06 (Pa. Super. 2021) (quoting Rolon v. Davies, 232 A.3d 773, 776-77 (Pa. Super. 2020)).

3 This Court has explained:

Entry of a non[]suit is proper only if the fact-finder, viewing all the evidence in favor of the burdened party, could not reasonably conclude the essential elements of the cause of action were established. A compulsory non[]suit can only be granted in cases where it is clear a cause of action was not established. The trial court must give the non-moving party the benefit of all favorable evidence along with all reasonable factual inferences arising from that evidence, resolving any conflict in the evidence in favor of the non[]moving party. A compulsory non[]suit is valid only in a clear case where the facts and circumstances lead to only one conclusion - the absence of liability.

Daddona v. Thind, 891 A.2d 786, 816 (Pa. Cmwlth. 2006) (citations omitted). Appellant argues that the trial court erred by entering a compulsory nonsuit based on the finding that Appellant did not meet its burden of proving a breach of contract. Specifically, Appellant contends that the primary basis for the Authority’s Motion for Nonsuit was that Appellant failed to follow the Contract’s General Conditions; however, whether Appellant failed to follow the General Conditions is absolutely not relevant to whether Appellant met its burden of proving its breach of contract claim. Appellant asserts that it had a contract, it completed its contractual obligations, and the Authority did not pay Appellant its entire Contract balance. The Authority rejoins that the Contract did not simply state - construct the System and the Authority will pay you; the Contract stated - construct the System and achieve substantial completion within 320 days - and if you fail to achieve substantial completion within 320 days, then the Authority shall deduct $1,300.00 per day from the Contract price.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Daddona v. Thind
891 A.2d 786 (Commonwealth Court of Pennsylvania, 2006)
Munoz, F. v. The Children's Hospital
2021 Pa. Super. 217 (Superior Court of Pennsylvania, 2021)
Rolon, F. v. Davies, T.
2020 Pa. Super. 106 (Superior Court of Pennsylvania, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
Global Heavy Corp. v. Univ. Area Joint Authority, Counsel Stack Legal Research, https://law.counselstack.com/opinion/global-heavy-corp-v-univ-area-joint-authority-pacommwct-2025.