Glenn v. United States Steel Corp., Inc.

423 So. 2d 152, 1982 Ala. LEXIS 3509
CourtSupreme Court of Alabama
DecidedNovember 19, 1982
Docket80-505
StatusPublished
Cited by20 cases

This text of 423 So. 2d 152 (Glenn v. United States Steel Corp., Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Glenn v. United States Steel Corp., Inc., 423 So. 2d 152, 1982 Ala. LEXIS 3509 (Ala. 1982).

Opinion

423 So.2d 152 (1982)

Patti M. GLENN, etc.
v.
UNITED STATES STEEL CORPORATION, INC., et al.

80-505.

Supreme Court of Alabama.

November 19, 1982.

Francis H. Hare, Jr., Terrell Wynn, Alex Newton, and James J. Thompson, Jr., of Hare, Wynn, Newell & Newton, for appellant.

Bibb Allen of London, Yancey, Clark & Allen, Birmingham, and Reggie Copeland, Jr., of Nettles, Barker & Janecky, Mobile, Robert G. Tate and J. Ross Forman, III of Thomas, Taliaferro, Forman, Burr & Murray, Birmingham, for appellee U.S. Steel Corp.

EMBRY, Justice.

The dependent widow of Charlie Glenn, deceased, brought this wrongful death action against United States Steel Corporation and Bucyrus-Erie Company, pursuant to § 25-5-11, Code 1975. Mrs. Glenn appeals from a judgment rendered on a jury verdict in favor of U.S. Steel and Bucyrus-Erie. We affirm.

The facts of the case are as follows: U.S. Steel contracted with J.M. Foster, Inc., to construct an addition to a building at U.S. Steel's Fairfield Works. The contract involved, among other things, the installation of two 42-inch pipelines. Under the terms of this contract, Foster was treated as an independent contractor. U.S. Steel furnished all pipes and valves needed for this project, while Foster furnished the rest of the equipment, materials and labor required for such installation. All materials, including those furnished by U.S. Steel, were placed under Foster's control for storage *153 and installation. U.S. Steel neither directed the manner in which Foster was to perform the work called for by the contract, nor did it provide any supervision on this project. The following provision was included in the contract:

"Contractor shall take all reasonable measures and precautions at all times to prevent injuries to or the death of any of his employees or any other person who enters upon Owner's premises. Such measures and precautions shall include, but shall not be limited to, all safeguards and warnings necessary to protect workmen and others against any conditions on Owner's premises which could be dangerous and to prevent accidents of any kind whenever work is being performed in proximity to any moving or operating machinery, equipment or facilities, whether such machinery, equipment or facilities are the property of or are being operated by, the Contractor, his subcontractors, the Owner or other persons."

Foster had been performing construction work at the Fairfield Works on a continuing basis for approximately 15 years and the supervisors working for Foster knew of the hazards presented by high voltage wires on the property.

Part of the material needed to install the pipelines inside the building were supports for 42-inch pipe. Foster furnished the pipe supports, which were delivered to the job site by the fabricator. U.S. Steel designated certain areas on the premises for storage of Foster's materials and equipment, including an area next to an interior on-premises road known as the scrap haul road. It was along the scrap haul road that Foster's employees unloaded the pipe supports and stored them for future use, because this area was near the building where the pipe supports were to be installed.

Six 44,000-volt electric wires crossed the scrap haul road near where the pipe supports were stored. Warning signs were placed on either side of where the wires crossed over the roadway advising of the danger and the voltage of the lines. Testimony at trial established that the wires were clearly visible at a distance from either end of scrap haul road and were an open and obvious danger to all involved.

On 11 August 1977, Charlie Glenn, employed by Foster as a crane oiler, and crane operator Mike Washburn, also an employee of Foster, were instructed by John Gower, Foster's construction superintendent, to move a 50-ton Bucyrus-Erie crane to assist in the loading of pipe supports onto a flatbed truck on the scrap haul road. Glenn drove the crane while Washburn operated the boom from the cab while facing the rear of the vehicle. While the crane was being moved, Gower stopped the crane to remind Glenn and Washburn where the pipe supports were located. Before he left, Gower reminded Glenn and Washburn to "watch out for them wires."

On the day of the accident, Marvin Blalock, the equipment foreman of Foster, also warned Glenn and Washburn about the overhead wires on scrap haul road. Blalock testified that he told them that as far as he was concerned, "those wires are all hot and don't get any closer than 17 feet of those wires."

When the cranes reached the area where the pipe supports were located, the pipefitters, who were Foster employees, directed Glenn to position the crane in an area near the overhead wires. Once the crane was in position, Glenn got out of the crane, and Washburn proceeded to lift the boom of the crane into position. Since Washburn faced the rear of the crane while it was being moved, he never saw the overhead wires. When asked during trial as to whether he knew the overhead wires were in the vicinity, Washburn testified, "Well, I knew that, I guess, subconsciously, I knew that they were in the general area because we had passed under them before, but, you know, you don't have time to pay attention or I didn't pay attention to it before...." At no time did Washburn get out of the cab of the crane and survey the area where the pipe supports were located.

Glenn got off the crane when it stopped and Washburn began to boom the crane up and swing it over to the pipe supports. *154 While doing so, Washburn inadvertently caused the crane to come into contact with the overhead wires, electrocuting Glenn, who had grabbed hold of the handrail of the crane while he was still on the ground.

In her original complaint, plaintiff, Glenn's widow, charged U.S. Steel with negligence and wantonness in: failing to warn Glenn of the presence of the high voltage electrical wires; failing to de-energize the wires; and designating areas for storage of materials and supplies in dangerous proximity to those wires. The complaint was subsequently amended to include Bucyrus-Erie as a party defendant. Plaintiff alleged that Bucyrus-Erie was negligent in the manufacture and sale of a defective crane.

The case was tried before a jury and a verdict returned in favor of U.S. Steel and Bucyrus-Erie; judgment was entered accordingly. Plaintiff's motion for a new trial was denied.

Mrs. Glenn concedes that no error was committed in the trial court's charge to the jury regarding the liability of Bucyrus-Erie and it is not an appellee here. It is a well settled rule that this court has the authority to reverse as to one defendant and leave undisturbed the verdict in favor of another defendant. See Harnischfeger Corporation v. Harris, 280 Ala. 93, 190 So.2d 286 (1966).

The issue presented on appeal is whether the trial court's jury instructions regarding a landowner's duty to an employee of an independent contractor constituted prejudicial error requiring reversal. The jury instructions in dispute are as follows:

"... Now, a landowner or the owner of property owes a duty to the employee or to an employee of an independent contractor to warn of any hidden dangers or latent defects on the property of which the property owner knows and which the independent contractor or his employee does not know, nor such that the independent contractor or employee ought to know....

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anthony Bone v. Elizabeth Delane Taylor
Court of Civil Appeals of Alabama, 2025
South Alabama Brick Co. v. Carwie
214 So. 3d 1169 (Supreme Court of Alabama, 2016)
Roberts v. NASCO EQUIPMENT CO., INC.
986 So. 2d 379 (Supreme Court of Alabama, 2007)
Kinsman v. Unocal Corp.
123 P.3d 931 (California Supreme Court, 2005)
Edmonson v. Cooper Cameron Corp.
374 F. Supp. 2d 1103 (M.D. Alabama, 2005)
Ex Parte Meadowcraft Industries, Inc.
817 So. 2d 702 (Supreme Court of Alabama, 2001)
Meadowcraft Industries, Inc. v. Price
817 So. 2d 697 (Court of Civil Appeals of Alabama, 2000)
Ramirez v. Alabama Power Co.
898 F. Supp. 1537 (M.D. Alabama, 1995)
Pope v. City of Talladega
602 So. 2d 890 (Supreme Court of Alabama, 1992)
Watkins v. United States
789 F. Supp. 1141 (M.D. Alabama, 1992)
Pickett v. United States Steel Corp.
495 So. 2d 572 (Supreme Court of Alabama, 1986)
Chance v. DALLAS COUNTY, ALA.
456 So. 2d 295 (Supreme Court of Alabama, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
423 So. 2d 152, 1982 Ala. LEXIS 3509, Counsel Stack Legal Research, https://law.counselstack.com/opinion/glenn-v-united-states-steel-corp-inc-ala-1982.